↑ Parent Menu⌂ Main Menu
← Chapter 6.1 Foundation Engineering: Bearing Capacity
GHRM
Railway Ground Hazard Risk Management · 6.0 · Analysis
Sections · click a car to open it

6.1.13 Practice Questions and Full Answers

Foundation bearing capacity governs the structural adequacy of every load-transfer element in railroad infrastructure — bridge abutments and piers, signal equipment…
Authors: Daniel P. Colwell and Mario Ruel
6.1.13 Practice Questions and Full Answers
Each question is worked in the same five parts as the examples. Questions 6.1-2 and 6.1-5 are reasoning questions.
Question 6.1-1: Square Footing on Clay, Undrained

Problem Statement

A short-line railroad is installing a new signal equipment house on a 6-ft-square spread footing at 3 ft depth, founded on stiff lean clay with the strength shown. The engineer must compute the ultimate and allowable bearing pressure, with the factor of safety shown, for the signal footing.

Given

VariableValueDescription
Footing6 ft × 6 ft; Df = 3 ft
SoilStiff lean clay; φ = 0; su = 1,500 psf; γ = 115 pcf
FS2.5

Required

  • qult and qallow

Equations

  1. Eq. 6.1-2: Nc = (Nq − 1) cotφ′; Nγ = 2(Nq + 1) tanφ′ — Nq from Table 6.1-1
  2. Eq. 6.1-3: Fcs = 1 + (B′/L′)(Nq/Nc); Fqs = 1 + (B′/L′) tanφ′; Fγs = 1 − 0.4 B′/L′ — shape
  3. Eq. 6.1-4: Fcd = 1 + 0.4 Df/B′; Fqd = 1 + 2 tanφ′(1 − sinφ′)² Df/B′; Fγd = 1 — depth, Df/B ≤ 1
  4. Eq. 6.1-1: qult = cNcFcsFcd + qNqFqsFqd + ½γB′NγFγsFγd — general bearing capacity
  5. Eq. 6.1-6: qallow = (qult − q)/FS + q

Steps

Step 1 · Factors at φ = 0
Nc = 5.14, Nq = 1.0, Nγ = 0
↓
Step 2 · Shape and depth
Fcs = 1 + 1.0/5.14; Fcd = 1 + 0.4(0.5)
Fcs = 1.195; Fcd = 1.20
↓
Step 3 · qult
1,500(5.14)(1.195)(1.20) + 345 = 11,056 + 345
qult = 11,400 psf
↓
Step 4 · qallow
11,056/2.5 + 345
4,770 psf = 2.38 tsf
↓
Solution
qult ≈ 11,400 psf; qallow ≈ 4,770 psf.

Solution

qult ≈ 11,400 psf; qallow ≈ 4,770 psf (2.38 tsf).

With φ = 0 the overburden term adds only q, so embedment helps mainly through the depth factor. The undrained case governs for a footing loaded quickly on clay.

Question 6.1-2: Effective Width and the Middle-Third Check

Problem Statement

A railroad retaining wall footing next to the track carries a vertical load and a moment from earth pressure and train surcharge. The designer reports a reduced effective width and asks whether the middle-third rule in AREMA Chapter 8 applies. The engineer must explain the effective width, when the middle-third check applies and what to do if the footing fails it.

Given

VariableValueDescription
LoadVertical load P with moment M
RuleAREMA Chapter 8: resultant within the middle third (e ≤ B/6) under unfactored load

Required

  • Meaning of B′
  • When the middle-third check applies and what to do if it fails

Equations

  1. Eq. 6.1-7: e = M/P; B′ = B − 2e

Steps

Step 1 · What does a moment do?
Moves the resultant off center by e = M/P.
↓
Step 2 · Effective width
B′ = B − 2e is the width that carries the load centrally; it replaces B in every bearing term.
↓
Step 3 · Middle third
e ≤ B/6 keeps the whole base in compression; if exceeded, widen the footing, re-center the load or deepen it.
↓
Solution
B′ = B − 2e; resultant must stay within B/6.

Solution

B′ = B − 2e is the reduced width that carries the load centrally, and it lowers the capacity. AREMA Chapter 8 requires e ≤ B/6 under unfactored loads so no part of the base goes into tension.

The check applies to every abutment footing and retaining wall base under earth pressure. Braking forces add to the moment on abutments, so check the case with braking as well.

