↑ Parent Menu⌂ Main Menu
← Chapter 6.1 Foundation Engineering: Bearing Capacity
GHRM
Railway Ground Hazard Risk Management · 6.0 · Analysis
Sections · click a car to open it

6.1.19 Laterally Loaded Piles and Shafts by Broms’ Method

Foundation bearing capacity governs the structural adequacy of every load-transfer element in railroad infrastructure — bridge abutments and piers, signal equipment…
Authors: Daniel P. Colwell and Mario Ruel
6.1.19 Laterally Loaded Piles and Shafts by Broms’ Method

Signal masts, catenary and communication poles, sign bridges, light towers and the piles of retaining walls and bridge bents along the track all carry horizontal load: wind on the structure and wires, braking and centrifugal forces, earth pressure and impact. Broms’ method (1964) is the standard hand check of the ultimate lateral load. It treats the soil reaction as a simple pressure diagram and asks which happens first: the soil around a short, stiff pile fails as the pile rotates or translates, or a long pile forms a plastic hinge at the yield moment of its section. It is quick, it brackets the answer, and it shows whether more embedment helps (short pile) or only a stronger section will (long pile). It gives no deflection; the working-load deflection still comes from p-y analysis (Section 6.1.6 tools).

6.1.19.1 Method

In clay the resistance is taken as zero over the top 1.5 diameters, where the soil can flow up and around the pile, and 9sub below. In sand the passive pressure on the pile is taken as three times the Rankine value, 3Kpγ′z, which allows for the three-dimensional wedge in front of a narrow pile. The two free-head cases used most along the track are:

Equation 6.1-26. Broms, free head, cohesive soil

Short: Hu(e + 1.5b + 0.5f) = 2.25 su b g²;   Long: Hu(e + 1.5b + 0.5f) = My;   f = Hu/(9sub),   L = 1.5b + f + g

f = depth below 1.5b to the point of zero shear (maximum moment); g = remaining length below it. The short-pile equation is solved by trial (the calculator uses bisection); the long-pile equation is a quadratic in Hu.

Equation 6.1-27. Broms, free head, cohesionless soil

Short: Hu = 0.5γ′bL³Kp/(e + L);   Long: Hu(e + 0.67f) = My,   f = 0.82√(Hu/(γ′bKp))

Kp = tan²(45° + φ′/2); γ′ = effective (buoyant below the water table) unit weight.

Table 6.1-7. Broms’ cases for a fixed head (cap restrains rotation, load at the ground surface)
BehaviorCohesive soilCohesionless soil
Short (translates)Hu = 9sub(L − 1.5b), if Hu(1.5b + 0.5f) ≤ MyHu = 1.5γ′bL²Kp, if (2/3)HuL ≤ My
Intermediate (hinge at head)Hu(1.5b + 0.5f) − My = 2.25subg²Hu = (0.5γ′bL³Kp + My)/L
Long (hinges at head and depth)Hu = 2My/(1.5b + 0.5f)Hu = 2My/(0.67f)

FHWA NHI-05-042 (superseded by GEC 12, FHWA-NHI-16-009 (2016)) recommends a factor of safety of about 2.5 on the Broms ultimate load. The yield moment is My = FyZ for a steel pile (plastic modulus Z) and the nominal flexural strength of the section for a reinforced concrete shaft.

6.1.19.2 Worked example

Example 6.1-4: Drilled Shaft for a Signal Mast in Stiff Clay

A cantilever signal mast on a Class I railroad located in Ohio sits on a 30-in. drilled shaft in stiff clay. Wind on the mast and signal heads gives a working lateral load of 12 kips whose resultant acts 20 ft above the ground. The shaft head is free to rotate.

H = 12 kips workinge = 20 ftL = 15 ftb = 30 in.stiff claysu = 1,500 psfGivenb = 30 in., L = 15 ft, e = 20 ftsu = 1,500 psf (stiff clay)My = 900 kip-ft; free headH = 12 kips; FS = 2.5RequiredHu (short or long), H allowShortest embedment for 12 kips
Free-head drilled shaft for a signal mast with the wind load acting 20 ft above the ground.

