↑ Parent Menu⌂ Main Menu
← Chapter 2.5 Clays: Properties, Typical Values and Behavior
GHRM
Railway Ground Hazard Risk Management · 2.0 · The Underworld
Sections · click a car to open it

2.5.7 Soft Clay Foundations: Embankment Stability

Clay is the soil whose behavior depends most on water and time: it is strong when dry and weak when wet, it consolidates for years under new fill, it swells and shrinks with the seasons, and in cut slopes it slowly loses strength until it slides.
Author: Daniel P. Colwell
2.5.7 Soft Clay Foundations: Embankment Stability

Placing fill on soft clay loads it faster than it can drain, so the critical condition is usually at the end of construction, using undrained strength. For a quick check of a wide fill on uniform soft clay:

Hmax = Nc suγfill FS     Nc = 5.14

Eq. 2.5-10 (bearing capacity of a strip load on undrained clay)

  • Embankments higher than Hmax need staged construction (with piezometers to confirm strength gain), berms, basal geosynthetic reinforcement, wick drains, lightweight fill or ground improvement (Chapter 7.2, Sections 7.2.3 to 7.2.5).
  • Strength gain between stages: Δsu ≈ (su/σ′v) · U · Δσ, where U is the average degree of consolidation under the stage load.
  • Widening an existing main-line embankment over soft clay is the common railroad case: the old embankment has consolidated the clay beneath it, but the new fill sits on weaker, unconsolidated clay. Analyze the widening, not the original section, and limit differential settlement between old and new tracks.
  • Monitor with settlement plates, piezometers and inclinometers; stop filling if pore pressure ratios or lateral movement accelerate (Chapter 5.3).
Placement of geosynthetic reinforcement for a column-supported embankment
Photo 2.5.7-1. Placement of geosynthetic reinforcement for a column-supported embankment. From FHWA (2004).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Placement of select fill for a column-supported embankment
Photo 2.5.7-2. Placement of select fill for a column-supported embankment. From FHWA (2004).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Fill placement to tension the geosynthetic
Photo 2.5.7-3. Fill placement to tension the geosynthetic. From the files of Joel Sloan.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Placement and compaction of embankment fill
Photo 2.5.7-4. Placement and compaction of fill for a column-supported embankment. From the files of Joel Sloan.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Column-supported T-Wall installation
Photo 2.5.7-5. Column-supported T-Wall installation. From FHWA (2004).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Completed T-Wall column-supported embankment at the Rancocas Bridge approach
Photo 2.5.7-6. Completed T-Wall column-supported embankment for the Rancocas Bridge approach. From FHWA (2004).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Geosynthetic placement for a column-supported embankment
Photo 2.5.7-7. Geosynthetic placement for a column-supported embankment. From the files of Jim Collin.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Geosynthetic placement with alternate roll direction from the previous layer
Photo 2.5.7-8. Geosynthetic placement with alternate roll direction from the previous layer. From the files of Jim Collin.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Base layer of geosynthetic reinforcement
Photo 2.5.7-9. Base layer of geosynthetic reinforcement for a column-supported embankment. From the files of Jim Collin.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
2.5.7.1 Chronic Settlement on Soft Clay: Consolidation or Bearing Failure

Track that keeps settling over soft clay is usually treated with ballast, and that works when the cause is consolidation, because consolidation slows down with time. A conference paper on very weak subgrade points out that the same symptom can come from a different mechanism: bearing-capacity (shear) failure of the clay under the embankment. Then the settlement rate does not slow, and each lift of ballast adds weight that drives the failure further. The paper's working rule is that a steady leveling effort, such as a carload of ballast every month, will not be cured by more surfacing. Telling the two apart early saves years of maintenance.

