Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
Authors: Daniel P. Colwell and Mario Ruel
7.2.17 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S12 under Supplemental References.

Case Study 17.17.1 — Measuring roller force with pile-driving monitors
Case study · Look (2023) §7.10

Related section: 7.2.2 Compaction Methods

Three trial embankments were built from extremely to slightly weathered rock taken from site cuttings: sandstone, basalt, and interbedded siltstone/sandstone. All of it broke down to meet “soil” specifications during placement and rolling (Look and Lacey, 2017). A 20.6-ton vibrating padfoot and a 19-ton smooth drum roller compacted each fill at field and targeted moisture.

Pile-driving monitors (PDM), which normally record set and energy for each hammer blow, tracked reflectors on the rollers. They measured each pass’s set, vibration frequency, amplitude, peak velocity and acceleration, and so the peak compaction force, which is not the same as static weight. Findings:

  • Dynamic force was well above static weight and changed with material and with each pass as the ground stiffened: about 26–40 tons equivalent for the padfoot and up to 76 tons for the smooth drum on the interbedded fill.
  • Maximum force and best material performance came after five to six passes; beyond that the values cycled and some rebound occurred.
  • Over-compaction broke the material down, which showed both in the force record and later in borehole shear test strengths.

Table 17-LK1. Padfoot roller, manufacturer’s values against PDM measurements (after Look 2023, Table 7.13)

ParameterManufacturerMeasured with PDM, three fills
Vibration frequency29 Hz high amp., 31 Hz low27.2–30.9 Hz (range)
Roller speed0–7 mphmedian 2.8 mph
Amplitude0.071 in. high, 0.047 in. lowmedians 0.055–0.087 in.
Force71 kips high amp., 52 kips lowmedians 53–83 kips

For railroad work: a pass-count specification without a check of the roller’s actual output can over-work weathered-rock fill. A trial embankment with measured rebound is a sound way to set the pass count for a large rail embankment.

Measured dynamic force of a 20.6-ton padfoot and a 19-ton smooth drum roller on three trial embankments.
Figure 17-LK1. Measured dynamic force of a 20.6-ton padfoot and a 19-ton smooth drum roller on three trial embankments. Source: Look (2023), Figure 7.10-3, p. 235.
Induced compaction (mm in the original figure; 25.4 mm = 1 in.) with each pass on the interbedded trial; rebound appears at about 5–6 passes.
Figure 17-LK2. Induced compaction (mm in the original figure; 25.4 mm = 1 in.) with each pass on the interbedded trial; rebound appears at about 5–6 passes. Source: Look (2023), Figure 7.10-5, p. 237.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §7.10, pp. 232–236. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 17.17.2 — Wick-drain rigs on dredged sand over 104 psf clay: four ways to size the platform
Case study · Look (2023) §12.7

Related section: 7.2.3 Prefabricated Vertical Drains (PVDs) with Staged Loading

At the Port of Brisbane reclamation, wick-drain rigs had to work for nine months on 31 acres of dredged sand, about 8.2 ft thick, over Holocene clay with a design undrained strength of 104 psf in the top 20 ft (Look and Honeyfield, 2016). Mud waves during filling left the sand thickness uncertain. BR470 is outside its range here, both for clay under 420 psf and for platform thickness to load width (D/W) above 1.5; it was used for the preliminary design for want of anything better.

Loads. The heaviest rig did not exert the highest pressure: the 50-ton CAT on narrower tracks produced 3,500 psf against 2,030 psf for the 89-ton machine. Check every rig.

Parameters. 27 LFWD tests, 8 DCPs and 4 borehole shear tests gave the sand properties. Two proof-roll passes raised the LFWD modulus by about 20% and reduced its scatter (10th percentile 4,400 psi rolled against 3,260 psi unrolled). Groundwater was found at 6.2–10 ft, not the 20 in. assumed. Clay directly under the sand measured 42–380 psf.

Four answers.

  • BR470 deterministic: 7.5 ft required.
  • BR470 with a PERT distribution and Latin Hypercube simulation: baseline 7 ft; 7.5 ft has under 5% probability of being exceeded. Subgrade strength dominates the tornado chart.
  • Finite element displacement, calibrated to proof-roll ruts, with a 3 in limit: 6.9 ft.
  • Finite element stress at the sand/clay interface against a lower-bound bearing factor Nc = 3.14 for combined shear, as mud waves imply: 7 ft.

Proof rolling as the check. A loaded proof truck will bog rather than topple, while an eccentrically loaded rig can topple, so the truck is the safer test. Proof rolling only means something with a defined vehicle and an acceptance deflection. A rock-filled truck loaded more evenly than a water truck (whose load sloshes) and was preferred. Mean ruts were 3.7 in. after one pass and 5.2 in. after two, and 4.7 in was adopted as the acceptance criterion.

Table 17-LK2. Wick-drain rigs and track pressures (after Look 2023, Table 12.20)

RigWeight (tons)Track width (ft)Critical track pressure
Komatsu excavator6532,700 psf
CAT excavator5033,500 psf
Komatsu excavator894.32,030 psf

For railroad work: ground improvement under new embankments on soft soil, such as wick drains for a yard expansion or a new grade across a marsh, puts the rigs on exactly this kind of platform. Size it by more than one method and calibrate the proof roll before the rigs move on.

