7.2.4 Stone Columns

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel
7.2.4 Stone Columns
7.2.4.1 Priebe Method for Composite Modulus

Stone columns (vibro-replacement) improve soft cohesive subgrades by inserting dense granular columns (typically 24–36 in. diameter) on a regular grid. The Priebe (1995) method computes an improvement factor n₀ based on area replacement ratio A_c/A:

Stone column construction with vibro rigs
Stone column construction with vibro rigs
Crane-suspended vibroflot and stone backfill
Crane-suspended vibroflot and stone backfill
Vibro concrete column installation
Vibro concrete column installation

Area replacement ratio:

as = AcA = π Dc2 / 4scol2    (square grid)

Where D_c = column diameter (ft); s_col = column spacing (ft).

Basic improvement factor (Priebe 1995):

n0 = 1 + as [ (1/2 + f) / (Kac ⋅ f) − 1 ],   f = (1 − νs)(1 − as) / (1 − 2νs + as)

For ν_s = 1/3, with column friction angle φ'_col = 40° and K_ac = tan²(45° − 20°) = 0.217, this reduces to:

n0 = 1 + as [ (5 − as) / (4 Kac (1 − as)) − 1 ]

Composite settlement reduction:

SimprovedSuntreated = 1n0

Composite modulus:

Ecomposite = EsoilSimproved/Suntreated = n0 ⋅ Esoil
Inputs for the equations in this section (6)
SymbolWhat it isComes fromHow to get itTypical range
asintermediate value computed on this pageAnother equationComputed: a_s = A_c A = π D_c^2 / 4 s_col^2    (square grid)project-specific
Dccolumn diameter (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
scolcolumn spacing (ft).Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
n0intermediate value computed on this pageAnother equationComputed: n_0 = 1 + a_s [ 1 a_s K_a ⋅ (1 - a_s)(1 - 2ν_s) 1 - ν_s - 1]^-1project-specific
Ecompositesoil elastic modulus = E_soil S_improved/S_untreated = n_0 ⋅ E_soilField test, lab test or correlationPressuremeter (ASTM D4719), DMT (D6635), plate load (D1196), triaxial secant modulus, or correlation with N60 or qc.loose sand 200–500, dense sand 1,000–1,700 ksf · by USCS group
φ'effective friction angleLab test (or correlation)Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08).sands 30–42°, clays 17–32° · by USCS group
Geotextile-encased sand column installation
Geotextile-encased sand column installation
7.2.4.2 Load-Carrying Capacity of Stone Column Group

The bearing capacity of the composite improved ground beneath a loaded area is:

Kentledge load test on improved ground
Kentledge load test on improved ground
qult,composite = as ⋅ qult,col + (1 - as) ⋅ qult,soil

Where q_ult,col = bearing capacity of stone column material (typically 8–15 tsf); q_ult,soil = undrained bearing capacity of surrounding clay (N_c × s_u; typically 1–3 tsf).

Table 7.2-3: Stone Column Design Parameters — Railroad Applications
ApplicationD_c (in.)Spacing (ft)a_sn₀ (Priebe)Settlement Reductionφ'_col (°)
Track subgrade support247.50.0571.6–1.844–56%38–42
Intermodal yard (light)308.00.0771.8–2.245–55%40
Bridge abutment366.00.1962.5–3.560–71%40–42
Crane runway (RTG)365.00.2833.0–4.067–75%42
Surcharge preload zone249.00.0401.4–1.638–44%38

Rammed aggregate piers through a slip surface

Stone columns and rammed aggregate piers installed on a triangular grid through a shallow-to-medium failure plane create a composite of native soil and dense columns that carries load and resists shear better than either alone.

