6.1.7 Uplift Capacity

Foundation bearing capacity governs the structural adequacy of every load-transfer element in railroad infrastructure — bridge abutments and piers, signal equipment…
Authors: Daniel P. Colwell and Mario Ruel
6.1.7 Uplift Capacity

Tension forces from wind uplift, seismic uplift, and locomotive-induced overturning at signal mast foundations must be checked. Net uplift capacity for a single pile:

Micropile applications — foundation support, retrofit, slopes, retention
Micropile applications — foundation support, retrofit, slopes, retention
Equation 6.1-19 — Pile Uplift Capacity:

Q_ult,tension = Σ(f_s · As) + W_pile

Skin friction in tension is typically reduced to 75–80% of the compression value for driven piles (FHWA GEC No. 12). In frost-susceptible soils, frozen soil adhering to the pile can impose a large upward force ("frost heave uplift") that is distinct from structural uplift, and it needs a separate check.