7.2.8 Geosynthetic Reinforcement

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel
7.2.8 Geosynthetic Reinforcement
7.2.8.1 Geotextile Filtration and Separation

Geotextiles placed at subgrade/subballast and subgrade/subbase interfaces prevent fines migration (filtration) and maintain aggregate performance (separation). Key design criteria:

Apparent Opening Size (AOS) criterion:

AOS ≤ D85,soil    (retention criterion)

Permeability criterion:

kgeotextile ≥ ksoil    (permittivity criterion)

AASHTO M 288 sets a minimum permittivity of 0.02 s⁻¹ for separation geotextiles. Check the owner railroad's specification (AREMA MRE Chapter 1) for track applications.

Geotextiles and geomembranes under track: what the field record shows

Use a geotextile for what it can do.

  • It is poor at reinforcement. It needs large stretch to work, creeps, slips against ballast, and its openings enlarge as it stretches. Use geogrid for reinforcement.
  • Its main role is separation, with filtration of seepage and in-plane drainage as secondary roles.
  • It does not shed water from above.

Requirements.

  • Only nonwoven fabrics are acceptable.
  • AOS < D85 of the protected soil. For a gap-graded soil, base this on the fines fraction. For new ballast over an undercut surface, use the gradation of the fouling material and ignore the ballast-size particles.
  • High tensile, puncture, elongation, abrasion, chemical and UV resistance.
  • Proven resistance to clogging, and a thick mat where transmissivity is needed.

Nonwovens fine enough for silt, and especially clay, may not exist.

Placement.

  • At least 12 in. below the tie bottom, out of reach of tamping tines and undercutter chains.
  • On a smooth surface sloped to drain, with no equipment running on the fabric and minimal UV exposure.
  • Never in double layers, which create a slip plane.

Durability record.

  • On a Class I railroad, fabric permeability fell 92% and transmissivity 85% within 15 months. Tensile strength fell 54% within 48 months.
  • At an AAR site near Caldwell, Texas, a clogged low-permittivity fabric trapped water, causing excess pore pressure and subgrade failure. It was believed to be the cause of a derailment.

“Undercut and add fabric” repairs often fail because the mud was not coming from the subgrade, or because the subgrade fines were too fine for the fabric. The book’s process is: diagnose the cause in the field and lab; compare geotextile and non-geotextile options; do an economic analysis; run a field trial; monitor and document. Only a properly graded, durable granular layer gives permanent separation and filtration (Chapter 2.3, §3.5.4).

Geomembranes. Uses:

  • Blocking surface infiltration. Place the membrane between sand layers at least 2–4 in. thick, never against ballast, and drain the water off its top.
  • Keeping expansive soil from drying.
  • Cutting capillary rise in frost-susceptible embankments.
  • Forming a cut-off below the water table in cuts.
Figure 7.2-24. EPS blocks being placed.
Figure 7.2-24. EPS blocks being placed.

Hazards: water trapped beneath the membrane creates a slip surface, and holes or leaky seams concentrate flow and erode soil, which is worse than having no membrane. Most leaks are at seams, so require seam testing. A bitumen emulsion sprayed into a sand or subballast layer, which can be done behind an undercutter, is a cheaper alternative with the same trapped-water risk.

After Selig & Waters (1994), ch. 12. Full reference under Supplemental References.

7.2.8.2 Geogrid Reinforcement

Biaxial geogrids (ASTM D6637) placed at subgrade/subbase interface improve load distribution and reduce differential settlement. The Giroud-Han (2004) method for granular layer thickness over weak subgrade:

Geogrid placement on subgrade
Geogrid placement on subgrade

The method gives the required base thickness h from the wheel load P, the tire contact radius r, the subgrade CBR, the number of axle passes N, the allowable rut depth, the base-to-subgrade modulus ratio and, for geogrids, the aperture stability modulus J. Its bearing capacity factor N_c is 3.14 without reinforcement, 5.14 with a geotextile and 5.71 with a geogrid, so the reinforcement benefit is largest on weak subgrade. Use the published equation or a calculator that implements it; for an intermodal reach stacker take the actual tire load and contact area.

For preliminary design, the simplified California chart method (USACE TM 5-818-8) is also acceptable when subgrade CBR and geogrid type are known.

