Micropiles are small-diameter (typically 5 to 12 in.) drilled and grouted piles with a steel casing and a center bar. Along the track they are used where a conventional pile rig cannot work: underpinning a bridge pier or abutment, supporting a load-transfer platform over soft ground, stitching an unstable fill, and building the micropile and tieback walls placed from the shoulder during track windows (Chapter 7.1). Because the pile is slender, almost all of the load goes into the ground through grout-to-ground bond along the bond zone; end bearing is ignored. The capacity is the smaller of that bond capacity and the structural capacity of the steel and grout in the cased and uncased lengths.
Equation 6.1-28. Allowable grout-to-ground bond capacity (FHWA NHI-05-039)
αbond = ultimate grout-to-ground bond (Table 6.1-8); Db = drilled diameter of the bond zone; Lb = bond length; FS = 2.0 with load testing (2.5 for seismic loading or creep-susceptible soil).
Equation 6.1-29. Allowable structural capacity (FHWA ASD)
Fy = the lower of the bar and casing yield strengths (strain compatibility). In the uncased bond zone only the bar and grout count. Flush-threaded casing joints may carry less tension than the pipe; count the casing in tension only to the joint’s rated strength.
| Ground | Type A | Type B | Type C | Type D |
|---|---|---|---|---|
| Silt and clay, soft to medium plastic | 5–10 | 5–14 | 7–17 | 7–21 |
| Silt and clay, stiff, dense to very dense | 7–17 | 10–28 | 14–28 | 14–28 |
| Sand, fine, loose to medium dense | 10–21 | 10–28 | 14–28 | 14–35 |
| Sand and gravel, medium to very dense | 14–31 | 17–52 | 21–52 | 21–56 |
| Gravel, medium to very dense | 14–38 | 17–52 | 21–52 | 21–56 |
| Glacial till, medium to very dense, cemented | 14–28 | 14–45 | 17–45 | 17–49 |
| Soft shale | 30–80 | – | – | – |
| Slate and hard shale | 75–200 | – | – | – |
| Limestone | 150–300 | – | – | – |
| Sandstone | 75–250 | – | – | – |
| Granite and basalt | 200–610 | – | – | – |
Bond values vary with the drilling method, flushing and grouting pressure as much as with the soil, so the design value must be confirmed by a verification test to 2.0 times the design load on a sacrificial or production pile and by proof tests (typically to 1.67 times) on a share of the production piles.
An abutment on a Class I railroad located in Pennsylvania is underpinned with micropiles drilled through the footing into dense sand and gravel. Each pile carries 80 kips in compression and 40 kips of uplift under the overturning case.
| Variable | Value | Description |
|---|---|---|
| Ground | Dense sand and gravel | Bond zone |
| Grouting | Type B (pressure through casing) | |
| αbond | 34.8 psi | Mid-range of 17.4–52.2 psi; to be verified by test |
| Db, Lb | 8 in.; 20 ft | Bond zone |
| Casing | 7.0 in. OD × 0.50 in. wall, Fy = 80 ksi | Cased length |
| Bar | #14, A = 2.25 in.², Fy = 75 ksi | Full length |
| f′c | 4,000 psi | Grout |
| FS | 2.0 | With load testing |
| Pc, Pt | 80 kips; 40 kips | Design loads |
The micropile carries 105 kips in compression, limited by grout-to-ground bond, and 92.8 kips in tension, limited by the bar in the uncased bond zone. The 20-ft bond length exceeds the 15.2 ft needed.
The bond value is the weak link and must be confirmed: run a verification test to 160 kips (2.0 × 80) before production, and proof-test about 5% of the production piles. If the test shows lower bond, lengthen the bond zone rather than changing the section.
Open the micropile calculator →
Grout-to-ground bond from the FHWA ranges for the ground and grouting method, cased and uncased structural capacity in compression and tension, the governing allowable loads and the bond length for a design load.
The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.