Given

VariableValueDescription
SoilStiff CL, su = 1,500 psfUU triaxial, upper 15 ft
b30 in. = 2.50 ftShaft diameter
L15 ftEmbedded length
e20 ftHeight of load resultant
My900 kip-ftNominal flexural strength of the shaft
H12 kipsWorking lateral load
FS2.5FHWA for Broms’ method

Required

  • Ultimate lateral load for short and long behavior, and which governs
  • Allowable lateral load and whether 15 ft of embedment is enough
  • Shortest embedment that carries the working load

Equations

  1. Eq. 6.1-26: f = Hu/(9sub); g = L − 1.5b − f — zone lengths
  2. Eq. 6.1-26: Hu(e + 1.5b + 0.5f) = 2.25subg² — short pile
  3. Eq. 6.1-26: Hu(e + 1.5b + 0.5f) = My — long pile
  4. Hallow = Hu/FS

Steps

Step 1 · Soil resistance
9sub = 9 × 1,500 × 2.50; 1.5b = 3.75 ft
33,750 lb/ft below 3.75 ft; L − 1.5b = 11.25 ft
↓
Step 2 · Short pile (Eq. 6.1-26)
Trial Hu = 36.0 kips: f = 36,026/33,750 = 1.067 ft; g = 11.25 − 1.067 = 10.18 ft
Hu,short = 36.0 kips
Spot check: Left side 36,026 × (20 + 3.75 + 0.53) = 874,800 ft-lb; right side 2.25 × 1,500 × 2.50 × 10.18² = 874,900 ft-lb. Balanced.
↓
Step 3 · Long pile (Eq. 6.1-26)
(1/(2 × 33,750))Hu² + 23.75Hu − 900,000 = 0
Hu,long = 37.0 kips
↓
Step 4 · Governing and allowable
min(36.0, 37.0) = 36.0 kips (short); 36.0/2.5
Hallow = 14.4 kips ≥ 12 kips
Spot check: The maximum moment at ultimate, 875 kip-ft, is just below My = 900 kip-ft, consistent with the short mode governing by a small margin.
↓
Step 5 · Minimum embedment
Find L with Hu = 2.5 × 12 = 30 kips
L = 13.9 ft
↓
Solution
Hallow = 14.4 kips; 15 ft of embedment is adequate in strength (13.9 ft minimum).

Solution

The 30-in. shaft 15 ft long has an ultimate lateral capacity of 36.0 kips (short-pile behavior) and an allowable load of 14.4 kips, above the 12-kip working load.

Because the short and long capacities are close, the design is balanced: a longer shaft gains little because the section would yield at about 37 kips. Deflection at 12 kips still needs a p-y check against the signal maintainer’s tolerance, and the top 1.5b of clay that the method ignores must not be disturbed by ditching or cable trenching beside the mast.

Open the laterally loaded pile calculator →
Broms’ short, intermediate and long modes for a free or fixed head in clay or sand, the governing ultimate and allowable lateral load, the embedment needed for a working load, and a capacity-versus-length chart.

6.1.19.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • FHWA NHI-05-042 (superseded by GEC 12, FHWA-NHI-16-009 (2016)), Design and Construction of Driven Pile Foundations, Vol. I (2006): Broms’ method for laterally loaded piles.Find source ↗
  • B.B. Broms (1964), Lateral resistance of piles in cohesive soils; Lateral resistance of piles in cohesionless soils. Journal of the Soil Mechanics and Foundations Division, ASCE, 90(SM2), 27–63, and 90(SM3), 123–156.Find source ↗
  • B.M. Das, Principles of Foundation Engineering: Broms’ ultimate lateral resistance.Find source ↗
← Previous · 5.0 Testing Chapter 5.5 — The Observational Method and Trigger-Action Response Plans
Next · 6.0 Analysis → Chapter 6.2 — Settlement Analysis