↑ Parent Menu⌂ Main Menu
← Chapter 6.5 Seismic Hazard and Liquefaction
GHRM
Railway Ground Hazard Risk Management · 6.0 · Analysis
Sections · click a car to open it

6.5.1 Background and Railroad Context

Seismic hazard characterization and liquefaction evaluation are critical components of geotechnical services for railroad infrastructure in seismically active regions.
Authors: Daniel P. Colwell and Mario Ruel
6.5.1 Background and Railroad Context

Earthquake damage to railroad infrastructure manifests through several mechanisms: embankment slope failures, liquefaction-induced track settlement and lateral spreading, bridge foundation movement, retaining wall failure, and disrupted drainage producing post-event flooding. The consequences range from temporary slow orders to multi-week line closures with significant freight revenue loss.

Railroad seismic design philosophy differs from building or highway design in several important ways:

  • Operational continuity: Class I railroads require rapid return to service following design-level events. Some owner railroads' seismic design criteria define a three-tier performance objective: (1) Frequent Earthquake Event (FEE, 108-yr return period, 50% PE in 75 years) — no significant damage, no service interruption; (2) Design Earthquake (DE, 475-yr return, 10% PE in 50 yr) — repairable damage, service restored within 72 hours; (3) Maximum Considered Earthquake (MCE, 2,475-yr return, 2% PE in 50 yr) — life safety preserved, service restored within 30 days.
  • Distributed infrastructure: A single mainline may traverse hundreds of miles of varying geological conditions. Screening-level assessments must efficiently identify critical exposures warranting detailed analysis.
  • Track geometry tolerance: FRA track geometry standards (49 CFR Part 213) define allowable surface deviations that translate directly into post-seismic settlement acceptance criteria. Class 4 track (maximum 60 mph freight) allows a profile deviation of 2 in. on a 62-ft chord (49 CFR 213.63); Class 7 (up to 125 mph) is held to the tighter limits of 49 CFR 213.331.
  • Bridge approach sensitivity: Settlement differential between bridge-on-pile-foundation and approach embankment on liquefied ground produces the "bump at the end of the bridge" phenomenon at orders of magnitude greater intensity than under static loading.
Earthquake Design basics
Earthquake Design basics
Supplemental reference

How earth fills actually fail in earthquakes

Towhata summarizes the Japan Society of Civil Engineers (JSCE, 2000) classification of residual deformation of road, railway and river-dike fills (Figure 14-S1): Type 1 shallow sliding of the slope surface; Type 2 a slip surface within the fill; Type 2′ a slip surface reaching soft foundation soil; Type 3 slumping (the fill sinks and spreads); and Type 4 densification and subsidence. Faulting directly beneath a fill is a separate case.

Types of earthquake-induced failure of earth fills: (1) surface sliding; (2) slip within the fill; (2′) slip reaching soft foundation; (3) slumping; (4) subsidence (JSCE, 2000, in Towhata, 2008).
Supplemental Figure 14-S1. Types of earthquake-induced failure of earth fills: (1) surface sliding; (2) slip within the fill; (2′) slip reaching soft foundation; (3) slumping; (4) subsidence (JSCE, 2000, in Towhata, 2008). Source: Towhata, I. (2008). Geotechnical Earthquake Engineering. Springer, p. 271.
  • Of 47 randomly selected JSCE cases: 5 Type 1, 23 Type 2, 12 Type 3, 7 Type 4. Every slump (Type 3) was associated with high excess pore pressure in the fill or the foundation.
  • Subsidence reached up to about 0.7 of the fill height. Types 2 and 3 produced the largest ratios. Sandy fills and sandy foundations settled most (pore pressure and liquefaction), but clayey or peaty foundations also produced significant subsidence.
  • Densification near a bridge abutment can stop traffic even when the bridge itself is undamaged — the railroad “bump” noted above.

Allowable displacement. Because earth structures can be restored far more quickly than steel or concrete, Towhata reports a survey of Japanese infrastructure operators on which observed earthquake displacements they would accept without prior seismic strengthening. Displacements greater than about 6.6 ft were generally not accepted, yet a 33-ft displacement of a railway embankment (Hachinohe) was judged acceptable because it could be restored. Restoration cost did not drive these judgments; effects on the public did. This supports the performance-based tiers in Section 6.5.1: set the allowable deformation by restoration time and consequence, not a single FS.

Source: Towhata, I. (2008). Geotechnical Earthquake Engineering. Springer

Seismic isolation of bridges and train protection

Profillidis frames railway seismic risk in two parts. First, structures, track and subgrade are designed for the regional design acceleration (up to about 10 ft/s² in his text) so that nothing collapses even in the most severe event. In zones of very high seismicity, bridges are fully isolated from their supports with dampers (Figure 6.5-11). Second, trains are protected during an event by trackside accelerometers that stop traffic above 2.1 ft/s² and reduce speed between 1.3 and 2.1 ft/s² (details in Chapter 3.8, §3.8.6).

Figure 6.5-11. Concrete railway bridge isolated from its supports by dampers, in a region of high seismicity. Profillidis Fig. 9.22.
Figure 6.5-11. Concrete railway bridge isolated from its supports by dampers, in a region of high seismicity. Profillidis Fig. 9.22.

After Profillidis (2014), §9.17, Fig. 9.22. Full reference under Supplemental References.

← Previous · 6.0 Analysis Chapter 6.4 — Infiltration and Seepage
Next · 6.0 Analysis → Chapter 6.6 — Tunnels and Portals