6.5.5 Cyclic Resistance Ratio from SPT Data

Seismic hazard characterization and liquefaction evaluation are critical components of geotechnical services for railroad infrastructure in seismically active regions.
Authors: Daniel P. Colwell and Mario Ruel
6.5.5 Cyclic Resistance Ratio from SPT Data
6.5.5.1 Fines Content Correction

Compute (N₁)₆₀ using the full correction chain established in Chapter 4.1:

N60 = Nmeas ⋅ Em ⋅ CB ⋅ CR ⋅ CS0.60
CN = √2,117σ'v ≤ 1.7    (Pa = 2,117 psf)
(N1)60 = CN ⋅ N60

For silty sands (fines content FC > 5%), apply fines correction to obtain the clean-sand equivalent (Idriss and Boulanger 2008):

Δ N = exp[1.63 + 9.7FC + 0.01 - (15.7FC + 0.01)2]    (FC in percent)
(N1)60,cs = (N1)60 + Δ N
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
  • IS-02 SPT overburden normalization (sands) (N₁)₆₀Use: Cohesionless soils; normalizes to σ'v0 = 1 atm. Cap of 1.7 recommended by NCEER workshop. Limits: Not applicable to clays. Unreliable at σ'v0 > ~4,200 psf, about 2 tsf (other CN forms preferred at depth).
  • IS-11 Cyclic resistance ratio of sand from SPT CRR₇.₅Use: Level-ground, clean to silty sands; Mw = 7.5, σ'v0 ≈ 1 tsf (2,090 psf). Valid for (N1)60cs < 30 (≥30 considered non-liquefiable). Limits: Requires magnitude (MSF), overburden (Kσ) and static-shear (Kα) corrections. Superseded in some practice by Idriss & Boulanger (2008, 2014) and Cetin et al. (2018).
Inputs for the equations in this section (4)
SymbolWhat it isComes fromHow to get itTypical range
N60SPT blow count = N_meas ⋅ E_m ⋅ C_B ⋅ C_R ⋅ C_S 0.60Field testStandard Penetration Test (ASTM D1586); measure hammer energy (ASTM D4633, withdrawn 2025) to correct to N60.loose sand 4–10, dense 30–50 blows/ft · by USCS group
CNintermediate value computed on this pageAnother equationComputed: C_N = √ 2,117 σ'_v ≤ 2.0    (P_a = 2,117 psf)project-specific
(N1)60SPT blow count = C_N ⋅ N60Field testStandard Penetration Test (ASTM D1586); measure hammer energy (ASTM D4633, withdrawn 2025) to correct to N60.loose sand 4–10, dense 30–50 blows/ft · by USCS group
σ'vvertical stress / pore pressureAnother equationFrom unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level.project-specific
Standard Penetration Test
Standard Penetration Test
6.5.5.2 CRR from (N₁)₆₀,cs

Using the Youd et al. (2001) relationship (after Rauch 1998) for M_w = 7.5:

CRR7.5 = 134 - (N1)60,cs + (N1)60,cs135 + 50[10 ⋅ (N1)60,cs + 45]2 - 1200

Valid for (N₁)₆₀,cs < 30. For (N₁)₆₀,cs ≥ 30, the soil is considered non-liquefiable.

Scatter plot chart of cyclic stress ratio versus corrected blow count, with curves separating liquefaction, marginal liquefaction, and no-liquefaction zones for
Photo 6.5.5-1. SPT liquefaction chart for magnitude 7.5 earthquakes. Youd et al. (2001); with permission from ASCE.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
CRR7.51 34 - (N_1)60,cs + (N_1)60,cs 135 + 50 [10 ⋅ (N_1)_60,cs + 45]^2 - 1 200Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
SPT-Based Liquefaction Triggering Chart
SPT-Based Liquefaction Triggering Chart
6.5.5.3 Factor of Safety Against Liquefaction
FSL = CRR7.5 ⋅ MSF ⋅ Ksigma ⋅ KalphaCSRM,σ'

Minimum FS_L acceptance criteria for railroad infrastructure:

Table 6.5-4: Minimum FS_L and Performance Level
RailroadFEE Min FS_LDE Min FS_LMCE Min FS_LGoverning Standard
Common baselineN/A1.21.0Common practice; AREMA Chapter 9 sets no FS_L

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.

6.5.5.4 SPT-Based Liquefaction Triggering Calculator

The library's chapter on geotechnical earthquake engineering (J. D. Bray) and the military handbook Soil Dynamics and Special Design Aspects (MIL-HDBK-1007/3) both rest on the Seed and Idriss simplified procedure: compare the cyclic stress ratio an earthquake imposes on a layer with the cyclic resistance ratio the layer can supply, estimated from its corrected SPT blow count. Railroad embankments over loose saturated sand and the approach fills of bridges in river valleys are the usual concerns; lateral spreading toward a channel can move a bridge abutment or pier even when the bridge itself is undamaged.

6.5.5.4.1 Method

Equation 6.5-1. Cyclic stress ratio (Seed and Idriss)

CSR = 0.65 (amax/g)(σv/σ'v) rd;  rd = 1 − 0.00233 z for z ≤ 30 ft; 1.174 − 0.00814 z for 30 to 75 ft (z = depth in feet; the metric form is 1 − 0.00765 z to 9.15 m and 1.174 − 0.0267 z to 23 m)

Equation 6.5-2. Cyclic resistance ratio for M 7.5 and factor of safety (NCEER clean-sand curve)

CRR7.5 = 1/(34 − N) + N/135 + 50/(10N + 45)² − 1/200,  N = (N1)60cs < 30

MSF = 102.24/Mw2.56;  FS = CRR7.5 MSF / CSR

Table 6.5-9. Corrections applied to the field blow count
CorrectionValue used by the calculator
EnergyER/60, with ER entered (automatic hammers commonly 75 to 90%)
Rod length0.75 below 13 ft of rod; 0.85 to 20 ft; 0.95 to 33 ft; 1.0 beyond
Borehole and samplerEntered (1.0 for standard practice)
OverburdenCN = (Pa/σ'v)0.5 ≤ 1.7
Fines content(N1)60cs = α + β(N1)60, α and β from fines content (Idriss and Seed)

6.5.5.4.2 Worked example: bridge approach fill on alluvium

For the eight-layer boring loaded as the calculator's example (amax = 0.25 g, Mw 7.0, water at 5 ft), the lowest factor of safety is 0.77 and 2 of the layers fall below 1.0. These are the loose layers at 10 and 15 ft, just below the water table. The layers at 20 and 35 ft are marginal (factors of safety of about 1.1), and the dense layers at 30 and 40 ft are too dense to liquefy. That pattern, with liquefaction confined to a shallow loose layer, is what drives lateral spreading toward a channel and settlement of the approach fill.

Open the liquefaction triggering calculator →
Layer-by-layer SPT procedure: corrections, fines adjustment, CSR, CRR, magnitude scaling and factor of safety, with a profile chart.

6.5.5.4.3 Sources in the library

These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.

  • Geotechnical Earthquake Engineering (J. D. Bray, handbook chapter), Siesmic folder: strong shaking, site response, liquefaction procedure and seismic slope stability.Find source ↗
  • Soil Dynamics and Special Design Aspects, MIL-HDBK-1007/3 (1997): liquefaction evaluation and dynamic properties.Find source ↗
  • Geotechnical Earthquake Engineering (book, Siesmic folder) and Principles of Soil Dynamics (Soil Dynamics folder) for background.Find source ↗