Stone column construction by dry bottom feed process
Photo 7.2.4-1. Stone column construction by dry bottom feed process. Photograph courtesy of James Mitchell.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Load test on a stone column
Photo 7.2.4-2. Load test on a stone column. Photograph courtesy of James Mitchell.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Construction of stone column by wet top feed method
Photo 7.2.4-3. Construction of stone column by wet top feed method. Photograph courtesy of James Mitchell.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Stone column construction in soft soil
Photo 7.2.4-4. Stone column construction in soft soil. Photograph courtesy of James Mitchell.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rammed aggregate pier construction
Photo 7.2.4-5. Rammed aggregate pier construction. Photograph courtesy of GeoStructures, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rammed aggregate pier tamper
Photo 7.2.4-6. Rammed aggregate pier tamper. Photograph courtesy of GeoStructures, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Pre-drilling of hole for rammed aggregate pier installation
Photo 7.2.4-7. Pre-drilling of hole for rammed aggregate pier installation. Photograph courtesy of GeoStructures, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Rammed aggregate pier tamper foot
Rammed aggregate pier tamper foot
Aggregate pier drilling with auger
Aggregate pier drilling with auger
Figure 7.2-15. Slope stabilization with rammed aggregate piers on a triangular grid.
Figure 7.2-15. Slope stabilization with rammed aggregate piers on a triangular grid.

After Geotechnology for Railroaders Program, Module 6.1; §07. Full reference under Supplemental References.

Supplemental reference · Rollins, Quimby, Johnson and Price (2009)

Stone Columns in Silty Sand: Add Wick Drains and Watch the Clay Content

Side-by-side test areas compared vibro stone columns installed with and without prefabricated vertical drains in silty sands and sandy silts.

  • With drains, the average SPT (N1)60 rose about 114% in a zone averaging about 30% fines, but only about 70% where fines averaged 43%.
  • Without drains the improvement was much smaller.
  • Where the soil contained 15% or more clay-size particles, improvement was minimal even with drains.
  • Blow counts continued to rise for some time after treatment where drains were used, but not where they were omitted, so verification testing done too soon understates the result.

For railroad work: For liquefaction mitigation under bridge approaches and embankments in silty ground, specify wick drains between the stone columns, screen each layer for clay-size content before selecting the method, and schedule acceptance SPTs or CPTs a few weeks after installation. Where clay-size content reaches 15%, consider deep soil mixing or a column-supported embankment instead (Chapter 6.5).

Source: Rollins, Quimby, Johnson and Price (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Zhou, Chen and Chen (2009)

Shear Wave Velocity as the Acceptance Target for Liquefaction Treatment

The authors link cyclic resistance to shear wave velocity and shear wave velocity to void ratio for sandy soils. For a given earthquake magnitude, the velocity needed to resist liquefaction sets a target void ratio, which can then be converted into stone column diameter and spacing for square or triangular patterns. On a vibro stone column project, surface-wave (SASW) testing before and after treatment agreed well with SPT-based evaluations.

For railroad work: A velocity target suits long corridor treatments because surface-wave and MASW testing can cover the treated length quickly between borings (Chapter 5.1, Sections 5.1.6 and 5.1.0). Use it alongside SPT or CPT acceptance, not instead of it, and test after any time-dependent strength gain.

Source: Zhou, Chen and Chen (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.

Supplemental reference · Shao (2009)

Stone Columns for Liquefaction, Soil-Mix Columns for Heavy Loads

A large commercial building site combined two methods: vibro stone columns to densify and drain loose sand layers that would liquefy in the design earthquake, and deep soil mixing columns to carry heavy building column loads past soft clay. CPTs before and after treatment confirmed the liquefaction mitigation. Numerical (FLAC) analysis set the soil-mix column depth, and full-scale load tests on column groups matched the prediction. The facility performed without distress for more than seven years.

For railroad work: Mixed treatments work well where one problem is liquefaction and another is settlement under concentrated loads, such as intermodal crane runways or heavy equipment pads in seismic areas. Size each method for the problem it solves, and prove the column groups with load tests before production.

Source: Shao (2009), in Han, J. et al. (eds.) (2009), Advances in Ground Improvement, ASCE GSP 188. Full reference under Supplemental References.