Inputs for the equations in this section (7)
SymbolWhat it isComes fromHow to get itTypical range
hintermediate value computed on this pageAnother equationComputed: h = P / (A_p ⋅ p_s) - 1 K_R ⋅ (1 + ε ⋅ h/√ A_p )    (iterative; ft)project-specific
Pwheel load per wheel (lb)Loading criteriaFrom the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications.project-specific
Apcontact area per wheel (in.²)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.≈ 100 in.²
psallowable subgrade stress = 3.2 × s_u for non-reinforcedDesign criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.project-specific
TBRtraffic benefit ratio (1.5–3.0 for biaxial geogrid)Product dataManufacturer's data sheet for the specified product, confirmed by project QA testing.project-specific
KRload distribution factor (depends on h, A_p, and layer modular ratio)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
suundrained shear strengthLab or field testLab: UU triaxial (ASTM D2850) or unconfined compression (D2166). Field: vane shear (D2573), CPT su = (qt − σv)/Nkt, or pocket penetrometer/Torvane for screening.soft 250–500, stiff 1,000–2,000 psf · by USCS group
7.2.8.3 Geosynthetic-Reinforced Load Transfer Platform (GRLT)

Over piled foundations or column-supported embankments (stone columns, rigid inclusions), a Geosynthetic-Reinforced Load Transfer Platform (GRLT) distributes track loads to column heads. GRLT design follows BS 8006:2010 or FHWA-HRT-17-097 (Giroud-Han approach):

Geosynthetic-reinforced haul road
Geosynthetic-reinforced haul road

Membrane tension in geosynthetic over column caps:

Fill placement tensioning geosynthetic
Fill placement tensioning geosynthetic
Tgeosynthetic = WT ⋅ s28 ⋅ δallow    (lb/ft)    (catenary approximation)

Where W_T = net soil weight transferred to geosynthetic (psf); s = clear span between column caps (ft); δ_allow = allowable sag (ft); typically δ ≤ s/30 for railroad applications.

Inputs for the equations in this section (3)
SymbolWhat it isComes fromHow to get itTypical range
WTnet soil weight transferred to geosynthetic (psf)Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
sclear span between column caps (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
δallowallowable deflection (in.)Design criterionSet by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification.typically δ ≤ s/30 for railroad applications
Base geosynthetic layer over columns
Base geosynthetic layer over columns

Geotextiles in railway subgrades

  • Types: woven (two perpendicular fiber sets, strongly anisotropic) and non-woven (random fibers, isotropic); polypropylene or polyester; 0.016–0.12 in. thick; 2.1–10 oz/yd².
  • Functions: separation of granular layers, reinforcement of weak soil, filtration and drainage, and some frost protection. Most railway installations are simply separators between subballast and subgrade.
  • Placement: under the subballast, never directly under ballast. A geotextile does not spread load, so it must not be used as a reason to reduce ballast or subballast thickness. Railways that did so saw puncture of the fabric and loss of the crossfall.
  • Benefit: a finite-element study found about a 10% reduction in stress at the top of subgrade (Figure 7.2-12). Maintenance savings were reported to repay the geotextile cost quickly.
  • Acceptance: verify tensile strength, elongation at failure, puncture and compressive strength, permeability and filtration against the soil before use. Filter criteria are in Chapter 2.3, §2.3.8.
Geotextile placement, Kansas DOT
Geotextile placement, Kansas DOT
Geotextile Design for Coastal Protection
Geotextile Design for Coastal Protection
Geotextile Filter Design
Geotextile Filter Design
Geosynthetic placement
Geosynthetic placement
Select fill placement over geosynthetic
Select fill placement over geosynthetic
Figure 7.2-12. Finite-element mesh for assessing the reinforcing effect of a geotextile in a railway subgrade. Profillidis Fig. 9.20.
Figure 7.2-12. Finite-element mesh for assessing the reinforcing effect of a geotextile in a railway subgrade. Profillidis Fig. 9.20.

After Profillidis (2014), §9.15, Fig. 9.20. Full reference under Supplemental References.

Geosynthetics, HMA underlayment and EPS: case histories

Geogrid can be placed before laying track or during out-of-face work with an undercutting chain. A hot-mix asphalt layer between 12 in. of ballast and 6 in. of compacted sub ballast spreads load and sheds water to the sides.

