Foundation bearing capacity governs the structural adequacy of every load-transfer element in railroad infrastructure — bridge abutments and piers, signal equipment…
The three examples cover the three foundation types under railroad structures: a spread footing, a driven pile group and a drilled shaft. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 6.1-1: Spread Footing for a Bridge Abutment
A bridge replacement on a Class I railroad located in West Virginia puts an abutment footing on stiff residual clay. Earth pressure behind the abutment adds a moment, which shifts the resultant toward the toe; the effective-width method replaces the true width with the width that carries the load centrally.
Spot check: The applied 6,541 psf is below the 9,766 psf allowable, consistent with FS > 3.
↓
Solution
FS = 4.59: the footing is adequate in bearing.
Solution
The resultant is within the middle third (e = 0.85 ft < 1.33 ft), qallow = 4.88 tsf, and the factor of safety under the applied load is 4.59.
Bearing is comfortably adequate; for a footing on stiff clay under a railroad bridge, settlement will govern. The settlement analysis (Chapter 6.2) must show total settlement under 1.0 in. and differential under 0.75 in. across the span, or the owner railroad’s limits, to hold FRA Class 4 geometry. The railroad’s bridge engineers will review the calculation.
Example 6.1-2: Driven H-Pile Group for a Bridge Pier
A pier replacement on a Class I railroad main line located in Kansas. HP14×117 piles are driven through loose fill into medium-dense alluvial sand and stop 2 ft above limestone. Side resistance is computed with the β-method, tip resistance with Meyerhof’s SPT method, and the group is checked for efficiency.
At 3D: θ = 18.4°, η = 0.728, 619 kips; at 4D: θ = 14.0°, η = 0.793, 674 kips
Both short of 800 kips
↓
Step 6 · 3×4 group at 4D
η = 1 − 14.0(17)/1,080 = 0.780; 12 × 94.4 × 0.780
883.5 kips ≥ 800 kips
↓
Solution
12 piles (3×4) at 4D spacing: 883 kips.
Solution
Qallow = 94.4 kips per pile; a 3×4 group of 12 piles at 4D spacing provides 883 kips against the 800-kip demand.
FHWA allows η = 1.0 for driven groups in sand that are not predrilled or jetted, because driving densifies the sand between piles, so the Converse-Labarre reduction here is conservative; with η = 1.0, nine piles would do. Set refusal criteria with WEAP, confirm capacity with CAPWAP on an agreed share of production piles, and confirm tip elevations in the field.
Example 6.1-3: Drilled Shaft for a Crane Rail Foundation
A rail-mounted gantry crane foundation for an intermodal facility on a Class I railroad located in Dallas, Texas. The shaft carries a heavy, repeated wheel load through stiff to very stiff clay. Side resistance is computed with the FHWA GEC 10 α-method, excluding the top 5 ft and the bottom diameter.
CSL Access Tube Requirements for Drilled Piles
Given
Variable
Value
Description
Load
180 kips per rail per axle; DLF 1.20 (assumed)
Demand 216 kips
Soil
CL, su = 1,800 psf to 20 ft; CH, su = 3,200 psf to 35 ft
Shaft
30 in. diameter, 35 ft deep (first trial)
FS
2.5
Assumes a load test
pa
2,117 psf
Required
Allowable capacity of the 30-in. shaft
A shaft size that meets the demand
Equations
Eq. 1 (GEC 10): α = 0.55 for su/pa ≤ 1.5; α = 0.55 − 0.1(su/pa − 1.5) up to 2.5 — side resistance factor
Eq. 6.1-10: Qs = Σ α su πD Δz — side resistance, 5 ft to one diameter above the tip
A 36-in. shaft just meets the demand (216.9 kips).
Solution
The 30-in. shaft provides 172 kips, short of 216 kips. A 36-in. shaft at 35 ft provides 216.9 kips, just meeting the demand at FS = 2.5.
With so little margin, a 42-in. shaft or a deeper tip is the prudent choice. FS = 2.5 assumes a load test, so confirm the owner’s load-test requirement (a static test to ASTM D1143 or a bidirectional test) before production shafts. Under repeated crane loading, the tip, which needs larger movement to mobilize, carries a larger share of the load than its 38% share of capacity suggests; settlement should be checked as well.