Issues considered for the platform: load, rig type, parameters, thickness, groundwater and methodology (Look and Honeyfield 2016).
Figure 17-LK3. Issues considered for the platform: load, rig type, parameters, thickness, groundwater and methodology (Look and Honeyfield 2016). Source: Look (2023), Figure 12.7-1, p. 437.
Measuring proof-roll rut depth; LFWD tests were run in and away from the wheel path (Look and Honeyfield 2016).
Figure 17-LK4. Measuring proof-roll rut depth; LFWD tests were run in and away from the wheel path (Look and Honeyfield 2016). Source: Look (2023), Figure 12.7-8, p. 445.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §12.7, pp. 432–446. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 17.17.3 — Lime-treated local soil in a reinforced slope: choosing by total internalised cost
Case study · Look (2023) §12.8

Related section: 7.2.7 Lime and Cement Stabilization

Prolonged rain in 2010/11 triggered a 656 ft landslide under a Sunshine Coast hinterland road, in colluvium up to 20 ft thick below a steep escarpment (Look 2012; Chew et al. 2012; Boyer et al. 2013). Five remediation options were compared on total internalised cost: construction cost plus embodied energy, greenhouse-gas emissions from fuel, transport and materials, and the cost of damage to local roads from heavy trucks hauling material. Environmental costs ranged from 2% to 23% of construction cost.

Options 3 and 4 had the lowest totals. Option 3 was chosen because the road authority wanted the fewest heavy trucks on local roads, and lime treatment let the high-plasticity “unsuitable” colluvium be screened of boulders and reused. With 4% hydrated lime cured seven days, shear box cohesion rose from about 420 psf to 1,250–2,200 psf at a similar friction angle; the design still used a softened cohesion of 104 psf.

The work was done in five stages with soil-nailed temporary slopes, drainage slots and regular inclinometer and survey monitoring. When inclinometer 2 showed excessive movement, inspection found a tree at the crown destabilized by the excavation. Once it was felled, the movement stopped.

Table 17-LK3. Remediation options, 2011 AU$ (after Look 2023, Table 12.23, from Chew et al. 2012)

OptionConstructionEnvironmentalTotal internalised
1. Cast-in-place pile wall with ground anchors*3,300,00067,0003,367,000
2. Rockfill buttress3,800,000628,0004,428,000
3. Reinforced fill slope, lime-treated local soil2,400,000278,0002,678,000
4. Reinforced fill slope, imported granular fill2,000,000452,0002,452,000
5. Earth fill embankment with rock toe3,200,000444,0003,644,000
* Greatest technical uncertainty.

For railroad work: slide repairs on remote lines face the same haul-cost and community questions. Reusing treated local soil cuts truck traffic on rural roads, and staged excavation with inclinometers is the standard of care on an active slide.

Cross section through the 660 ft landslide in up to 20 ft of colluvium (Chew et al. 2012).
Figure 17-LK5. Cross section through the 660 ft landslide in up to 20 ft of colluvium (Chew et al. 2012). Source: Look (2023), Figure 12.8-1, p. 447.
Inclinometer 2 showed excessive movement, traced to a crown tree destabilized by the excavation.
Figure 17-LK6. Inclinometer 2 showed excessive movement, traced to a crown tree destabilized by the excavation. Source: Look (2023), Figure 12.9-3, p. 449.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §12.8, pp. 446–448. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 17.17.4 — Working platform at the edge of a creek, designed for slope stability
Case study · Look (2023) §12.6

Related section: 7.2.8 Geosynthetic Reinforcement

A bridge pier at the edge of a creek, with the next pier 8 ft into it, needed a platform for a BG28 piling rig for a day and an outrigger crane for beam lifting. The temporary-works designer rightly declined to design it with the standard method, since slope stability over soft clay governed. Sheet piling would have cost almost five times the roughly AU$100,000 (2015) platform. Moving the pier about 10 ft would have removed the problem, which shows why constructability belongs in design.

A deep rock-fill replacement moved the critical slip surface deeper, with high-strength geogrids within the rock fill. Stability was checked separately for standing (uniform 3,800 psf, FS 1.5, above the 1.3 usually accepted for temporary works), penetrating (uniform and trapezoidal, FS 1.3) and extracting. The extracting case was the most critical (FS 1.2) even though its 5,500 psf design pressure is lower than penetration’s 6,400 psf, because of where the load sits. Large plate load tests were run but cannot test a deep slip surface, so an excavator was walked along the edge first. The work went without incident, though rig depressions had to be repaired before the outrigger came on.

Table 17-LK4. Design pressures for the BG28 piling rig (after Look 2023, Table 12.19)

OperationDesign pressureFactor of safety adopted
Handling / transporting / standing3,780 psf1.5
Penetration6,390 psf1.3
Extracting5,470 psf1.2 (critical, trapezoidal)

For railroad work: bridge replacement platforms beside streams and next to embankment slopes need a global stability check for each rig operation, not only a bearing check. The extract phase and the outrigger reactions are often the governing cases.

Platform beside the creek, edge checked with an excavator before the piling rig moved on; design section with multiple high-strength geogrids.
Figure 17-LK7. Platform beside the creek, edge checked with an excavator before the piling rig moved on; design section with multiple high-strength geogrids. Source: Look (2023), Figure 12.6-2, p. 433.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §12.6, pp. 430–432. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.