The Vesić (1973) generalization of Terzaghi's original equation is the standard for computing ultimate unit bearing capacity q_ult for shallow foundations:


q_ult = c · Nc · Fcs · Fcd · Fci
+ q · Nq · Fqs · Fqd · Fqi
+ 0.5 · γ · B · Nγ · Fγs · Fγd · Fγi
Where:
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| c | cohesion intercept (psf) | Lab test | Effective cohesion intercept from the same triaxial or direct-shear tests used for φ'. Take c' = 0 for sands and for long-term design unless tests justify more. | 0–300 psf · by USCS group |
| q | effective overburden pressure at footing base = γ · D_f (psf) | Another equation | From unit weights, layer thicknesses and the groundwater level: σv = Σγihi, u = γw × depth below the water table, σ' = σ − u. Use the design groundwater level. | project-specific |
| Df | embedment depth (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
| γ | effective unit weight of soil below footing base (pcf) | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
| B | footing width (ft) | Project geometry | From project plans, survey and the design layout; layer depths and thicknesses from the boring logs. | project-specific |
Nq = e^(π·tan φ') · tan²(45 + φ'/2)
Nc = (Nq − 1) · cot φ' (use Nc = 5.14 when φ' = 0)
Nγ = 2(Nq + 1) · tan φ'
| φ' (°) | N_c | N_q | N_γ | Typical Soil Description |
|---|---|---|---|---|
| 0 | 5.14 | 1.00 | 0.00 | Soft–medium clay (UU condition) |
| 5 | 6.49 | 1.57 | 0.45 | Soft clay with minor sand |
| 10 | 8.35 | 2.47 | 1.22 | Silty clay |
| 15 | 10.98 | 3.94 | 2.65 | Stiff clayey silt |
| 20 | 14.83 | 6.40 | 5.39 | Dense silt, loose sand |
| 25 | 20.72 | 10.66 | 10.88 | Medium-dense sand |
| 30 | 30.14 | 18.40 | 22.40 | Dense sand, gravel-sand |
| 35 | 46.12 | 33.30 | 48.03 | Dense gravel |
| 40 | 75.31 | 64.20 | 109.4 | Very dense gravel |
| 45 | 133.9 | 134.9 | 271.8 | Dense rock fill |
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Nq | intermediate value computed on this page | Another equation | Computed: Nq = e^(π·tan φ') · tan²(45 + φ'/2) | project-specific |
| Nc | intermediate value computed on this page | Another equation | Computed: Nc = (Nq − 1) · cot φ' (use Nc = 5.14 when φ' = 0) | project-specific |
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
For a rectangular footing of width B and length L (L ≥ B):
Fcs = 1 + (B/L)(Nq/Nc)
Fqs = 1 + (B/L) tan φ'
Fγs = 1 − 0.4(B/L)
For a strip footing: B/L → 0, so F_cs = F_qs = F_γs = 1.0. For a circular footing (B = L): B/L = 1.0.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| Fcs | intermediate value computed on this page | Another equation | Computed: Fcs = 1 + (B/L)(Nq/Nc) | project-specific |
| Fqs | intermediate value computed on this page | Another equation | Computed: Fqs = 1 + (B/L) tan φ' | project-specific |
| Fγs | intermediate value computed on this page | Another equation | Computed: Fγs = 1 − 0.4(B/L) | project-specific |
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
No additional content.
Fcd = 1 + 0.4(Df/B)
Fqd = 1 + 2·tan φ'·(1 − sin φ')²·(Df/B)
Fγd = 1.0
For D_f/B > 1, replace D_f/B with arctan(D_f/B) in radians in the F_qd expression.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
For a resultant load inclined at angle β from vertical (due to braking or wind forces):
Fci = Fqi = (1 − β/90)²
Fγi = (1 − β/φ')²
β is in degrees. For purely vertical loading, β = 0 and all inclination factors = 1.0.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| φ' | effective friction angle | Lab test (or correlation) | Triaxial CU with pore pressure (ASTM D4767) or CD (D7181), or direct shear (D3080). Sands are rarely sampled: estimate from SPT or CPT correlations (IS-04, IS-05, IS-08). | sands 30–42°, clays 17–32° · by USCS group |
| γ | total (moist) unit weight | Lab test | Weigh and measure undisturbed tube samples (ASTM D7263); for fill, use the compaction spec. Or compute γ = γd(1 + w). | sands 105–135, clays 95–130 pcf · by USCS group |
No additional content.
q_allow = (q_ult − q) / FS + q
Where q = surcharge at footing base; FS = factor of safety (typically 3.0 for railroad structures with limited investigation; 2.5 with comprehensive investigation).
