6.5.18 Critical Speed and Train-Induced Ground Vibration

Seismic hazard characterization and liquefaction evaluation are critical components of geotechnical services for railroad infrastructure in seismically active regions.
Authors: Daniel P. Colwell and Mario Ruel
6.5.18 Critical Speed and Train-Induced Ground Vibration

Earthquakes are not the only dynamic load on soft ground. A train running on very soft soil can approach the speed of the surface (Rayleigh) wave in the ground, and the track deflection then builds into a resonant, wave-like response with uplift as well as downward movement. The best-documented case is a high-speed line on soft clay in Sweden where analysis put the peak response at about 146 mph (235 km/h), with deflections growing sharply as train speed approached it. For most railroad track the problem does not arise, but it should be checked where speeds above about 80 mph are planned over soft clay, peat or organic soil (Chapters 2.5 and 2.6).

6.5.18.1 Method

Equation 6.5-3. Critical speed estimate

Vcr ≈ VR = Vs(0.862 + 1.14ν)/(1 + ν)

Vs = shear wave velocity of the soft layer; ν = Poisson's ratio (the bracket is the standard elastic approximation, about 0.95 for saturated clay).

Up to about 25% of the Rayleigh wave velocity the deflection bowl under a train is symmetric and quasi-static. Above that it stretches sideways and compresses ahead of the train, and the amplitude grows rapidly as VR is approached. Published practice limits train speed to two-thirds of the critical speed and, where soft ground is improved for a higher speed, requires the improvement to raise the critical speed to 1.5 to 2.0 times the intended maximum speed. Falling weight deflectometer and surface-wave tests (SASW, MASW) can measure the response or the shear wave velocity directly (Chapter 5.1).

6.5.18.2 Worked example: passenger upgrade over soft clay

Table 6.5-10. Vs = 200 ft/s, ν = 0.49, proposed 110 mph (calculator output)
ResultValue
Estimated critical speed130 mph
Two-thirds speed limit87 mph
Line speed as a share of critical speed85 %
Shear wave velocity needed for 1.5 × line speed254 ft/s
Increase in small-strain shear modulus needed1.6 times

The present ground would limit speed to about 87 mph. Raising the critical speed to 165 mph calls for a shear wave velocity near 255 ft/s in the improved zone, which deep mixing or column-supported embankment designs can be checked against (Chapter 7.2).

Open the critical speed calculator →
Rayleigh wave critical speed from shear wave velocity, the two-thirds speed limit, and the stiffness needed to meet a remediation ratio.

6.5.18.3 Sources in the library

These documents are in the reference library. The method summaries above are paraphrased; equations are standard or published forms.

  • Railway Geotechnics (Li, Hyslip, Sussmann and Chrismer, 2016), Chapter 3.3.8 (critical speed) and Chapter 8 (FWD and surface wave methods).Find source ↗
  • The Effects of Railway Traffic on Embankment Stability (UK rail safety research report, 2011): dynamic response of embankments.Find source ↗
  • Design and Construction of Pavements and Rail Tracks (Balkema): soft-ground case histories with low shear wave velocity.Find source ↗