Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S12 under Supplemental References.
Related section: 7.2.2 Compaction Methods
Three trial embankments were built from extremely to slightly weathered rock taken from site cuttings: sandstone, basalt, and interbedded siltstone/sandstone. All of it broke down to meet “soil” specifications during placement and rolling (Look and Lacey, 2017). A 20.6-ton vibrating padfoot and a 19-ton smooth drum roller compacted each fill at field and targeted moisture.
Pile-driving monitors (PDM), which normally record set and energy for each hammer blow, tracked reflectors on the rollers. They measured each pass’s set, vibration frequency, amplitude, peak velocity and acceleration, and so the peak compaction force, which is not the same as static weight. Findings:
Table 17-LK1. Padfoot roller, manufacturer’s values against PDM measurements (after Look 2023, Table 7.13)
| Parameter | Manufacturer | Measured with PDM, three fills |
|---|---|---|
| Vibration frequency | 29 Hz high amp., 31 Hz low | 27.2–30.9 Hz (range) |
| Roller speed | 0–7 mph | median 2.8 mph |
| Amplitude | 0.071 in. high, 0.047 in. low | medians 0.055–0.087 in. |
| Force | 71 kips high amp., 52 kips low | medians 53–83 kips |
For railroad work: a pass-count specification without a check of the roller’s actual output can over-work weathered-rock fill. A trial embankment with measured rebound is a sound way to set the pass count for a large rail embankment.


Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §7.10, pp. 232–236. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Related section: 7.2.3 Prefabricated Vertical Drains (PVDs) with Staged Loading
At the Port of Brisbane reclamation, wick-drain rigs had to work for nine months on 31 acres of dredged sand, about 8.2 ft thick, over Holocene clay with a design undrained strength of 104 psf in the top 20 ft (Look and Honeyfield, 2016). Mud waves during filling left the sand thickness uncertain. BR470 is outside its range here, both for clay under 420 psf and for platform thickness to load width (D/W) above 1.5; it was used for the preliminary design for want of anything better.
Loads. The heaviest rig did not exert the highest pressure: the 50-ton CAT on narrower tracks produced 3,500 psf against 2,030 psf for the 89-ton machine. Check every rig.
Parameters. 27 LFWD tests, 8 DCPs and 4 borehole shear tests gave the sand properties. Two proof-roll passes raised the LFWD modulus by about 20% and reduced its scatter (10th percentile 4,400 psi rolled against 3,260 psi unrolled). Groundwater was found at 6.2–10 ft, not the 20 in. assumed. Clay directly under the sand measured 42–380 psf.
Four answers.
Proof rolling as the check. A loaded proof truck will bog rather than topple, while an eccentrically loaded rig can topple, so the truck is the safer test. Proof rolling only means something with a defined vehicle and an acceptance deflection. A rock-filled truck loaded more evenly than a water truck (whose load sloshes) and was preferred. Mean ruts were 3.7 in. after one pass and 5.2 in. after two, and 4.7 in was adopted as the acceptance criterion.
Table 17-LK2. Wick-drain rigs and track pressures (after Look 2023, Table 12.20)
| Rig | Weight (tons) | Track width (ft) | Critical track pressure |
|---|---|---|---|
| Komatsu excavator | 65 | 3 | 2,700 psf |
| CAT excavator | 50 | 3 | 3,500 psf |
| Komatsu excavator | 89 | 4.3 | 2,030 psf |
For railroad work: ground improvement under new embankments on soft soil, such as wick drains for a yard expansion or a new grade across a marsh, puts the rigs on exactly this kind of platform. Size it by more than one method and calibrate the proof roll before the rigs move on.


Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §12.7, pp. 432–446. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Related section: 7.2.7 Lime and Cement Stabilization
Prolonged rain in 2010/11 triggered a 656 ft landslide under a Sunshine Coast hinterland road, in colluvium up to 20 ft thick below a steep escarpment (Look 2012; Chew et al. 2012; Boyer et al. 2013). Five remediation options were compared on total internalised cost: construction cost plus embodied energy, greenhouse-gas emissions from fuel, transport and materials, and the cost of damage to local roads from heavy trucks hauling material. Environmental costs ranged from 2% to 23% of construction cost.
Options 3 and 4 had the lowest totals. Option 3 was chosen because the road authority wanted the fewest heavy trucks on local roads, and lime treatment let the high-plasticity “unsuitable” colluvium be screened of boulders and reused. With 4% hydrated lime cured seven days, shear box cohesion rose from about 420 psf to 1,250–2,200 psf at a similar friction angle; the design still used a softened cohesion of 104 psf.
The work was done in five stages with soil-nailed temporary slopes, drainage slots and regular inclinometer and survey monitoring. When inclinometer 2 showed excessive movement, inspection found a tree at the crown destabilized by the excavation. Once it was felled, the movement stopped.
Table 17-LK3. Remediation options, 2011 AU$ (after Look 2023, Table 12.23, from Chew et al. 2012)
| Option | Construction | Environmental | Total internalised |
|---|---|---|---|
| 1. Cast-in-place pile wall with ground anchors* | 3,300,000 | 67,000 | 3,367,000 |
| 2. Rockfill buttress | 3,800,000 | 628,000 | 4,428,000 |
| 3. Reinforced fill slope, lime-treated local soil | 2,400,000 | 278,000 | 2,678,000 |
| 4. Reinforced fill slope, imported granular fill | 2,000,000 | 452,000 | 2,452,000 |
| 5. Earth fill embankment with rock toe | 3,200,000 | 444,000 | 3,644,000 |
| * Greatest technical uncertainty. | |||
For railroad work: slide repairs on remote lines face the same haul-cost and community questions. Reusing treated local soil cuts truck traffic on rural roads, and staged excavation with inclinometers is the standard of care on an active slide.


Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §12.8, pp. 446–448. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Related section: 7.2.8 Geosynthetic Reinforcement
A bridge pier at the edge of a creek, with the next pier 8 ft into it, needed a platform for a BG28 piling rig for a day and an outrigger crane for beam lifting. The temporary-works designer rightly declined to design it with the standard method, since slope stability over soft clay governed. Sheet piling would have cost almost five times the roughly AU$100,000 (2015) platform. Moving the pier about 10 ft would have removed the problem, which shows why constructability belongs in design.
A deep rock-fill replacement moved the critical slip surface deeper, with high-strength geogrids within the rock fill. Stability was checked separately for standing (uniform 3,800 psf, FS 1.5, above the 1.3 usually accepted for temporary works), penetrating (uniform and trapezoidal, FS 1.3) and extracting. The extracting case was the most critical (FS 1.2) even though its 5,500 psf design pressure is lower than penetration’s 6,400 psf, because of where the load sits. Large plate load tests were run but cannot test a deep slip surface, so an excavator was walked along the edge first. The work went without incident, though rig depressions had to be repaired before the outrigger came on.
Table 17-LK4. Design pressures for the BG28 piling rig (after Look 2023, Table 12.19)
| Operation | Design pressure | Factor of safety adopted |
|---|---|---|
| Handling / transporting / standing | 3,780 psf | 1.5 |
| Penetration | 6,390 psf | 1.3 |
| Extracting | 5,470 psf | 1.2 (critical, trapezoidal) |
For railroad work: bridge replacement platforms beside streams and next to embankment slopes need a global stability check for each rig operation, not only a bearing check. The extract phase and the outrigger reactions are often the governing cases.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §12.6, pp. 430–432. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.