↑ Parent Menu⌂ Main Menu
← Chapter 7.2 Ground Improvement Methods
GHRM
Railway Ground Hazard Risk Management · 7.0 · Design
Sections · click a car to open it

Supplemental References

Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel
Supplemental References

Material in the green “Supplemental reference” boxes throughout this chapter was added from the following documents in the LEVI geotechnical library. Text is summarized or paraphrased; tables are reproduced with their original source noted; figures are reproduced from the cited document for internal reference use. Consult the original document before relying on a value for design. Blocks marked “After UFC 4-860-01FA (2004)” draw on item S10 and are rewritten for railroad clients. Blocks marked “After Selig & Waters (1994)” summarize item S11 for railroad clients; tables are condensed from the book and its figures are not reproduced. The Case Studies section summarizes case studies from item S12 by Burt G. Look; its figures are reproduced from the book for internal reference use, and the closing “For railroad work” note in each case study is added by the authors of this manual. Blocks tagged “Project management” summarize methods, examples and figures from the project-management, estimating and construction-management books listed here, applied to railroad work; the closing “For railroad work” note in each block is added by the authors of this manual.

  1. Blacklock, J. R. and Lawson, C. H. (1977). Handbook for Railroad Track Stabilization Using Lime Slurry Pressure Injection. FRA/ORD-77/30, Federal Railroad AdministrationFind source ↗Library entry
  2. Pengelly, A. D. Injection for Railroad Subgrades. Hayward Baker, Inc. (scanned; text recovered by OCR)Find source ↗
  3. Hayward Baker, Inc. Railroad Subgrade Stabilization (brochure)Find source ↗
  4. National Lime Association (2004). Lime-Treated Soil Construction Manual: Lime Stabilization & Lime Modification, Bulletin 326Find source ↗
  5. SHRP2 R02 / GeoTechTools (2012). Column-Supported Embankments — fact sheet, design guidance and photographsFind source ↗
  6. SHRP2 R02 / GeoTechTools (2012). Rapid Impact Compaction and Jet Grouting fact sheetsFind source ↗
  7. Schaefer, V. R. et al. (2017). Ground Modification Methods Reference Manual, Vol. I. Geotechnical Engineering Circular No. 13, FHWA-NHI-16-027Find source ↗
  8. Profillidis, V. A. (2014). Railway Management and Engineering, 4th ed. Farnham, UK: Ashgate. Chapters 7–9, 11–13, 16–17, 20 and 22 (track system, mechanical behavior of track, subgrade, sleepers, ballast, transverse effects, maintenance, slab track, electrification foundations, safety)Find source ↗Library entry
  9. Geotechnology for Railroaders Program, Modules 1–8 (two-day training course reference: risk management, geology and soils, ballast and sub ballast, drainage, slides, slope and subgrade stabilization, scour, rock falls, beaver dams, winter problems, spring thaw, extreme weather, earthquakes). Field photographs and figures from the course; slope stabilization process slides adapted from material by D. ColwellFind source ↗
