7.2.2 Compaction Methods

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel
7.2.2 Compaction Methods
7.2.2.1 Proctor Compaction Fundamentals

The relationship between dry unit weight and moisture content is defined by the Proctor test. The maximum dry unit weight γ_d,max and optimum moisture content w_opt are the design targets for compaction control (Chapter 5.3).

Understanding Soil Behavior — Compaction
Understanding Soil Behavior — Compaction
Soil Compaction
Soil Compaction
Vibrocompaction process
Vibrocompaction process
Sand compaction pile construction, Hollister CA
Sand compaction pile construction, Hollister CA
Blast densification — casing placement
Blast densification — casing placement

Zero Air Voids (ZAV) line:

γZAV = Gs ⋅ γw1 + w ⋅ Gs    (pcf)

Where G_s = specific gravity (≈ 2.70 for most soils); γ_w = 62.4 pcf; w = water content (decimal).

Relative compaction (RC):

RC = γd,fieldγd,max × 100%

Standard Proctor (ASTM D698): 12,400 ft·lb/ft³ compactive effort; appropriate for light to moderate railroad facility construction. Modified Proctor (ASTM D1557): 56,000 ft·lb/ft³ compactive effort; commonly specified for intermodal yards, bridge approach fills and railroad embankments.

Standard Proctor Test
Standard Proctor Test
Inputs for the equations in this section (2)
SymbolWhat it isComes fromHow to get itTypical range
Gsspecific gravity (≈ 2.70 for most soils)Lab testSpecific gravity of solids (ASTM D854). 2.65–2.70 is usually adequate for mineral soils when untested.2.64–2.80 mineral; lower if organic · by USCS group
wwater content (decimal).Lab testOven-dry water content of samples (ASTM D2216); field check by microwave (D4643) or nuclear gauge (D6938).gravels/sands 3–25%, clays 15–70% · by USCS group
7.2.2.2 Vibratory Compaction

Vibratory compaction (smooth drum, padfoot) densifies granular fills and coarse-grained subgrades. Compaction effectiveness is described by the influence depth Z_eff:

Withdrawal of vibratory probe
Withdrawal of vibratory probe
Zeff = k √WAf    (ft)

Where W = drum weight (lb); A_f = drum contact area (ft²); k = empirical constant (0.08–0.12 for granular materials).

Lift thickness limits by soil type:

  • Granular (GW, GP, SW): 12–18 in. uncompacted
  • Silty/clayey soils (SM, SC, ML, CL): 8–12 in. uncompacted
  • Heavy clay (CH): 6–8 in. uncompacted (padfoot drum required)
Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
Wdrum weight (lb)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Afdrum contact area (ft²)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
kempirical constant (0.08–0.12 for granular materials).Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
7.2.2.3 Dynamic Compaction

Dynamic compaction densifies loose fills and granular soils by repeated high-energy drops of a heavy pounder (10,000–30,000 lb) from heights of 30–90 ft.

Dynamic compaction crater inspection
Dynamic compaction crater inspection
High-energy impact roller
High-energy impact roller
Dynamic Compaction
Dynamic Compaction

Influence depth (Menard & Broise 1975):

D = n √Wh ⋅ H    (m)

Where (metric, as published; multiply D by 3.28 for feet):

  • W_h = weight of pounder (metric tons)
  • H = drop height (m)
  • n = empirical efficiency factor (0.35–0.65; 0.50 typical for saturated granular soil)

Energy per unit area:

E = ndrops ⋅ Wh ⋅ HAgrid    (ton·ft/ft²)

For railroad applications, dynamic compaction is restricted to areas beyond client setback from active track (Table 7.2-1). Vibration monitoring (Chapter 5.3) with a peak particle velocity (PPV) threshold of 0.5 in./s at the nearest track is commonly required.

Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
Whweight of pounder (tons)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Hdrop height (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
nempirical efficiency factor (0.35–0.65Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
Supplemental reference

What densification can realistically achieve

Table 17-S2. Upper-bound test values after deep dynamic compaction (GEC 13, Table 4-2, from FHWA 1986)

Soil typeSPT N (blows/ft)CPT qc (tsf)PMT limit pressure (tsf)
Pervious coarse-grained: sands and gravel30–50200–30020–25
Semipervious: sandy silts25–35135–17714.6–20
Semipervious: silts and clayey silts20–35104–13510.4–14.6
Partially saturated impervious: clay fill, mine spoil20–40*N/A14.6–20
Landfills15–40*N/A5.2–10.4

* Higher values may reflect large particles. These are maxima for estimating what is possible; verify actual improvement by testing while the equipment is still on site, and allow for delayed improvement as pore pressures dissipate.

Rapid impact compaction (RIC) is a smaller-footprint alternative where the setbacks in Table 7.2-1 rule out a crane and pounder. A 5–9 ton weight on an excavator drops about 4 ft onto a 5-ft-diameter tamper at 40–60 blows/min. It densifies granular fills, ash and building waste to about 10–20+ ft and covers about 9,000–30,000 ft2 per shift. Groundwater should be at least 3 ft below the surface. It is not recommended for weak, low-permeability, clayey or high-fines soils. Energy and set per blow are recorded for QC, with SPT or CPT before and after for QA. Recorded peak noise was about 88 dBA. The depth of compaction cannot be controlled precisely.

Dynamic compaction — crane and tamper
Dynamic compaction — crane and tamper
Blast densification — surface expression
Blast densification — surface expression
Rapid Impact Compaction — First Pass
Rapid Impact Compaction — First Pass
Rapid Impact Compaction — Hammer and Anvil Foot
Rapid Impact Compaction — Hammer and Anvil Foot
Rapid Impact Compaction in Progress
Rapid Impact Compaction in Progress

Jet grouting diameters reported by SHRP2 range from about 3 to 15 ft (larger than the 1.5–5 ft in Section 7.2.6.3, which reflects smaller systems). Depths are generally under 100 ft but exceed 160 ft in some cases. Soilcrete strength reflects the soil (higher in sands and gravels). Highly plastic clays and fibrous peat erode poorly and are not recommended. Spoil must be removed continuously, and surface or lateral movement must be watched — an important check beneath or next to track.

Source: Schaefer, V. R. et al. (2017). Ground Modification Methods Reference Manual, Vol. I. Geotechnical Engineering Circular No. 13, FHWA-NHI-16-027 · SHRP2 R02 / GeoTechTools (2012). Rapid Impact Compaction and Jet Grouting fact sheets

Technology sheets for this method · see 7.2.16 Technology Library

Large crane and 14.0 Mg tamper for dynamic compaction
Photo 7.2.2-1. Large crane and 14.0 Mg (30.9 kips) tamper for dynamic compaction. From Elias et al. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
13.6 Mg tamper and crater formed during dynamic compaction
Photo 7.2.2-2. 13.6 Mg (30.0 kips) tamper and crater formed during dynamic compaction. From Elias et al. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Hammer and anvil portion of a rapid impact compactor
Photo 7.2.2-3. Hammer and anvil portion of rapid impact compactor. Courtesy of Peter Becker.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rapid impact compactor following the first pass of compaction points, with craters visible in the ground
Photo 7.2.2-4. Rapid impact compactor following first pass of compaction points. Courtesy of Peter Becker.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rapid impact compactor in the process of compaction, tamper foot engaged with the ground
Photo 7.2.2-5. Rapid impact compactor in the process of compaction. Courtesy of Peter Becker.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

Case study: 7.2.17.1 Measuring roller force with pile-driving monitors (Look 2023), in §17.17 Case Studies.

