Miller describes the precedence diagramming method (PDM), in which boxes are activities and arrows are relationships. PDM allows four link types: finish-to-start (F-S), start-to-start (S-S), finish-to-finish (F-F) and start-to-finish (S-F). He considers F-S sufficient for almost every real situation and warns that the other three are seldom needed. A lag is a delay placed on a link. It is appropriate only for a true waiting period that uses no resources and is outside the manager’s control, such as shipping time. It should not be used to hide work, and because most software does not draw lags on the network, they show up only in the dates.
Two further points apply to duration estimates. First, the most common network flaw is building logic around limited resources; logic should assume unlimited resources, with resource conflicts resolved later during scheduling. Second, subject-matter experts usually estimate workload (hours of effort for an average performer), not duration. Duration is workload divided by the effective workday, the hours per day actually available to the activity: 48 hours ÷ 6 hours per day = 8 days. Where an estimate is uncertain, Miller uses a PERT weighted average, (optimistic + 4 × most likely + pessimistic) ÷ 6; with 6, 10 and 20 days the result is about 11 days.
For railroad work:
Source: Miller, D. P. (2009). Building a Project Work Breakdown Structure: Visualizing Objectives, Deliverables, Activities, and Schedules. ESI International Project Management Series. Boca Raton, FL: Auerbach Publications (CRC Press, Taylor & Francis Group), pp. 72–75, 105–109. Summarized and paraphrased. Full reference under Supplemental References.
Kelly, Male and Graham recommend weighting and scoring when several technically feasible options compete and none is clearly best. The first step is to agree on the criteria. Correlated criteria should be avoided because they count the same attribute twice; their example is that ease of cleaning and cost of cleaning should not both be used. Weights then come from a paired comparison. Each criterion is compared with every other, the more important of each pair is recorded, and each criterion’s number of “wins” becomes its weight. Each option is scored 1–5 against each criterion. Score is multiplied by weight and the products are summed. Sensitivity checks, made by changing a few weights and scores, show whether the ranking is robust.

Their worked example compares internal partitions for a building that is reorganized every two to six years. Eight criteria (demountability, noise attenuation, finish, support of fittings, concealing services, capital cost, maintenance cost and reliability of supply) received weights of 4, 6, 3, 0, 5, 3, 4 and 3. Stud-and-board partitions totaled 109 and plastered blockwork 104, while the proprietary systems scored 76–91, mainly because noise attenuation carried the highest weight. The authors say the result should prompt a second look rather than be accepted mechanically. Any preferred option must still be technically feasible, economically viable, functionally suitable and acceptable to the client.
For railroad work: The method suits ground improvement and subgrade remediation choices, such as undercut-and-replace versus geogrid-reinforced subballast versus lime or cement stabilization versus deep soil mixing. Typical criteria are track outage required, ability to work from the track or the right-of-way, settlement performance under the design traffic in MGT, construction risk in the expected soils, capital cost, maintenance demand and supply-chain or contractor availability. Derive the weights with the railroad’s engineering and operations staff in the room, because operations typically values outage time very differently from engineering. Keep capital cost as one weighted criterion, or compare it separately on a whole-life basis, and show the sensitivity run in the report so the choice can be audited.
Source: Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell Science, pp. 75–77, 308–310. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
The ASCE Committee on Specifications defines two basic types of specification.
A performance specification has three requirements:
The guide compares the two types as follows:
Prescriptive specifications fit where the end result cannot be fully defined or where loss of design control is unacceptable. Performance specifications fit where end-result specification is normal practice, or where the contractor’s ingenuity is wanted. The two can be combined, as with concrete specified by both strength and mix limits, but they must not conflict on the same product or activity.
For “or equal” clauses, list the salient characteristics that will be used to judge equality. Read every reference standard before citing it, because standards contain options and may conflict with one another. Do not over-specify. Each tighter quality level or tolerance adds cost.
For railroad work: Ground improvement suits a performance or hybrid approach, because specialty contractors own the equipment and know-how. A deep soil mixing or grouting GSP for an embankment or subgrade might specify:
Avoid also fixing the binder dosage and mixing energy unless the railroad accepts responsibility for the result. Stone columns and PVDs are often specified prescriptively (spacing, length, material). In that case acceptance should be based on installation records, and settlement performance should not be made a separate contractual guarantee unless the design responsibility is transferred clearly.
Source: ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers, pp. 14–22. Summarized and paraphrased. Full reference under Supplemental References.
Sullivan et al. use breakeven analysis when the choice between two alternatives turns mainly on one uncertain factor. Write the equivalent worth (PW or annual worth) of each alternative as a function of that factor, set the two expressions equal, and solve for the factor. If the best estimate of the factor lies above the breakeven value, one alternative wins; if below, the other does. The method works the same way for a single project: set its equivalent worth to zero and solve for the factor.
Factors commonly tested this way are annual expenses, interest rate, service life, and hours of use. In their examples, a hybrid car beats a conventional car only above a fuel price of $3.64/gal. Three motors trade places at 1,694 and 4,389 operating hours per year. In each case the analysis gives the decision-maker one number to argue about instead of a whole cash-flow table.
For railroad work: the classic case is ground improvement or undercutting compared with continued spot maintenance at a chronic soft subgrade or mud spot. The uncertain factor is how many maintenance interventions a year the location really needs. Each intervention includes surfacing, ballast, flagging, and the train-delay cost of the slow order that follows. As an illustration only, with inputs chosen for the example:
If track inspection records show the spot being surfaced six times a year, the fix is justified. If it is surfaced twice a year, it is not, unless safety risk or capacity value changes the picture. Two other breakeven tests are useful: the service life the improvement must achieve, and the first cost at which it stops paying. Present these breakeven values to the client rather than a single net present worth, because they show plainly which input the decision depends on. They also show which records to check, such as maintenance-of-way work orders and slow-order logs.
Source: Sullivan, W. G., Wicks, E. M. and Koelling, C. P. (2015). Engineering Economy, 16th ed. Upper Saddle River, NJ: Pearson, pp. 476–482. Summarized and paraphrased. Full reference under Supplemental References.
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.