Question 6.1-3: Pipe Pile Capacity by the Meyerhof SPT Method

Problem Statement

A Class I railroad is replacing a ballast-deck trestle with a new bridge on closed-end pipe piles driven into uniform sand. The piles will be 40 ft long with the tip 30 ft into the sand, and no load test is planned. The engineer must estimate the allowable pile capacity from SPT blow counts for the bent design.

Given

VariableValueDescription
Pile12 in. closed-end pipe; L = 40 ft; Db = 30 ft
N6018Uniform SP sand
FS3.0No load test

Required

  • Allowable capacity

Equations

  1. Eq. 6.1-15: fs = 0.02 N60 (tsf) — driven displacement pile
  2. Eq. 6.1-16: qp = 0.4 N60(Db/B) ≤ 4N60 (tsf)

Steps

Step 1 · Side (Eq. 6.1-15)
0.36 tsf × 3.14 × 40 = 0.36 × 125.7
Qs = 45.3 tons
↓
Step 2 · Tip (Eq. 6.1-16)
0.4 × 18 × 30 = 216 tsf; limit 72 tsf; 72 × 0.785
Qp = 56.5 tons
↓
Step 3 · Allowable
101.8 / 3.0
33.9 tons = 67.9 kips
↓
Solution
Qallow ≈ 34 tons (68 kips).

Solution

Qult = 101.8 tons; Qallow ≈ 34 tons (68 kips).

The tip limit governs, so driving deeper into the same sand adds only side resistance. Refine with WEAP and confirm with CAPWAP or a load test; SPT-based pile capacities carry ±30 to 40% uncertainty.

Question 6.1-4: Group Efficiency of a Concrete Pile Group

Problem Statement

A pier of a new railroad bridge is supported by a 4 × 3 group of 16-in. square concrete piles at 4-ft spacing, each with the allowable capacity shown. The engineer must compute the group efficiency and the capacity of the group to compare with the pier load from the design train.

Given

VariableValueDescription
D16 in. = 1.333 ft
S4.0 ft (S/D = 3.0)
m, n4 and 3
Qallow120 kips per pile

Required

  • Group efficiency and group capacity

Equations

  1. Eq. 6.1-17: η = 1 − θ[(n − 1)m + (m − 1)n] / (90 m n); θ = arctan(D/S) in degrees — Converse-Labarre group efficiency

Steps

Step 1 · θ
arctan(1.333/4.0)
18.4°
↓
Step 2 · η
1 − 18.4(8 + 9)/1,080 = 1 − 0.290
0.710
↓
Step 3 · Group
12 × 120 × 0.710
1,022 kips against 1,440 kips summed
↓
Solution
η = 0.71; group 1,022 kips.

Solution

η = 0.71; group capacity 1,022 kips, 29% below the sum of individual piles.

If the demand is close to the individual sum, spread the piles to S/D of 3.5 to 4 or add piles. In clay, check block failure as well; it can govern over the efficiency-reduced sum.

Question 6.1-5: Why Micropiles for Underpinning Passenger Structures

Problem Statement

A passenger railroad needs to underpin the foundations of a station canopy and an overhead bridge pier that sit within a few feet of high-speed track, where geometry tolerances are tight and track windows are short. The engineer must explain why micropiles are the preferred foundation and which parameters govern their design.

Given

VariableValueDescription
SettingUnderpinning existing structures on a passenger corridor
ConstraintsTight geometry limits (49 CFR 213 Subpart G); short track windows

Required

  • Why micropiles are preferred
  • Which parameters govern their design

Equations

  1. Eq. 1: Qult = fb π Ddrill Lb — bond-zone capacity

Steps

Step 1 · Vibration
Rotary or rotary-percussion drilling of small casings causes little vibration, protecting track geometry and existing foundations.
↓
Step 2 · Access
Compact rigs fit short track windows and low headroom.
↓
Step 3 · Load path
Load goes past soft fill to competent soil or rock.
↓
Step 4 · Design parameters
Grout-to-ground bond fb, bond length Lb, and the structural capacity of the bar or casing.
↓
Solution
Low vibration, small rigs, deep load transfer; designed on bond stress.

Solution

Micropiles install with little vibration from compact rigs that fit short track windows, and they carry load past soft fill. Their design is governed by grout-to-ground bond stress, bond length and the steel section.

Bond stresses come from the FHWA micropile manual and must be confirmed by load tests (ASTM D1143), commonly to 200% of design load on a share of piles agreed with the railroad.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).
← Previous · 5.0 Testing Chapter 5.5 — The Observational Method and Trigger-Action Response Plans
Next · 6.0 Analysis → Chapter 6.2 — Settlement Analysis