CIR deceleration data map during initial IR passes
Photo 7.2.2-6. Initial passes Credit: photographer not stated in the source.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
CIR deceleration data map after 40 IR passes
Photo 7.2.2-7. After 40 IR passesSource: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Broons BH-1300 four-sided impact roller towed by a four-wheel drive tractor
Photo 7.2.2-8. Broons (BH-1300) four-sided ("square") impact roller towed using a four-wheel drive heavy tractor. Photograph from http://www.broons.com/impact/Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Impactor 2000 square impact roller in the field
Photo 7.2.2-9. Impactor 2000 "square" impact roller. Credit: photographer not stated in the source.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Landpac 25-kJ three-sided impact roller in operation
Photo 7.2.2-10. Landpac 25-kJ three-sided impact roller. Photograph from www.landpac.co.za, courtesy of Land Pac®.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Labeled diagram of vibratory compaction equipment: a crane-mounted mast lowers a vibrator and probe into the ground, connected to a control unit, powerpack, and
Photo 7.2.2-11. Main elements of vibratory compaction equipment. After Massarsch and Fellenius (2005).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Grain size distribution chart with four zones A, B, C, and D bounded by percent passing versus grain size, showing the range of soil gradations suitable for vib
Photo 7.2.2-12. Range of soil types treated by vibrocompaction. Elias et al. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Three-panel line diagram showing the generic vibrocompaction process: probe penetration, backfill addition, and probe withdrawal with densified soil column
Photo 7.2.2-13. Generic vibrocompaction process. Figure courtesy of FHWA, Elias et al. (2006).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Crane-suspended probe-type vibrator being lowered into the ground at a vibrocompaction site
Photo 7.2.2-14. Probe-type vibrator being lowered into the ground. Credit: photographer not stated in the source.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Vibroflotation equipment and crane operating on a large sand island construction site, Palm Island, Dubai
Photo 7.2.2-15. Vibroflotation (vibrocompaction) at Palm Island, Dubai. Credit: photographer not stated in the source.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
7.2.2.4 Compaction Control and Lime-Treated Fill: Lessons from UK Practice

Method and end-product specification

UK earthworks specifications control compaction in two ways. A method specification fixes the plant, layer thickness and number of passes for each material class, with daily records of what was done. An end-product specification sets a minimum compacted state that is tested in place; a layer should not be covered until it has been shown to comply (Dumelow, 2012, Section 75.5, pp. 1119–1133). AREMA and most railroad specifications are end-product (percent of maximum dry density at a moisture range), so the testing frequency and the hold on covering a layer are what make them work.

Table 7.2-12. Rapid field acceptability tests for cohesive fill used in UK practice
TestTimeTypical acceptable limitConstraint
Moisture Condition Value (MCV)About 15 min8 to 16Must be correlated with fundamental tests for each material; weak for granular or very silty or sandy soils
Hand shear vaneAbout 1 minOver about 1,460 psf (70 kPa)Not suitable for clay with much sand or gravel

Dumelow (2012), p. 1133. Shear strength converted from kPa.

Lime treatment: the size of the clods matters

Bender-element tests on a clayey soil treated with 3% lime and compacted to a dry density of about 100 pcf (1.60 Mg/m³) found (Tang, Vu and Cui, 2011, pp. 35–44):

  • Lime raised the small-strain stiffness sharply; about 200 hours after treatment the stiffness no longer depended on the moulding water content.
  • The larger the maximum clod size (0.016 to 0.2 in., 0.4 to 5 mm, in the tests), the lower the stiffness. Field clods can be inches across, so laboratory specimens prepared from finely ground soil overstate field stiffness.
  • Wetting–drying cycles cut the stiffness of untreated specimens through microcracking but changed treated specimens little; only drying well below the initial water content cracked the treated soil.

For lime-treated subgrade and fill, specify pulverisation (Section 7.2.7), prepare laboratory mixes at the field clod size, and protect the treated layer from drying out before it is covered.

Sources

Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.

  • Dumelow, P. G. (2012). Earthworks material specification, compaction and control. Chapter 75 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1115–1142Find source ↗Library entry
  • Tang, A. M., Vu, M. N. and Cui, Y.-J. (2011). Effects of the maximum soil aggregates size and cyclic wetting–drying on the stiffness of a lime-treated clayey soil. Géotechnique 61(5); reprinted in Partial Saturation in Compacted Soils, pp. 35–44Find source ↗
Supplemental reference · Lu, Filz and Han (2009)

Dynamic Compaction of Dumped Rock-and-Soil Fill

A building pad in mountainous terrain sat on 6.5 to 26 ft of weathered rock and soil that had been end-dumped without compaction two years earlier. Most particles were 0.2 to 8 in., with some over 20 in., and the fill carried only about 1,500 to 2,100 psf. Treatment used two high-energy passes of about 2,200 kip-ft per drop, followed by two lighter ironing passes of about 1,100 and 740 kip-ft.