Figure 7.2-18. Geogrid reinforcement under the ties or by undercutting chain.
Figure 7.2-18. Geogrid reinforcement under the ties or by undercutting chain.
Figure 7.2-19. HMA underlayment between ballast and sub ballast, shedding water to the sides.
Figure 7.2-19. HMA underlayment between ballast and sub ballast, shedding water to the sides.
  • Prairie main line: subgrade fines contaminated the ballast. Finger tests confirmed plastic fines, and bearing calculations sized the fix: excavate, place full-width woven geotextile, and backfill with clean granular fill.
  • Quebec swamp crossing: decomposed corduroy and organic soil pumped mud. The fix was a shear-key trench along the shoulder backfilled with clean ballast (ideally with nonwoven geotextile), shoulders regraded to drain, and the trench left to drain ballast pockets toward the clay below.
  • Ontario main line: woven geotextile placed beneath a lifted track panel at night within a possession window.
  • EPS lightweight fill (about $670/m³, or about $19/ft³, in 2016 dollars; about $600/m³ in 2012) reduces load on soft ground, but it can float in a flood unless ballasted and drained.
Geotextile Selection — Woven vs Nonwoven
Geotextile Selection — Woven vs Nonwoven
Figure 7.2-20. Full-width woven geotextile on a prairie main line.
Figure 7.2-20. Full-width woven geotextile on a prairie main line.
Figure 7.2-21. Organic mud pumping through ballast at a Quebec swamp crossing.
Figure 7.2-21. Organic mud pumping through ballast at a Quebec swamp crossing.
Figure 7.2-22. Track panel lifted for geotextile placement on an Ontario main line.
Figure 7.2-22. Track panel lifted for geotextile placement on an Ontario main line.
Figure 7.2-23. EPS block fill mass over soft foundation soil.
Figure 7.2-23. EPS block fill mass over soft foundation soil.

After Geotechnology for Railroaders Program, Module 6.2; §03–05. Full reference under Supplemental References.

Geotextile handling under track

  • Limit sunlight exposure to 7 days from removal of the shipping cover to final placement.
  • Keep equipment off geotextile until it has at least 6 in. of sub-ballast or ballast cover.
  • Overlap at least 3 ft in both the longitudinal and transverse directions.
  • Direct surface drainage away from placed fabric to prevent contamination.

Inspection checks are in Chapter 5.3, Table 15-S1.

After UFC 4-860-01FA (2004), ch. 9, §4b. Full reference under Supplemental References.

Case study: 7.2.17.4 Working platform at the edge of a creek, designed for slope stability (Look 2023), in §17.17 Case Studies.

Supplemental reference · Chen, Chen, Wang and Xu (2009)

Column-Supported Embankments: Arching Height and Which Design Method to Trust

Field measurements on an instrumented column-supported embankment confirmed soil arching in the fill and allowed four design approaches to be compared.

  • Arching developed fully once the fill height was at least 1.1 to 1.5 times the clear spacing between column caps.
  • Where the columns floated in the soft layer, the soil below the column tips contributed 50% to 60% of the total settlement.
  • BS 8006 predicted the share of load carried by the columns poorly, and the German EBGEO method predicted much higher values than were measured. The Nordic guideline and the authors’ closed-form method, which includes negative skin friction on the columns, agreed with the measurements.

For railroad work: Keep the embankment above the full-arching height everywhere, including at the low ends of bridge approaches. If the columns do not reach a firm layer, compute the settlement of the soil beneath the column tips explicitly. Check the load share with more than one method; the design procedure in the column-supported embankment sheet (Section 7.2.16) is the starting point.

Source: Chen, Chen, Wang and Xu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Filz and Plaut (2009)

Geosynthetic over Column Caps: Where It Strains Most

Three kinds of numerical analysis of the geosynthetic layer over column caps all showed that strain peaks at the corners of square caps and at the edges of round caps.

  • Peak strain is smaller with round caps than with square caps at the same area replacement ratio.
  • With square caps, strain is smaller when the strands run parallel to the diagonals of the column layout than when they run parallel to the rows.
  • Deflection and strain increase as the vertical load on the geosynthetic increases, and as the area replacement ratio, the stiffness of the soil between columns and the geosynthetic stiffness decrease.

For railroad work: Where a load transfer platform (Section 7.2.8.3) carries track, specify round caps where practical, or orient biaxial reinforcement diagonally to square caps, to reduce peak strain and long-term creep of the reinforcement.

Source: Filz and Plaut (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Han and Bhandari (2009)

Column-Supported Embankments Under Repeated Loading

Most studies of geosynthetic-reinforced, column-supported embankments use static loads, but railroad embankments carry repeated loads. A discrete element model of the fill over pile caps was loaded cyclically.