2.5.7.1.1 Reading the record

Table 2.5-13. Settlement mechanisms on soft clay
Compression (consolidation)Displacement (bearing failure)
Rate with timeFalls; approaches equilibriumSteady or increasing
Effect of added ballastSmall extra settlement, then levels offAdds driving load; can accelerate movement
Field signsUniform sag; no heaveBulging or heave at the toe or shoulder, ditch distortion
RemediesTime, surcharge, drainsToe berm (buttress); compaction or permeation grouting; sheet piles or other reinforcement, usually at least 25 ft long

Equation 2.5-13. Bearing check for an embankment on soft clay (strip, φ = 0)

FS = 5.14 su / (γH + q)

su = undrained shear strength; γH = embankment pressure; q = track and train load spread to the base of the embankment.

The calculator converts ballast deliveries to an equivalent settlement over the affected length, computes the rate in each period, and compares the last third of the record with the first. A ratio below 0.7 is read as consolidation and 0.7 or more as displacement. These thresholds are a screening choice, not a published criterion. The diagnosis should be confirmed with survey points, an inclinometer at the toe and piezometers before a remedy is chosen.

2.5.7.1.2 Worked examples

Table 2.5-14. Two records (calculator output)
RecordRate first third / last thirdDiagnosisBearing FS
About one 30-cu-yd car per month over 1,000 ft8.33 in./yr / 8.33 in./yrRate steady: consistent with bearing-capacity displacement0.95 (su 400 psf, 8 ft fill)
Surveyed settlement 1.2, 0.8, 0.6 ... 0.2 in. per quarter4.00 in./yr / 0.90 in./yrRate falling: consistent with consolidation (compression)

The first site settles at a constant rate on clay whose bearing factor of safety is below one; more ballast will not fix it. A toe berm is often the cheapest remedy where right-of-way and wetland permits allow; grouting or sheet piles work from within the right-of-way. The second site is consolidating and should level off.

Open the settlement diagnosis calculator →
Settlement rate from surfacing or survey records, trend classification, and the bearing factor of safety of the embankment on soft clay.

2.5.7.1.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • AREMA conference paper (2015): track leveling and alignment stability, options and approaches for very weak subgrade.Find source ↗
  • AREMA conference paper (2020): history of heavy axle load subgrade research at the federal accelerated testing facility.Find source ↗
  • AREMA conference paper (2019): remediation of ballast pockets in a 30-ft railway embankment with geogrid and ballast drains.Find source ↗
  • AREMA Manual for Railway Engineering, Chapter 1 Roadway and Ballast (2012, Volume 1), Part 1 Roadbed: maintenance exploration of creeping failures.Official page ↗
2.5.7.2 Building Embankments on Soft Clay in Stages

Soft clay may not carry a new embankment or siding fill placed all at once, but it gains strength as it consolidates under each lift. Duncan, Wright and Brandon devote a chapter to this. The critical moments are the ends of the fast placement periods, when pore pressures are highest. The factor of safety then rises during each pause as the pressures dissipate. They cite Polish test fills that, built in stages, safely reached twice the thickness the original strength would allow, and later twice that again before failing. They also show the reverse: where consolidation during construction is ignored, an analysis can call for staging or drains that are not needed. For a first estimate, their bearing capacity screen F = 5.53 su/(γH) gives the height each stage can reach. The strength gained after each pause is the undrained strength ratio times the effective stress actually gained.