  • Plate load tests after treatment gave an ultimate bearing pressure above 9,000 psf and a secant modulus of about 5,000 psi.
  • Sand cone tests and ground-penetrating radar both showed improvement to at least 20 ft, with relative compaction above 95%.
  • The strip footings built on the treated fill settled little and stabilized quickly.

For railroad work: Old side-cast and end-dumped fills of rock and soil are common along mountain grades and at abandoned yards. The case shows that coarse, boulder-bearing fill can be brought to a reliable bearing surface by dynamic compaction where vibration limits allow it, and that GPR is a practical way to confirm the depth of improvement. Keep the vibration limits of Section 7.2.2.3 for any work near live track, signals and structures.

Source: Lu, Filz and Han (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Yan, Dong and Chu (2009)

Explosive Replacement of Soft Clay with Crushed Stone

Explosives are best known in ground improvement for densifying loose saturated sand (see the blasting densification sheet in Section 7.2.16). This paper describes a different use: explosive replacement. Crushed stone is stockpiled beside the area to be treated, charges are set in the soft clay in a planned pattern, and the blast opens cavities into which the stockpile slides. Charge weight and spacing were set from blast-cavity equations.

  • On a highway project the stone was densely packed in the top 16 to 20 ft, but in the bottom 10 to 13 ft it was mixed into the clay.
  • Ground-penetrating radar located the dense stone layer reliably.

For railroad work: Explosive replacement is a remote-site option for building a new alignment across a shallow soft clay or organic deposit where excavation and replacement would be slow. It is not suited near operating track or structures. Expect incomplete replacement at the base of the deposit and verify with borings and GPR.

Source: Yan, Dong and Chu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Singh and Hymavathi (n.d.)

Dynamic Replacement and Rotational Dynamic Compaction

Dynamic replacement uses heavy tamping to drive large pillars of imported granular material into soft saturated soil. The craters are filled with stone or sand and pounded again, forming columns that both reinforce the soil and drain it. The soil between the pillars is compressed, and the excess pore pressure this creates takes hours to dissipate, so passes are spaced in time. Rotational dynamic compaction drops a tamper that also rotates as it falls; in comparative trials it penetrated about twice as far as a conventional tamper and gave higher cone resistance, increasing the depth of improvement in granular soils.

For railroad work: Both methods produce strong ground vibration and crater heave, so the setback from active track (Table 7.2-1) and the vibration limits for dynamic compaction in Section 7.2.2 apply. Dynamic replacement suits yard and access road areas on soft ground away from operating track, where its columns also speed consolidation.

Source: Singh and Hymavathi (n.d.). Full reference under Supplemental References.

Supplemental reference · Blasting

Explosive Methods Near Track: Which Limits Apply

Two explosive ground improvement methods appear in this chapter. Blast densification of loose saturated sand is described in the technology sheet in Section 7.2.16. Explosive replacement of soft clay is described in the box above. Both deliberately cause strong vibration and, for blast densification, temporary liquefaction of the treated layer.

For railroad work: Treat either method as blasting, not as ground improvement vibration. The same controls apply as for rock excavation blasting:
(1) the scaled-distance or monitored-PPV limits of Section 5.3.27;
(2) a seismograph at the nearest track, structure and signal equipment;
(3) the 0.5 in./s at-rail threshold in this section.
Liquefaction of the treated layer can spread to untreated loose ground beyond the treatment area, so keep these methods well clear of operating track. Use them for new alignments and yards on greenfield ground, and confirm the result by CPT several weeks after treatment, when strength gain has occurred.

Source: 30 CFR 816.61–816.68. Full reference under S23.

← Previous · 7.0 Design Chapter 7.1 — Retaining Structures
Next · 7.0 Design → Chapter 7.3 — Pavement Subgrade Evaluation