Railway Ground Hazard Risk Management · 6.0 · Analysis
Sections · click a car to open it

6.5.13 Practical Recommendations

Seismic hazard characterization and liquefaction evaluation are critical components of geotechnical services for railroad infrastructure in seismically active regions.
Authors: Daniel P. Colwell and Mario Ruel
6.5.13 Practical Recommendations
  1. Conduct seismic screening before detailed investigation. Use USGS Unified Hazard Tool to extract PGA at all bridge and embankment locations before mobilizing rigs. Sites with 475-yr PGA < 0.10g (or 0.07g for a passenger railroad) are typically screened out of detailed liquefaction analysis. This screening step costs nothing and focuses investigation resources on critical exposures.
  2. Sample across the full profile to 50 ft for liquefaction analysis. Shallow SPT refusal on dense layers does not preclude liquefaction in interbedded loose sands at intermediate depths. Continuous SPT at 2.5-ft intervals from the groundwater table to 50 ft or refusal (whichever is deeper) is the recommended minimum program for DE-level liquefaction analysis.
  3. Pair SPT with CPTu soundings for spatial continuity. SPT provides the direct (N₁)₆₀ value needed for triggering analysis, but CPTu provides vertical resolution of thin liquefiable layers (<3 ft) that SPT's 18-in. sample interval can miss. Owner railroads may require minimum one CPTu per 500 ft of alignment in known liquefiable zones.
  4. Include seasonal groundwater in all CSR calculations. WT depth controls σ'_v and therefore CSR. NMSZ sites with shallow seasonal WT (5–10 ft depth in spring) may show FS_L 15–25% lower than the same calculation at summer WT. Report CSR at both conditions; govern on worst case. Report both conditions in the GDR.
  5. Do not rely on Youd lateral spreading model as sole design input. The Youd MLR model has a standard deviation of about 0.2 in log₁₀ D_H, so a prediction is uncertain by roughly a factor of 1.6 at one standard deviation. For D_H > 3 ft, supplement with numerical analysis (e.g., FLAC or PLAXIS with PM4Sand constitutive model) to narrow the uncertainty band before finalizing remediation scope.
  6. Document post-liquefaction residual strength conservatively. Seed & Harder (1990) lower-bound values are appropriate for safety-critical railroad structures (bridges, retaining walls, major embankments). The upper bound of the s_ur envelope is not appropriate for design and should never be used without explicit railroad client approval.
  7. Integrate seismic assessment output into GIS deliverables. Owner railroads may require FS_L and estimated seismic settlement tabulated at milepost resolution with GIS shapefile delivery. Structure the liquefaction summary table to feed directly into the client's infrastructure risk management database, using milepost, latitude/longitude, event return period, and remediation priority as key fields.
Supplemental reference

Using intensity reports for post-earthquake track inspection

Before instrumental data are available, the Modified Mercalli (MM) intensity describes ground effects that map directly to railroad damage. From the MM descriptions reproduced in Geological Hazards:

MMGround and track effects described
VIIISand and mud ejected in small amounts; changes in well water
IXGround cracked conspicuously; underground pipes broken
XGround badly cracked; rails bent; considerable landslides from river banks and steep slopes; sand and mud shifted
XIBridges destroyed; broad fissures; earth slumps and land slips in soft ground; rails bent greatly

Elnashai and Di Sarno list rail bending or rupture and derailment among the typical earthquake damage to highway and railway lifelines, along with pier failure, unseating at bearings and pavement cracking and settlement. They also note that lurch cracking of soft saturated ground and movement toward steep slopes and cliffs damage transportation corridors even away from the fault. Intensity scales differ internationally (Figure 1.13 in Elnashai compares MM, MCS, MSK, EMS and the 7-level JMA scale), so convert when using foreign reconnaissance reports.

EPS geofoam behind integral abutments

Numerical models of two integral-abutment bridges (13 variants each, with dense to loose sand and stiff to soft clay around the piles) found that replacing compacted backfill with EPS geofoam reduced seismic moment and shear in the integral abutments in every case. The cost was slightly larger abutment and pier displacement and somewhat higher pier forces, which the author judged designable. For railroad structures in moderate seismic zones, the same approach can reduce abutment demand. Check the added displacement against track tolerances, and see Chapter 6.2 for geofoam properties and buoyancy.

Source: Elnashai, A. S. and Di Sarno, L. (2008). Fundamentals of Earthquake Engineering. Wiley · Bolt, B. A., Horn, W. L., Macdonald, G. A. and Scott, R. F. (1977). Geological Hazards: Earthquakes, Tsunamis, Volcanoes, Avalanches, Landslides, Floods, 2nd ed. Springer-Verlag

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-02 SPT overburden normalization (sands) (N₁)₆₀Use: Cohesionless soils; normalizes to σ'v0 = 1 atm. Cap of 1.7 recommended by NCEER workshop. Limits: Not applicable to clays. Unreliable at σ'v0 > ~4,200 psf, about 2 tsf (other CN forms preferred at depth).