  • Permanent strain accumulated in the fill with each cycle. The geogrid-reinforced embankment deformed about 25% less than the unreinforced one.
  • Reinforcement increased the share of load carried by the piles, and that share stayed nearly constant through the cycles.
  • Tension in the geogrid kept increasing as it deformed with each cycle, and its distribution between caps depended on the geogrid’s bending stiffness as well as the fill and foundation properties.

For railroad work: Static design methods do not capture the growth of reinforcement tension and fill deformation under train loading. For column-supported track, keep the load transfer platform well above the full-arching height, allow for reinforcement tension growth with load cycles, and monitor track settlement through the first months of traffic (Chapter 3.8, Section 3.8.9).

Source: Han and Bhandari (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Zheng and Liu (2009)

Lateral Behavior of Embankment Columns: Where They Break

Three-dimensional analyses of piled embankments loaded to failure divided the ground under and beside the embankment into three zones:

  • An extension-bending zone under the crest, where columns are pulled and bent.
  • A shear zone under the side slope, where deflections and bending moments are largest and unreinforced columns are most likely to break in bending.
  • A compression-bending zone beyond the toe, where columns are least affected.

For columns without steel reinforcement, bending failure is more critical than shear failure. Stability analyses that credit the full shear strength of every column therefore overstate the factor of safety.

For railroad work: For embankment widenings and approach fills on columns, check the columns under the side slope for bending, consider reinforced or composite columns in the outer rows, and do not credit unreinforced column shear strength in the slope stability analysis without checking bending (Chapter 6.3).

Source: Zheng and Liu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Liu, Chen and Liu (2009); Miao, Wang, Zhang and Zhang (2009)

Large-Diameter Concrete Pipe Piles and Controlled Modulus Columns

Cast-in-place concrete pipe piles. A thin-walled concrete pipe about 3.3 ft in outside diameter with a 4-in. wall is cast in place between vibro-driven casings. Field trials for a highway embankment found:

  • Concrete slump should be 2.4 to 3.5 in.
  • Install piles from the center of the area outward.
  • Short controlled pauses while casting prevent gaps in the wall, but pauses longer than about 20 seconds sharply increase concrete use.
  • Integrity and load testing methods used for drilled shafts apply.

Controlled modulus columns. Model tests showed that the share of load carried by the columns is sensitive to the stiffness of the load plate above them, so the stiffness of the cushion or load transfer layer can be used to control total and differential settlement.

For railroad work: Both are alternatives to driven piles for bridge approach embankments. Whatever the column type, the stiffness of the cushion or load transfer platform is a design variable, not just a working surface.

Source: Liu, Chen and Liu (2009); Miao, Wang, Zhang and Zhang (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Huang and Li (2009); Liu, Xie, Shi and Zhu (2009)

Mixed Long and Short, Rigid and Flexible Columns

  • Long, relatively rigid piles control total and differential settlement; short piles mainly raise bearing capacity of the upper soft soil. For the same maximum settlement, a mixed long-and-short layout needs less total pile length than uniform piles.
  • Pile caps raise the share of load carried by the piles. There is an optimum cap coverage that minimizes total and differential settlement.
  • With rigid and flexible piles together, lengthening the rigid piles reduces settlement more effectively than stiffening the flexible ones.
  • The stiffness of the cushion over the piles controls how load is shared among rigid piles, flexible piles and soil.

For railroad work: For long approach embankments, a layout that varies column length with fill height and with depth to firm soil can save cost over a uniform grid. Check differential settlement where the layout changes (Chapter 6.2).

Source: Huang and Li (2009); Liu, Xie, Shi and Zhu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Liao, Ye and Xu (2009)

Geogrid Pullout: Bearing on the Cross Ribs Does Most of the Work

Pullout tests on biaxial geogrid in sand separated the two parts of pullout resistance: friction along the longitudinal ribs and passive (bearing) resistance against the transverse ribs.

  • Both grow with pullout displacement and soften after their peaks.
  • Passive resistance on the transverse ribs was the main contributor, but its share decreased as the normal stress increased.

For railroad work: Pullout capacity of geogrid in reinforced platforms and walls depends on intact transverse ribs and good fill around them. Use the manufacturer’s tested interaction coefficients for the actual fill (Chapter 7.1), and protect the grid from installation damage that would cut the cross ribs.

Source: Liao, Ye and Xu (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.