  10. U.S. Army Corps of Engineers, Naval Facilities Engineering Command and Air Force Civil Engineer Support Agency (2004). UFC 4-860-01FA, Railroad Design and Rehabilitation. Unified Facilities Criteria, 16 January 2004 (supersedes TI 850-02, 1 March 2000); approved for public release, distribution unlimited. Used on this page: ch. 6 (§8) and ch. 9 (§4)Find source ↗Library entry
  11. Selig, E. T. and Waters, J. M. (1994). Track Geotechnology and Substructure Management. London: Thomas Telford. Used on this page: chs. 11 and 12Find source ↗Library entry
  12. Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. Leiden: CRC Press/Balkema (Taylor & Francis). ISBN 978-1-032-10470-6. Case studies used on this page: §7.10, §12.6, §12.7, §12.8Find source ↗Library entry
  13. Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., and Segner, R. O., Jr. (2015). Construction Project Management: A Practical Guide to Field Construction Management, 6th ed. Hoboken, NJ: John Wiley & Sons. Used on this page for project-management materialFind source ↗
  14. Bull, J. W. (ed.) (2015). Life Cycle Costing for the Analysis, Management and Maintenance of Civil Engineering Infrastructure. Dunbeath, Scotland: Whittles Publishing. Used on this page for project-management materialFind source ↗
  15. Miller, D. P. (2009). Building a Project Work Breakdown Structure: Visualizing Objectives, Deliverables, Activities, and Schedules. ESI International Project Management Series. Boca Raton, FL: Auerbach Publications (CRC Press, Taylor & Francis Group). Used on this page for project-management materialFind source ↗
  16. Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell Science. Used on this page for project-management materialFind source ↗
  17. ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers. Used on this page for project-management materialFind source ↗
  18. Sullivan, W. G., Wicks, E. M. and Koelling, C. P. (2015). Engineering Economy, 16th ed. Upper Saddle River, NJ: Pearson. Used on this page for project-management materialFind source ↗
  19. Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill. Used on this page for project-management materialFind source ↗
  20. Han, J., Zheng, G., Schaefer, V. R. and Huang, M. (eds.) (2009). Advances in Ground Improvement: Research to Practice in the United States and China. Proceedings of the US–China Workshop on Ground Improvement Technologies, Orlando, Florida. ASCE Geotechnical Special Publication 188. Reston, VA: ASCE. Used on this page: Sections 7.2.2 to 7.2.8 and 7.2.18Find source ↗
  21. Hausmann, M. R. (1990). Engineering Principles of Ground Modification. New York: McGraw-Hill. Used on this page: Section 7.2.19Find source ↗
  22. Singh, K. and Hymavathi, J. (n.d.). Lecture Notes on Ground Improvement Techniques (A60127). Hyderabad: Institute of Aeronautical Engineering, Department of Civil Engineering. Used on this page: Sections 7.2.2, 7.2.6 and 7.2.7 (dynamic replacement, compensation grouting, lime columns)Find source ↗
  23. U.S. Office of Surface Mining Reclamation and Enforcement. 30 CFR 816.61–816.68, Use of Explosives (airblast limits 816.67(b); ground vibration limits, scaled distance and blasting-level chart 816.67(d)). Used on this page: Section 7.2.2Open source ↗

