6.1.8 Representative Data Tables

Foundation bearing capacity governs the structural adequacy of every load-transfer element in railroad infrastructure — bridge abutments and piers, signal equipment…
Authors: Daniel P. Colwell and Mario Ruel
6.1.8 Representative Data Tables
Table 6.1-2 — Typical Bearing Capacity Values by Soil Type (English Units)
Soil Type (USCS)Consistency/Densitys_u or φ'q_allow Shallow Fdn (tsf)Railroad Application
CH (Fat Clay)Very softs_u = 250–500 psf0.25–0.50Avoid; use piles — Class I railroad located in coastal Georgia
CL (Lean Clay)Softs_u = 500–1,000 psf0.5–1.0Siding footings minimum 3 ft embed.
CLStiffs_u = 1,000–2,000 psf1.0–2.0Bridge abutment footings — a Class I railroad
CL/MLVery stiffs_u = 2,000–4,000 psf2.0–4.0Grade crossing slabs — a short-line railroad
SM (Silty Sand)Looseφ' = 28–32°1.0–1.5Use piles for bridge loads — a Class I railroad
SP (Poorly Graded Sand)Medium denseφ' = 32–36°1.5–2.5Signal foundations — a Class I railroad
SW/GWDenseφ' = 36–40°2.5–4.5Intermodal crane footings — a Class I railroad
GW (Well-graded Gravel)Very denseφ' = 40–45°4.5–7.0Mainline bridge piers — a Class I railroad
CL over bedrockStiff clay capMixed1.5–3.0 w/ piles to rockClass I railroad located in Appalachia
Limestone/SandstoneCompetent rockRQD > 50%10–50+A Class I railroad bridge piers
Table 6.1-3 — Pile Type Selection Guide
ClientPreferred Pile TypeMinimum FS (w/test)Minimum FS (no test)Wave Equation RequiredLoad Test Required
FRA (all classes)Per AREMA Ch. 82.5 min3.0 minAs applicablePer client

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.