7.2.13 Ground Improvement Checklist

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel
7.2.13 Ground Improvement Checklist

Checklist · Part VII · Stabilization Methods

Ground Improvement Checklist

Investigation Phase (Pre-Design)0 of 6
Design Phase0 of 8
Construction Phase0 of 6
Deliverable Phase0 of 5

Levy (2007) describes how a contractor builds a formal Construction Quality Control Plan (CQCP). A qualified CQCP manager owns the plan in the same way a safety director owns the safety program. The plan should include, at a minimum, an organization chart locating the CQCP manager, proposed personnel, designated authorities and their duties, operating procedures for inspections, tests and documentation, a subcontractor and vendor rating system, help in selecting quality-oriented subcontractors, training for field staff, and field inspection report forms.

The core tool is the inspection checklist: a short, numbered list of the quality points for one work type, signed and dated by the inspector. Levy’s concrete placement checklist, for example, runs from approved shop drawings on site and the correct strength ordered, through form and rebar approval, testing requirements (slump, number of cylinders, temperature), vibration, curing, and hot- or cold-weather protection. Similar lists can be prepared for every trade with help from an engineer or a qualified subcontractor. Checklists serve as a guide for less experienced supervisors and also signal that quality matters; copies can be given to the subcontractor to document compliance or deficiencies.

His inspection tips: check quality on every walkthrough and at least weekly; notify the subcontractor promptly of unacceptable work and set a date for correction, then verify it; if poor work continues, bring the subcontractor’s owner or the manufacturer’s representative to the site and confirm the meeting in writing; and walk the work for a punch list before a subcontractor demobilizes.

For railroad work: Ground improvement under or beside track lends itself to this method because acceptance depends on records produced as the work is done. A checklist for each technique (stone columns, jet grouting, compaction grouting, deep soil mixing, PVDs, geosynthetic placement) might cover approved submittal and mix design on site, layout against track stationing and clearance envelopes, installation parameters logged per element (depth, pressure, volume, time), spoil and heave observations, track surface monitoring during work near live track, sampling and testing frequency, and nonconformance actions. Signed checklists, combined with the element logs, give the railroad a defensible basis for accepting work that cannot be seen once it is installed.

Source: Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill, pp. 220–227. Summarized and paraphrased. Full reference under Supplemental References.

Ticks are saved in this browser.
Plain text version

Investigation Phase (Pre-Design)

  • [ ] Confirm soft layer depth, thickness, and lateral extent from boring/CPTu data
  • [ ] Obtain c_v and c_h from consolidation tests and/or piezocone dissipation tests
  • [ ] Measure s_u profile (VST or CPTu N_kt method) to determine staged loading feasibility
  • [ ] Test sulfate content (ASTM D4327) at all sites where lime or cement stabilization is planned
  • [ ] Evaluate sensitivity (S_t = s_u / s_u,remolded) to assess disturbance risk from installation
  • [ ] Confirm access constraints (setback from track, overhead clearance, crane swing radius)

Design Phase

  • [ ] Select improvement method by owner railroad requirements and schedule constraint
  • [ ] For PVDs: compute d_e, μ (full formulation), T_r required; verify drain discharge capacity q_w
  • [ ] For stone columns: compute a_s, n₀ (Priebe); verify composite bearing capacity
  • [ ] For DSM: select binder type; set the laboratory q_u target ≥ 4× the field design q_u (f_lab = 0.25)
  • [ ] For lime/cement: run laboratory trial mixes at 4%, 6%, 8% binder; confirm target PI or q_u
  • [ ] For geosynthetics: verify AOS criterion for filtration; specify permittivity per AASHTO M 288 and the owner's specification
  • [ ] Prepare staged loading schedule with FS_slope ≥ 1.3 at each stage (see Chapter 6.3)
  • [ ] Define performance monitoring instrumentation plan (type, location, frequency, trigger levels)

Construction Phase

  • [ ] Verify mandrel type and size (PVD); document mandrel dimensions for smear zone estimate
  • [ ] Confirm as-installed drain/column locations vs. design grid; document deviations > 6 in.
  • [ ] Monitor piezometer responses and compare to predicted dissipation curves during wait period
  • [ ] Perform QC strength/bearing tests (Table 7.2-3 criteria) after improvement and before loading
  • [ ] Document any anomalous grout takes (grouting), column refusals (stone columns), or auger torque spikes (DSM)
  • [ ] Maintain vibration monitoring log for all activities within client exclusion zone

Deliverable Phase

  • [ ] Include improvement design calculation in GDR appendix (PVD spacing, stone column a_s/n₀, etc.)
  • [ ] Provide as-built drain/column layout plan
  • [ ] Provide performance monitoring data summary (piezometer, settlement plate, strength tests)
  • [ ] Compare post-improvement performance to design targets; note any deficiencies
  • [ ] Transmit monitoring data to client's infrastructure management system in required format
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-14 Undrained shear strength from CPT SᵤUse: Fine-grained soils penetrated undrained (Ic > ~2.6). Limits: Nkt depends on reference test (vane, CIUC, DSS) and plasticity; calibrate locally. Use Nkt toward upper end for conservative Su.
  • IS-20 Hydraulic conductivity from CPT kUse: Naturally deposited soils; first-order profiling of k with depth. Limits: Order-of-magnitude only (±1 log cycle). Not for man-made fills; prefer CPTu dissipation t50 or field pumping tests for design.