Thermal methods change the ground by removing or adding heat. Artificial ground freezing turns pore water into ice, giving the soil very high temporary strength and making it nearly watertight within hours to weeks. Heat treatment bakes clay at several hundred degrees and changes it permanently. Freezing is a specialist but established method; heat treatment is mostly of historical interest because of its fuel use (Hausmann 1990).
Freezing works in almost any soil or rock with enough pore water, which sets it apart from grouting. It fails where groundwater flows fast enough to carry heat in faster than the pipes remove it, so seepage velocity must be checked (pumping tests, Chapter 2.8) before freezing is chosen.
Frozen soil is a four-phase material: solids, ice, unfrozen water and air. Some water stays unfrozen well below 32°F, especially in clay and in salty pore water, and this unfrozen water explains why frozen-soil strength and stiffness depend so strongly on temperature. Artificial freezing runs much colder (−4°F to −256°F) than natural frost, and the ice lenses form parallel to the freeze pipes rather than to the ground surface.
| Material | qu (psi) | qu (tsf) |
|---|---|---|
| Pure ice | 220 | 16 |
| Frozen sand | 1,450 | 104 |
| Frozen silt | 580 | 42 |
| Frozen clay | 290 | 21 |
Water expands about 9% when it freezes. Saturated fine-grained soils under low confining stress can heave much more than that, because water migrates to the freezing front and builds ice lenses. When the ground thaws, the ice lenses melt and the soil consolidates, so settlement can follow. Thaw also returns the soil to, or below, its original strength: freezing is a temporary support, not a permanent improvement.
| Circulating brine | Liquid nitrogen (LN2) | |
|---|---|---|
| Coolant | Calcium chloride brine in a closed loop; lowest theoretical temperature −67°F | Liquid nitrogen vented to the air after passing through the pipes, or injected into porous soil; −321°F |
| Time to freeze | Days to weeks, depending on soil, water content, brine temperature and pipe spacing (typically about 2 to 4.5 ft) | Hours; suited to emergencies and active seepage |
| Quantity | Refrigeration plant runs continuously | About 1,000 to 3,200 lb of LN2 per yd³ of soil for initial freezing (about 1,350 lb/yd³ for preliminary estimates); the same quantity again maintains the frozen state for about 2 to 3 weeks |
| Other | Lower cost for long jobs. A pipe leak releases brine that can thaw the frozen zone and contaminate groundwater | Higher frozen strength allows thinner walls and less ice-lens heave; requires closer control and monitoring; the gas is not toxic but displaces oxygen in confined spaces |
Heat to remove. The latent heat of the pore water dominates: L = 144 γd w Btu/ft³ (Eq. 7.2-1), where γd is the dry unit weight (pcf), w the water content (decimal) and 144 Btu/lb the heat of fusion of water. A soil with γd = 100 pcf and w = 0.25 needs about 3,600 Btu/ft³ of latent heat alone, plus the sensible heat to cool it.
Freeze wall for a circular shaft. The simplest (elastic, Lamé) estimate of the thickness of a frozen ring around an opening of radius a under lateral earth and water pressure p0 is d = a [ (qu / (qu − 2 p0))0.5 − 1 ] (Eq. 7.2-2), with qu chosen for the design temperature, strain and duration. More advanced elastic-plastic and creep formulas exist; a specialty contractor normally designs the freeze.
Monitoring. Thermocouples or temperature probes in the frozen zone and on the coolant lines; survey and inclinometers for heave and creep movement. Ultrasonic measurements can sometimes confirm frozen thickness.
Heating clay above about 750°F (400°C) causes permanent mineral changes: the clay loses lattice water, plasticity drops and strength and durability rise. Past methods used moving surface furnaces for roads and burners in boreholes to stabilize embankments and waste deposits; each borehole treated a zone about 3 ft in radius. Fuel use is high, about 10 to 20 gallons of fuel oil per cubic yard of soil, so the method is rarely economical today except where the ground already contains fuel or waste.
For railroad work: Freezing is most likely on a railroad project as support for a jacked, bored or mined crossing under the track through running sand or silt below the water table, or to cut off seepage in a deep excavation beside the track where dewatering would cause settlement (Section 7.1.17). The frozen zone heaves as it forms and settles as it thaws, and both move the track: keep the frozen zone below the track structure where possible, set track geometry and settlement monitoring with action levels and slow orders for both the freezing and the thaw periods, and plan for thaw consolidation after the crossing is complete. Brine leaks under the track can thaw the wall locally, so ask how leaks are detected and isolated. Confirm the groundwater velocity before relying on freezing, and coordinate with utilities in the right-of-way, which can be damaged by frost heave or act as heat sources.
Source: Hausmann (1990), Chapter 15. Full reference under Supplemental References.