The net allowable bearing pressure is:
q_net,allow = (q_ult − q) / FS
For railroad bridge abutments, FS ≥ 3.0 is common practice. For yard and siding structures, FS = 2.5 may be acceptable with borings at every foundation location; confirm with the owner railroad.
| Symbol | What it is | Comes from | How to get it | Typical range |
|---|---|---|---|---|
| q | surcharge at footing base | Loading criteria | From the loading criteria: AREMA MRE (Cooper E-80, impact), structural loads from the designer, or equipment specifications. | project-specific |
| FS | factor of safety (typically 3.0 for railroad structures with limited investigation | Design criterion | Set by the owner railroad's standards, AREMA, AASHTO, USACE or the project specification. | typically 3.0 for railroad structures with limited investigation |
Strong layer over weak layer. A compacted ballast/subballast section or desiccated crust over soft clay is the typical railroad profile, and the Vesić equation (which assumes one homogeneous soil) overestimates capacity there. Das presents the Meyerhof and Hanna (1978) method: when the strong layer thickness H is small relative to B, the footing punches through the top layer (resisted by adhesion and passive force on vertical planes below the footing edges) and then fails the lower layer in general shear:
qu = qb + 2(Ca + Pp sin δ′)/B − γ1H ≤ qt (capacity of the top layer alone)
where qb is the bearing capacity of the weaker layer and Ca = c′aH is the adhesion force. If H is large, the failure surface stays in the top layer and qt governs. For signal and equipment foundations on a thin working platform over soft subgrade, check this mechanism.
Footing at the top of a slope. Signal masts, catenary poles and bridge abutments often sit on or near an embankment crest. Meyerhof (1957) gives qu = c′Ncq + ½γBNγq, with Ncq and Nγq charted against slope angle, footing setback b/B, embedment Df/B and, for clay, the stability number Ns = γH/cu. Capacity increases with setback distance (Das charts b/B from 0 to about 6); a footing right at the crest can have a small fraction of its level-ground capacity. A worked example, footings on the slope face and poles in slopes are in Section 6.1.23. Always follow with a global slope stability check (Chapter 6.3).
Source: Das, B. M. Principles of Foundation Engineering. Cengage Learning
For signal houses, small culvert headwalls and other minor railroad structures — or to sanity-check a Vesić result — NAVFAC DM-7.02 (Table 1) gives presumptive allowable pressures intended to provide adequate safety against failure and avoid detrimental settlement of individual footings:
Table 11-S1. Presumptive allowable bearing pressure, tsf (NAVFAC DM-7.02, Table 1, abridged)
| Bearing material | Consistency | Range | Recommended |
|---|---|---|---|
| Massive crystalline igneous/metamorphic rock (granite, basalt, gneiss) | Hard, sound | 60–100 | 80 |
| Foliated metamorphic rock (slate, schist) | Medium hard, sound | 30–40 | 35 |
| Hard cemented shale, siltstone, sandstone, limestone without cavities | Medium hard, sound | 15–25 | 20 |
| Weathered or broken bedrock (RQD < 25), except argillaceous | Soft rock | 8–12 | 10 |
| Compaction shale / argillaceous rock, sound | Soft rock | 8–12 | 10 |
| Glacial till, hardpan (GW-GC, GC, SC) | Very compact | 8–12 | 10 |
| Gravel, gravel–sand (GW, GP, SW, SP) | Very compact / medium / loose | 6–10 / 4–7 / 2–6 | 7 / 5 / 3 |
| Coarse to medium sand (SW, SP) | Very compact / medium / loose | 4–6 / 2–4 / 1–3 | 4 / 3 / 1.5 |
| Fine to medium sand, silty or clayey sand (SW, SM, SC) | Very compact / medium / loose | 3–5 / 2–4 / 1–2 | 3 / 2.5 / 1.5 |
| Inorganic clay (CL, CH) | Very stiff–hard / medium–stiff / soft | 3–6 / 1–3 / 0.5–1 | 4 / 2 / 0.5 |
| Inorganic silt, varved silt-clay-fine sand | Very stiff–hard / medium–stiff / soft | 2–4 / 1–3 / 0.5–1 | 3 / 1.5 / 0.5 |
NAVFAC’s notes matter for railroad use: controlled compacted fill takes the value of the equivalent natural soil; organic soil and uncompacted fill (common in old railroad embankments) must be investigated case by case; on compressible fine-grained soil, settlement generally governs; and a rock value may never exceed the intact UCS. Transient wind or earthquake loads may increase the pressure by up to one-third. Presumptive values are not a substitute for analysis where differential settlement matters, soils are soft, or groundwater is shallow.