Photograph credits

The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.

  1. Photo 7.2.2-1 — Large crane and 14.0 Mg (30.9 kips) tamper for dynamic compaction. From Elias et al. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  2. Photo 7.2.2-2 — 13.6 Mg (30.0 kips) tamper and crater formed during dynamic compaction. From Elias et al. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  3. Photo 7.2.2-3 — Hammer and anvil portion of rapid impact compactor. Courtesy of Peter Becker. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  4. Photo 7.2.2-4 — Rapid impact compactor following first pass of compaction points. Courtesy of Peter Becker. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  5. Photo 7.2.2-5 — Rapid impact compactor in the process of compaction. Courtesy of Peter Becker. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  6. Photo 7.2.2-6 — Initial passes Photographer not stated in the source. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  7. Photo 7.2.2-7 — After 40 IR passes Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  8. Photo 7.2.2-8 — Broons (BH-1300) four-sided ("square") impact roller towed using a four-wheel drive heavy tractor. Photograph from http://www.broons.com/impact/ Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  9. Photo 7.2.2-9 — Impactor 2000 "square" impact roller. Photographer not stated in the source. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  10. Photo 7.2.2-10 — Landpac 25-kJ three-sided impact roller. Photograph from www.landpac.co.za, courtesy of Land Pac®. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  11. Photo 7.2.2-11 — Main elements of vibratory compaction equipment. After Massarsch and Fellenius (2005). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  12. Photo 7.2.2-12 — Range of soil types treated by vibrocompaction. Elias et al. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  13. Photo 7.2.2-13 — Generic vibrocompaction process. Figure courtesy of FHWA, Elias et al. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  14. Photo 7.2.2-14 — Probe-type vibrator being lowered into the ground. Photographer not stated in the source. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  15. Photo 7.2.2-15 — Vibroflotation (vibrocompaction) at Palm Island, Dubai. Photographer not stated in the source. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  16. Photo 7.2.3-1 — Placing the Anchor on the Drain. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  17. Photo 7.2.3-2 — Inserting the Mandrel into the Ground. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  18. Photo 7.2.3-3 — Inserting the Drain Core within the Jacket to Maintain Continuity. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  19. Photo 7.2.3-4 — Stapling the Drain Splice. (Photograph from www.cofra.nl, courtesy of Geotechnics B.V.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  20. Photo 7.2.3-5 — Schematic of a Generic PVD Installation for a Highway Embankment, showing the surcharge, drainage blanket, wick drains, and monitoring instrumentation (deep settlement points, settlement platform, groundwater observation well, inclinometer, and piezometers). (Figure from Elias et al. 2006) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  21. Photo 7.2.4-1 — Stone column construction by dry bottom feed process. Photograph courtesy of James Mitchell. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  22. Photo 7.2.4-2 — Load test on a stone column. Photograph courtesy of James Mitchell. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  23. Photo 7.2.4-3 — Construction of stone column by wet top feed method. Photograph courtesy of James Mitchell. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  24. Photo 7.2.4-4 — Stone column construction in soft soil. Photograph courtesy of James Mitchell. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  25. Photo 7.2.4-5 — Rammed aggregate pier construction. Photograph courtesy of GeoStructures, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  26. Photo 7.2.4-6 — Rammed aggregate pier tamper. Photograph courtesy of GeoStructures, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  27. Photo 7.2.4-7 — Pre-drilling of hole for rammed aggregate pier installation. Photograph courtesy of GeoStructures, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  28. Photo 7.2.5-1 — CSV installation adjacent to a sheet pile wall. From the files of Jim Collin. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  29. Photo 7.2.5-2 — Top view of the CSV auger and cement hopper. From the files of Jim Collin. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  30. Photo 7.2.5-3 — Deep mixing rig on levee project in New Orleans, LA. From Trevi Icos Corporation. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  31. Photo 7.2.5-4 — Batch plant and deep mixing rig. From Trevi Icos Corporation. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  32. Photo 7.2.5-5 — Close-up view of mixing. From Trevi Icos Corporation. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  33. Photo 7.2.5-6 — Exposed top of deep mixing columns. From Fudo Construction. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  34. Photo 7.2.5-7 — Exposed sides of deep mixing columns. From George Filz (2010). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  35. Photo 7.2.6-1 — Jet grouting process schematic. Photograph courtesy of Hayward Baker, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  36. Photo 7.2.6-2 — Multiple jet grouting rigs. Photograph courtesy of Soilmec S.p.A. (2006). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  37. Photo 7.2.6-3 — Drilling to place grout pipes. Courtesy of Hayward Baker, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  38. Photo 7.2.6-4 — Example of improvement of soil under an existing structure. From Munfakh (1991). Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  39. Photo 7.2.6-5 — Example of chemical grouting underpinning of a structure to allow excavation without settlement of the foundation. Courtesy of Hayward Baker, Inc. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  40. Photo 7.2.7-1 — Compaction of chemical stabilized soil. Photograph courtesy of Carmeuse Lime & Stone, from carmeusena.com. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  41. Photo 7.2.7-2 — Mixing of chemical stabilized soil. Photograph courtesy of Carmeuse Lime & Stone, from carmeusena.com. This same photograph is also used as the Fact Sheet document's cover image. Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  42. Photo 7.2.16-1 — Overview of bio-treatment soil improvement systems, showing how biogeochemistry (the chemical reaction network and biological system) and soil habitat interact to alter mechanical properties, with process monitoring guiding up-scaling toward field application. (Adapted from DeJong et al. 2011.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  43. Photo 7.2.16-2 — Overview of possible bio-treatment soil improvement systems applied to a levee cross-section — including bio-reinforcement to prevent erosion, bio-mineralization to stabilize slopes and immobilize carbon, bio-film to prevent groundwater seepage, and bio-dechlorination of contaminants. (Jason DeJong, personal communication, 2012.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  44. Photo 7.2.16-3 — Light microscope photos of (a) untreated sand and (b) sand treated with an iron-based biocement. (Chu et al. 2011; with permission from ASCE.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
← Previous · 7.0 Design Chapter 7.1 — Retaining Structures
Next · 7.0 Design → Chapter 7.3 — Pavement Subgrade Evaluation