Cross-section diagram of an embankment on weak soil, showing a reinforcement layer at the base of the embankment atop weak soil, which in turn overlies a stiffe
Photo 2.5.7.2-1. Embankment on Weak Foundation (after Bonaparte and Christopher 1987).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Three cross-section diagrams showing bearing failure, rotational failure, and lateral spreading failure modes of an embankment on soft foundation soil
Photo 2.5.7.2-2. Reinforced embankment failure modes (Holtz et al. 2008).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Two labeled rotational failure model diagrams showing disturbing and resisting moments, failure surface radius R, and reinforcement tension Tg with the geometry
Photo 2.5.7.2-3. Reinforcement required to provide rotational stability (a) after Christopher and Holtz (1985) after Wager (1981); (b) after Bonaparte and Christopher (1987) for the case in which the reinforcement does not increase soil strength (Holtz et al. 2008).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Two labeled cross-section diagrams showing sliding of the embankment on the reinforcement and rupture of the reinforcement with sliding on the foundation soil,
Photo 2.5.7.2-4. Reinforcement required to limit lateral embankment spreading (a) embankment sliding on reinforcement; (b) rupture of reinforcement and embankment sliding on foundation soil (from Bonaparte, R., and B. Reproduced with permission of the Transportation Research Board).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Workers on an unrolled geosynthetic sheet at the edge of a cleared, muddy embankment alignment cut through forest
Photo 2.5.7.2-5. Placing geosynthetic reinforcement prior to filling. From the files of Ryan Berg.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A bulldozer spreading granular fill over geosynthetic reinforcement along a roadway embankment cut through forest
Photo 2.5.7.2-6. Placing granular material over geosynthetic reinforcement. From the files of Ryan Berg.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

2.5.7.2.1 Method

Equation 2.5-14. Stage height and strength gain

Hallow = 5.53 su / (γfill Freq)  (Duncan, Wright and Brandon Eq. 7.10)

su(t) = su0 + (su/σ′v) Σ Δσi U(t − ti);   su/σ′v = 0.11 + 0.0037PI (Das) or from CU tests

Table 2.5-15. Two approaches to staged construction analysis (Duncan, Wright and Brandon, Section 11.2)
ApproachStepsNotes
Effective stressGet c′ and φ′ from drained or CU tests; estimate undrained excess pore pressures; compute dissipation during construction; analyze the ends of the fast placement periodsDepends on predicting pore pressures, which is difficult; field piezometers are essential
Total stress (undrained strength)Estimate the strength gain from consolidation and the strength ratio; analyze each stage with the increased undrained strengthMatches how failure would actually occur (undrained); the approach used in this calculator

The profession does not agree on which approach is better (Ladd, 1991). Either way, the critical times are the ends of the fast placement periods.

2.5.7.2.2 Worked example

A 25 ft embankment is to go over 30 ft of soft clay with su = 400 psf, PI = 30 (strength ratio 0.221), cv = 0.15 and ch = 0.30 ft²/day, and a required factor of 1.3 at the end of each stage. The initial strength carries only 13.6 ft. With wick drains at 6 ft, a first lift to 13.6 ft and a 90-day wait add enough strength to finish in 2 stages, by about day 120. Without drains, 90-day waits stall short of the final height. Waits of a year are needed, and the embankment takes 775 days. Drains, a lighter fill, or reinforcement are the alternatives to time.

Place each new lift on measured pore pressure dissipation, not on the predicted schedule: piezometers in the clay, settlement plates and inclinometers at the toe. Confirm each stage with a circular slip analysis (Chapter 6.3) using the strength actually gained.

Open the staged construction calculator →
Stage heights from the 5.53 su screen, strength gain from consolidation of each lift (vertical and, with wick drains, radial), the number of stages and the time to reach the final height.

2.5.7.2.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • J.M. Duncan, S.G. Wright and T.L. Brandon, Soil Strength and Slope Stability, 2nd edition: Chapter 11, analyses of embankments with partial consolidation, observed behavior of staged fills, and Eq. 7.10Find source ↗
  • B.M. Das, Principles of Geotechnical Engineering, 7th edition: Skempton's strength ratio relation and consolidationFind source ↗
  • B.M. Das, Advanced Soil Mechanics, 4th edition: radial consolidation (Barron) and precompressionFind source ↗
  • R.F. Craig, Craig's Soil Mechanics, 7th edition: vertical drains and staged loadingFind source ↗Library entry
← Previous · 2.0 The Underworld Chapter 2.4 — Silts: Properties, Typical Values and Liquefaction
Next · 2.0 The Underworld → Chapter 2.6 — Peats and Organic Soils: Properties, Typical Values and Behavior