6.1.20 Micropile Axial Capacity

Foundation bearing capacity governs the structural adequacy of every load-transfer element in railroad infrastructure — bridge abutments and piers, signal equipment…
Authors: Daniel P. Colwell and Mario Ruel
6.1.20 Micropile Axial Capacity

Micropiles are small-diameter (typically 5 to 12 in.) drilled and grouted piles with a steel casing and a center bar. Along the track they are used where a conventional pile rig cannot work: underpinning a bridge pier or abutment, supporting a load-transfer platform over soft ground, stitching an unstable fill, and building the micropile and tieback walls placed from the shoulder during track windows (Chapter 7.1). Because the pile is slender, almost all of the load goes into the ground through grout-to-ground bond along the bond zone; end bearing is ignored. The capacity is the smaller of that bond capacity and the structural capacity of the steel and grout in the cased and uncased lengths.

6.1.20.1 Method

Equation 6.1-28. Allowable grout-to-ground bond capacity (FHWA NHI-05-039)

PG,allow = (αbond/FS) π Db Lb

αbond = ultimate grout-to-ground bond (Table 6.1-8); Db = drilled diameter of the bond zone; Lb = bond length; FS = 2.0 with load testing (2.5 for seismic loading or creep-susceptible soil).

Equation 6.1-29. Allowable structural capacity (FHWA ASD)

Compression: Pc,allow = 0.40f′cAgrout + 0.47Fy(Abar + Acasing);   Tension: Pt,allow = 0.55Fy(Abar + Acasing)

Fy = the lower of the bar and casing yield strengths (strain compatibility). In the uncased bond zone only the bar and grout count. Flush-threaded casing joints may carry less tension than the pipe; count the casing in tension only to the joint’s rated strength.

Table 6.1-8. Typical ultimate grout-to-ground bond, psi (FHWA NHI-05-039 Table 5-3, converted from kPa). Type A gravity grout; B pressure grout through the casing; C single global post-grout; D multiple post-grout
GroundType AType BType CType D
Silt and clay, soft to medium plastic5–105–147–177–21
Silt and clay, stiff, dense to very dense7–1710–2814–2814–28
Sand, fine, loose to medium dense10–2110–2814–2814–35
Sand and gravel, medium to very dense14–3117–5221–5221–56
Gravel, medium to very dense14–3817–5221–5221–56
Glacial till, medium to very dense, cemented14–2814–4517–4517–49
Soft shale30–80–––
Slate and hard shale75–200–––
Limestone150–300–––
Sandstone75–250–––
Granite and basalt200–610–––

Bond values vary with the drilling method, flushing and grouting pressure as much as with the soil, so the design value must be confirmed by a verification test to 2.0 times the design load on a sacrificial or production pile and by proof tests (typically to 1.67 times) on a share of the production piles.

6.1.20.2 Worked example

Example 6.1-5: Micropile Underpinning a Bridge Abutment

An abutment on a Class I railroad located in Pennsylvania is underpinned with micropiles drilled through the footing into dense sand and gravel. Each pile carries 80 kips in compression and 40 kips of uplift under the overturning case.

abutment footingPc = 80, Pt = 40 kipscasing 7.0 × 0.50 in.Lb = 20 ftDb = 8 in.dense sand and gravelGivenDb = 8 in., Lb = 20 ft; Type B groutαbond = 34.8 psi; FS = 2.0Casing 7.0 × 0.50 in., 80 ksi#14 bar, 75 ksi; f′c = 4,000 psiRequiredBond and structural capacityGoverning allowable loadsBond length needed
Micropile drilled through the abutment footing: cased through the upper soil, grouted bond zone in dense sand and gravel.

Given

VariableValueDescription
GroundDense sand and gravelBond zone
GroutingType B (pressure through casing)
αbond34.8 psiMid-range of 17.4–52.2 psi; to be verified by test
Db, Lb8 in.; 20 ftBond zone
Casing7.0 in. OD × 0.50 in. wall, Fy = 80 ksiCased length
Bar#14, A = 2.25 in.², Fy = 75 ksiFull length
f′c4,000 psiGrout
FS2.0With load testing
Pc, Pt80 kips; 40 kipsDesign loads

Required

  • Allowable bond capacity
  • Structural capacity of the cased and uncased lengths
  • Governing allowable compression and tension; bond length needed

Equations

  1. Eq. 6.1-28: PG = (αbond/FS)πDbLb
  2. Eq. 6.1-29: Pc = 0.40f′cAg + 0.47Fy(Abar + Acasing) — compression
  3. Eq. 6.1-29: Pt = 0.55FyAbar — tension, casing joints not counted
  4. Lb,req = P × FS/(αbondπDb)

Steps

Step 1 · Bond capacity (Eq. 6.1-28)
34.8 × π × 8 × 240 = 210,000 lb; /2.0
PG = 105.0 kips (5.25 kips per ft)
↓
Step 2 · Areas
Acasing = π/4(7.0² − 6.0²); grout in casing π/4(6.0²) − 2.25; grout in bond zone π/4(8²) − 2.25
10.21 in.²; 26.0 in.²; 48.0 in.²
↓
Step 3 · Structural compression (Eq. 6.1-29)
Cased: 0.40(4.0)(26.0) + 0.47(75)(2.25 + 10.21); uncased: 0.40(4.0)(48.0) + 0.47(75)(2.25)
Cased 480.9 kips; uncased 156.1 kips
Spot check: Fy = min(80, 75) = 75 ksi for strain compatibility; the steel term dominates the cased length (439 of 481 kips).
↓
Step 4 · Structural tension
0.55 × 75 × 2.25
92.8 kips (bar only)
↓
Step 5 · Governing
Compression min(105.0, 480.9, 156.1); tension min(105.0, 92.8)
105.0 kips (bond) and 92.8 kips (bar)
↓
Step 6 · Bond length
80,000 × 2.0 / (34.8 × π × 8 × 12)
Lb,req = 15.2 ft ≤ 20 ft
Spot check: Check: 15.2 ft × 5.25 kips/ft = 80 kips.
↓
Solution
Allowable 105.0 kips in compression and 92.8 kips in tension, both above the design loads.

Solution

The micropile carries 105 kips in compression, limited by grout-to-ground bond, and 92.8 kips in tension, limited by the bar in the uncased bond zone. The 20-ft bond length exceeds the 15.2 ft needed.

The bond value is the weak link and must be confirmed: run a verification test to 160 kips (2.0 × 80) before production, and proof-test about 5% of the production piles. If the test shows lower bond, lengthen the bond zone rather than changing the section.

Open the micropile calculator →
Grout-to-ground bond from the FHWA ranges for the ground and grouting method, cased and uncased structural capacity in compression and tension, the governing allowable loads and the bond length for a design load.

6.1.20.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • FHWA NHI-05-039, Micropile Design and Construction (Sabatini, Tanyu, Armour, Groneck and Keeley, 2005): Chapter 5, Table 5-3 and the allowable structural capacities; Chapter 7, load testing.Official page ↗
  • Library, Railroad / AREMA / AREMA Comm 1 / Micropile Retaining Walls: micropile and soil-nail walls built from the track for shoulder repairs (company and site names withheld).Find source ↗