Source: Naval Facilities Engineering Command (1986). Foundations and Earth Structures, Design Manual 7.02 (NAVFAC DM-7.02)

USACE EM 1110-1-2908 notes that rock foundation design is usually controlled by settlement, sliding or overturning, but bearing must still be checked, and the failure mode depends on joint spacing S relative to footing width B, joint orientation and condition (Figure 11-S1):

For non-strip footings EM 1110-1-2908 applies Sowers’ shape corrections: Nc × 1.2 (circular), 1.25 (square), 1.12 (L/B = 2), 1.05 (L/B = 5); Nγ × 0.70, 0.85, 0.90, 0.95 respectively. Because rock masses usually have a large margin, USACE recommends starting from lower-bound c and φ.
Source: U.S. Army Corps of Engineers (1994). Rock Foundations. EM 1110-1-2908
The USACE manual Bearing Capacity of Soils (EM 1110-1-1905) sets out the general bearing capacity equation with the Terzaghi, Meyerhof, Hansen and Vesic factor sets and works each through the same footing. The Vesic set is used here because it handles footing shape, embedment and inclined load in one consistent form and is the basis of many agency programs. Track structures add two things to the usual building problem: longitudinal braking and traction forces make the load inclined, and the manual's table of typical factors of safety lists 4 for railway bridges, against 3 for ordinary footings.
Equation 6.1-20. General bearing capacity equation (EM 1110-1-1905, Eq. 4-1)
where σ'D is the effective overburden at the footing base, γ'H the effective unit weight within a depth B below the base, and each ζ the product of shape, depth and inclination factors.
Equation 6.1-21. Vesic bearing capacity factors
| Effect | Cohesion ζc | Surcharge ζq | Wedge ζγ |
|---|---|---|---|
| Shape | 1 + (B/W)(Nq/Nc) | 1 + (B/W) tanφ | 1 − 0.4 B/W |
| Depth (k = D/B, or tan−1(D/B) when D/B > 1) | ζqd − (1 − ζqd)/(Nc tanφ); 1 + 0.4k for φ = 0 | 1 + 2 tanφ (1 − sinφ)² k | 1 |
| Inclination (m = (2 + B/W)/(1 + B/W)) | ζqi − (1 − ζqi)/(Nc tanφ) | (1 − T/Q)m | (1 − T/Q)m+1 |
The calculator reproduces the manual's Vesic worked example (B = 3 ft, W = 6 ft, D = 2 ft, φ' = 30°, T/Q = 0.2): qu = 5.86 ksf.
Groundwater is handled as the manual recommends: σ'D uses buoyant weight below the water table, and γ'H is interpolated between moist and buoyant weight when the water table lies within B below the base. In loose or soft soil the local-shear option reduces tanφ by one third, which gives the lower-bound estimate of the manual's Equation 4-9.
| Input | Value | Result | Value |
|---|---|---|---|
| Footing B × W, embedment D | 8 ft × 30 ft, 4 ft | Nc, Nq, Nγ | 35.49, 23.18, 30.21 |
| φ', c | 32°, 0 | Correction factors ζc, ζq, ζγ | 1.102, 1.100, 0.666 |
| γ, γsat, water depth | 125 pcf, 130 pcf, 6 ft | Ultimate qu | 19.34 ksf |
| T/Q (longitudinal braking) | 0.10 | Allowable qa at FS 4 (railway bridge) | 4.83 ksf |
| Factor of safety | 4 | Allowable vertical load | 1,160.2 kips |
The inclination factor alone removes roughly a fifth of the surcharge and wedge terms in this example, which is why longitudinal forces from braking and traction should be carried into the bearing check rather than treated only in the structural design. Settlement (Chapter 6.2) usually controls for footings wider than about 6 ft on sand.
Open the bearing capacity calculator →
Vesic method per EM 1110-1-1905: footing shape, embedment, inclined load, water table, local shear, and allowable pressure for a chosen factor of safety.
These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.