Ground improvement is a fundamental tool in the railroad geotechnical consultant's toolkit, employed when in-situ subgrade conditions cannot support track, structure, or…
The four examples size the most common ground improvement methods under railroad fills, yards and track: wick drains, stone columns, lime treatment and slurry injection of ballast pockets. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 7.2-1: Wick Drain Spacing for a Staged Embankment
A main line embankment widening on a Class I railroad located in coastal Georgia sits on 30 ft of soft fat clay. The next fill stage can go on only after 90% consolidation, and the schedule allows 120 days. Vertical drainage alone is hopeless at this thickness, so the question is how close the wick drains must be.
Given and required for Example 7.2-1.
Given
Variable
Value
Description
H
30 ft, two-way; Hdr = 15 ft
Soft CH
cv, ch
0.006 and 0.012 ft²/day
dw
0.196 ft
Equivalent drain diameter
Target
U ≥ 90% in 120 days
Required
Vertical degree of consolidation in 120 days
Radial degree needed
Drain spacing that achieves it
Equations
Eq. 4: Tv = cvt/Hdr²; Uv ≈ √(4Tv/π) — vertical
Eq. 5: 1 − U = (1 − Uv)(1 − Ur) — Carrillo
Eq. 1: μ = ln(de/dw) − 0.75 — drain geometry term, no smear or well resistance; de = 1.05s (triangular)
Eq. 2: Ur = 1 − exp(−8Tr/μ); Tr = cht/de² — Barron and Hansbo radial consolidation
de = 2.10; μ = 1.621; Tr = 0.453; t = 0.453 × 4.41 / 0.012
166 days: still too long
↓
Step 5 · s = 1.5 ft
de = 1.575; μ = 1.334; Tr = 0.373; t = 0.373 × 2.48 / 0.012
77 days < 120 days
Spot check: Time scales with de²: halving the spacing cuts the time by about four.
↓
Solution
1.5-ft triangular spacing: about 77 days.
Solution
Wick drains at 1.5-ft triangular spacing reach 90% in about 77 days, inside the 120-day window.
The margin covers part of the effect of smear and well resistance, which are ignored here; check the spacing with the full μ before final design. Install with a static-push mandrel to limit disturbance, and place piezometers at three depths: the next stage goes on when they show 90%, not when the calendar does.
Example 7.2-2: Stone Columns Under a Container Stack
A container laydown area on a Class I railroad located in Port Arthur, Texas, sits on 18 ft of soft fat clay. Four-high stacks would settle about 18 in. Stone columns stiffen the ground; Priebe’s improvement factor says how much, and the column size and spacing are adjusted until the settlement meets the 6-in. target.
Given and required for Example 7.2-2.
Given
Variable
Value
Description
Clay
H = 18 ft; Cc = 0.45; e0 = 1.20; σ′0 = 1,100 psf; su = 450 psf
Untreated settlement is about 18.6 in. Stone columns 36 in. in diameter at 4.5-ft square spacing (n0 = 3.52) bring it to about 5.3 in.
Carry the columns through the full 18 ft of clay, with angular 3/4- to 3-in. stone (φ′ ≥ 40°). Load test production columns (ASTM D1143) at about one per 100, minimum five, and place settlement plates in each quadrant of the stacking area to confirm the performance.
Example 7.2-3: Lime Treatment of a High-Plasticity Clay Subgrade
An access road subgrade on a Class I railroad located near Moose Jaw, Saskatchewan, is fat clay with a PI of 46. Lime lowers the plasticity and builds strength. The first estimate of the lime content uses the PI reduction rule; the design content is then confirmed in the laboratory.
Treated Proctor about 88 pcf at 24%; qu,28 of 90 to 130 psi in trial mixes; lime demand by the Eades-Grim test (ASTM D6276, pH ≥ 12.4)
↓
Step 3 · Specification
7% hydrated lime, 12 in. deep; mellow 24 to 48 hours; 98% Modified Proctor at −2 to +1% of optimum; protect from freezing 3 days
↓
Solution
7% hydrated lime, 12 in. deep.
Solution
Use 7% hydrated lime (ASTM C977) mixed 12 in. deep, mellowed 24 to 48 hours and compacted to 98% of the treated Proctor.
Test the sulfate content of every borrow lot of about 500 yd³. If any lot exceeds about 3,000 ppm, stop and review the treatment under the NLA guidance (Section 7.2.7.1); switching to cement does not avoid sulfate heave. QC: phenolphthalein checks of distribution, PI at 1 and 7 days, and qu at 7 and 28 days (ASTM D2166).
Example 7.2-4: Slurry Quantity to Fill Ballast Pockets
A main line on a Class I railroad located in central Kansas has been surfaced again and again over a soft clay cut. A CPT sounding at the worst low spot shows ballast from about 2 ft to 6 ft below the top of tie. The roadmaster plans railroad-cement injection over 600 ft of track and asks how much slurry and how much dry cement to order, and how many tank loads that is.
Given and required for Example 7.2-4.
Given
Variable
Value
Description
w, t
8 ft, 4 ft
Width and thickness of the ballast pocket zone from the CPT sounding (2 to 6 ft below top of tie)
n
20%
Void space in the pocket zone that slurry replaces (water and voids)
—
7.48 gal/ft³
Unit conversion
c
5 lb/gal
Dry solids per gallon of railroad-cement slurry (specific gravity about 1.4, above the 1.25 minimum)
L
600 ft
Length of track to treat
—
20,000 gal
Slurry tank on the flat car
Required
Slurry per track foot, V
Dry solids per track foot, W, compared with the usual range
Total slurry, total dry solids and tank loads for 600 ft
Equations
Eq. 1: A = w × t — area of the pocket zone, ft² (ft³ per track ft)
Eq. 2: V = n × A × 7.48 — slurry, gal per track ft
Eq. 3: W = V × c — dry solids, lb per track ft
Eq. 4: Totals = V × L and W × L
Steps
Step 1 · Pocket zone (Eq. 1)
A = 8 × 4
32 ft² = 32 ft³ per track ft
↓
Step 2 · Slurry (Eq. 2)
0.20 × 32 = 6.4 ft³; 6.4 × 7.48
V ≈ 48 gal per track ft
↓
Step 3 · Dry solids (Eq. 3)
48 × 5
W = 240 lb per track ft
Spot check: Within the usual 200 to 250 lb per track ft; mild sites take about 150 and severe sites up to 1,000.
↓
Step 4 · Totals (Eq. 4)
48 × 600 = 28,800 gal; 240 × 600 = 144,000 lb
28,800 gal; 72 tons; 28,800 / 20,000 = 1.44, so 2 tank loads
↓
Solution
48 gal and 240 lb per track ft; about 72 tons of dry cement in 2 tank loads.
Solution
Plan on about 48 gal of slurry and 240 lb of dry cement per track foot: 28,800 gal and 72 tons for the 600 ft, mixed in two tank loads.
The 20% void ratio is the weakest number in the calculation. It is assumed from the track geometry and maintenance history, not measured, so order some margin and use 48 gal per track ft as the target in the operator’s daily log. If the takes run well short, tighten the crib spacing or add a staged second pass into the skipped cribs. If they run well over, the pockets are larger than the sounding suggested. Because the cone will not push through set cement, check the result with borings for moisture and strength rather than a repeat CPT.