6.1.23 Footings at the Top of or on a Slope

Foundation bearing capacity governs the structural adequacy of every load-transfer element in railroad infrastructure — bridge abutments and piers, signal equipment…
Authors: Daniel P. Colwell and Mario Ruel
6.1.23 Footings at the Top of or on a Slope

Railroad foundations are often close to a slope: signal and communication bungalows, catenary and signal mast footings, retaining wall and wingwall footings, and culvert headwalls on embankment shoulders or at the tops of cuts. The slope removes part of the passive wedge on one side, so the bearing capacity drops as the footing gets closer to the crest and as the slope gets steeper. Two cases are treated separately (Das and Sivakugan 2019, Sections 7.8 and 7.9; Bowles 1996, Section 4.9).

6.1.23.1 Footing on top of a slope (setback b from the crest)

Equation 6.1-34. Meyerhof (1957) bearing capacity of a strip footing on top of a slope

qu = c′Ncq + ½γBNγq;   granular soil: qu = ½γBNγq;   clay (φ = 0): qu = cuNcq

Ncq and Nγq are read from Meyerhof’s charts as functions of β, b/B (or b/H), Df/B and φ′ or Ns (Das and Sivakugan 2019, Figs. 7.20 and 7.21). The factors rise with setback and reach the level-ground values at a setback of a few footing widths; read that limit from the chart for the case at hand.

Equation 6.1-35. Stability number for clay slopes

Ns = γH / cu

If B < H use the Ns = 0 curves with b/B; if B ≥ H use the curves for the calculated Ns with b/H.

6.1.23.2 Footing on the slope face

Where the footing is on the face of the slope with a level base, the general bearing capacity equation (Section 6.1.2.6) is multiplied by ground inclination factors. Vesić’s factors are gq = gγ = (1 − tanβ)² and, for φ = 0, gc = 1 − 2β/(π + 2) with β in radians; Hansen’s, given by Bowles, are similar. For β = 30°, gq = gγ = 0.18 and gc = 0.80, so in sand the slope removes over 80% of the γ and q terms. The equations do not apply if β exceeds φ′, and the overall slope stability usually governs before bearing does.

6.1.23.3 Lateral loads on poles and piles in slopes

Catenary poles, signal masts and transmission structures on embankment side slopes resist overturning by passive pressure on the downhill side, which is reduced by the slope. Bowles suggests reducing the face (bearing) part of the lateral subgrade modulus ks by the ratio RF of the passive force for the actual ground slope to that for level ground, while leaving the side-shear part unchanged. For example, with ks = 2,000 split equally between face and sides and RF = 0.6, the revised ks = 1,000 + 0.6 × 1,000 = 1,600. The same idea applies to Broms’ method (Section 6.1.19): use a reduced passive coefficient on the downhill side, or ignore the soil above a line drawn from the toe of the embedment out to the slope face.

For railroad work: Treat any foundation within about two footing widths of a crest, or on a slope face, as a slope problem first and a bearing problem second. Include the train surcharge in the global check, keep the foundation out of the zone that a future ditch cleaning or slope flattening will remove, and protect the crest from runoff. For mast and pole foundations on fill slopes, embed below the loose shoulder material (often 2 to 3 ft of ballast and side-cast spoil) and neglect it in the lateral analysis.

6.1.23.4 Worked example

Example 6.1-8: Signal Bungalow Footing at the Crest of a Clay Cut

Problem Statement

A continuous footing for a signal bungalow and cable trough on a Class I railroad located in Missouri has to sit at the top of a 20-ft-high cut slope in clay, set back only 2 ft 8 in. from the crest because of the track centers. Check the allowable bearing pressure using Meyerhof’s factors for a foundation on top of a slope (Section 6.1.23). This is Das and Sivakugan’s Example 7.8 restated in English units.

footing B = 4 ft Df = 4 ft b = 2.67 ft H = 20 ft β = 30° Clay: cu = 1,050 psf, φ = 0, γ = 111 pcf Required:stability number Ns qu and qall (FS = 4) overall slope check Black = given; red = required
Figure 6.1-18. Given and required for Example 6.1-8: strip footing near the crest of a clay slope.

Given

VariableValueDescription
B, Df4 ft, 4 ftFooting width and depth
b2.67 ftDistance from the footing edge to the crest
H, β20 ft, 30°Slope height and angle
cu, γ1,050 psf, 111 pcfUndrained shear strength (φ = 0) and unit weight
FS4Factor of safety on the slope-reduced capacity, as in Das’s example

Required

  • (a) Stability number Ns and which Ncq curve to use
  • (b) Ultimate and allowable bearing pressure
  • (c) What else must be checked

Equations

  1. Eq. 6.1-34: qu = cu Ncq (φ = 0)
  2. Eq. 6.1-35: Ns = γH / cu; use the Ns = 0 curves when B < H
  3. Eq. 3: qall = qu / FS

Steps

Step 1 · (a) Stability number
111 × 20 / 1,050
Ns = 2.1; but B = 4 ft < H = 20 ft, so use the Ns = 0 curves
↓
Step 2 · (a) Chart inputs
Df/B = 4/4 = 1; b/B = 2.67/4 = 0.67; β = 30°
Ncq = 6.3 (Das and Sivakugan 2019, Fig. 7.21)
Spot check: Same ratios as Das’s SI example (B = 1.2 m, b = 0.8 m), so the chart reading carries over.
↓
Step 3 · (b) Ultimate
1,050 × 6.3
qu = 6,615 psf
Spot check: Das’s SI answer 315 kN/m² = 6,580 psf; the difference is rounding of cu.
↓
Step 4 · (b) Allowable
6,615 / 4
qall ≈ 1,650 psf
↓
Step 5 · (c) Other checks
Overall stability of the slope with the footing load and train surcharge (Chapter 6.3); settlement; frost depth; erosion of the crest
Bearing alone does not clear the site
↓
Solution
Ns = 2.1 but B < H, so Ncq = 6.3 from the Ns = 0 curves; qu ≈ 6,600 psf; qall ≈ 1,650 psf.

Solution

(a) Ns = 2.1, but B < H so the Ns = 0 curve applies. (b) qu ≈ 6,600 psf, qall ≈ 1,650 psf. (c) Global stability with the train surcharge, settlement and crest erosion.

A bungalow footing usually bears well under 1,650 psf, so bearing is not the issue; the slope is. Run the global stability analysis with the footing load and the Cooper E-80 surcharge on the nearby track (Section 6.1.4 and Chapter 6.3), and keep surface water from the bungalow roof and cable trough away from the crest. If the setback cannot be increased, a short drilled shaft or helical piles that carry the load below the potential slip surface are often cheaper than a wider footing.

6.1.23.5 Sources

  1. Bowles, J. E. (1996). Foundation Analysis and Design, 5th ed. New York: McGraw-Hill.
  2. Das, B. M. and Sivakugan, N. (2019). Principles of Foundation Engineering, 9th ed., SI edition. Boston: Cengage Learning.
← Previous · 5.0 Testing Chapter 5.5 — The Observational Method and Trigger-Action Response Plans