Chapter 2.6 — Peats and Organic Soils: Properties, Typical Values and Behavior

Peat and organic soil are mostly water held in plant remains. They are the weakest and most compressible ground a railroad crosses: they settle for decades through secondary compression, carry little load, and keep moving long after the fill is placed.
Author: Daniel P. Colwell

Primary References: Mesri and Ajlouni (2007); Mesri, Stark, Ajlouni and Chen (1997); Edil and den Haan (1994); Landva and Pheeney (1980); MacFarlane (1969, Muskeg Engineering Handbook); Holtz, Kovacs and Sheahan (2011); FHWA GEC 13 (ground modification); ASTM D2974, D4427, D1997, D2435.

Typical Values for This Chapter — from the GHRM Soil & Rock Properties Database

Values for organic soils (OL, OH) and peat (Pt) from the database. English units; every value cites its library source, table and page. For preliminary design and checking test results, not a substitute for site testing.

Unit weight & specific gravity (20 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Dry unit weightCohesive soilsCL-CH / OL-OHSoft – organic50.9pcfLOOK T7.3, p.104
Saturated unit weightCohesive soilsCL-CH / OL-OHSoft – organic89.1pcfLOOK T7.3, p.104
Dry unit weightCohesive soilsCL-CH / OL-OHSoft – non-organic76.4pcfLOOK T7.3, p.104
Saturated unit weightCohesive soilsCL-CH / OL-OHSoft – non-organic101.9pcfLOOK T7.3, p.104
Dry unit weightCohesive soilsCL-CH / OL-OHStiff101.9pcfLOOK T7.3, p.104
Saturated unit weightCohesive soilsCL-CH / OL-OHStiff114.6pcfLOOK T7.3, p.104
Dry unit weightCohesive soilsCL-CH / OL-OHHard114.6pcfLOOK T7.3, p.104
Saturated unit weightCohesive soilsCL-CH / OL-OHHard127.3pcfLOOK T7.3, p.104
Bulk (saturated) unit weightClay – unconsolidated mudsOH / CHNatural101.9105.1108.2pcfCB T3.1, p.79
Dry unit weightClay – unconsolidated mudsOH / CHNatural57.363.670pcfCB T3.1, p.79
Bulk (saturated) unit weightClay – soft, open-structuredCL-CHNatural108.2114.6121pcfCB T3.1, p.79
Dry unit weightClay – soft, open-structuredCL-CHNatural7079.589.1pcfCB T3.1, p.79
Bulk (saturated) unit weightClay – firm or stiff, normally consolidatedCL-CHNatural114.6127.3140pcfCB T3.1, p.79
Dry unit weightClay – firm or stiff, normally consolidatedCL-CHNatural82.8101.9121pcfCB T3.1, p.79
Bulk (saturated) unit weightTropical red claysCL-MHNatural108.2120.9133.7pcfCB T3.1, p.79
Dry unit weightTropical red claysCL-MHNatural82.898.7114.6pcfCB T3.1, p.79
Specific gravity of solidsMost clay mineralsCL-CH2.672.72.73–CB T3.1, p.79
Void ratio (natural)Soft organic clayNatural state2.52.853.2–DASP T3.2, p.76
Natural water content (saturated)Soft organic clayNatural state90105120%DASP T3.2, p.76
Dry unit weightSoft organic clayNatural state3844.551pcfDASP T3.2, p.76
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Compaction (standard Proctor) (13 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Maximum dry unit weightOrganic silts, low plasticityOLAASHTO T 9982.892.3101.9pcfCB T3.2, p.80
Optimum moisture contentOrganic silts, low plasticityOLAASHTO T 992126.532%CB T3.2, p.80
Maximum dry unit weightOrganic silts/clays, high plasticityOHAASHTO T 9966.884.3101.9pcfCB T3.2, p.80
Optimum moisture contentOrganic silts/clays, high plasticityOHAASHTO T 99213345%CB T3.2, p.80
Maximum dry unit weight (ASTM D698)Inorganic silts and clayey siltsMLUFC 3-220-20 Table 3-195107.5120pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Inorganic silts and clayey siltsMLUFC 3-220-20 Table 3-1121824%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilInorganic silts and clayey siltsMLUFC 3-220-20 Table 3-13.0×10⁻⁸3.0×10⁻⁷3.0×10⁻⁶cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Organic silts, low plasticityOLUFC 3-220-20 Table 3-18090100pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Organic silts, low plasticityOLUFC 3-220-20 Table 3-1212733%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilOrganic silts, low plasticityOLUFC 3-220-20 Table 3-13.0×10⁻⁸cm/sUFC322020 T3-1, p.120
Maximum dry unit weight (ASTM D698)Organic claysOHUFC 3-220-20 Table 3-16582.5100pcfUFC322020 T3-1, p.120
Optimum moisture content (ASTM D698)Organic claysOHUFC 3-220-20 Table 3-11228.545%UFC322020 T3-1, p.120
Hydraulic conductivity of compacted soilOrganic claysOHUFC 3-220-20 Table 3-13.0×10⁻⁹cm/sUFC322020 T3-1, p.120
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Plasticity & swell (11 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Plasticity index for swelling potentialExpansive claysCL-CHLow swell potential (Seed et al. 1962)07.515%CB T8.4, p.180
Plasticity index for swelling potentialExpansive claysCL-CHMedium swell potential (Seed et al. 1962)102030%CB T8.4, p.180
Plasticity index for swelling potentialExpansive claysCL-CHHigh swell potential (Seed et al. 1962)2037.555%CB T8.4, p.180
Plasticity index for swelling potentialExpansive claysCL-CHVery high swell potential (Seed et al. 1962)40%CB T8.4, p.180
Plasticity index for expansion potentialExpansive claysCL-CHVery high (probable expansion >30% of volume)35%CB T8.6, p.185
Plasticity index for expansion potentialExpansive claysCL-CHHigh (probable expansion 20–30% of volume)253341%CB T8.6, p.185
Plasticity index for expansion potentialExpansive claysCL-CHMedium (probable expansion 10–30% of volume)1521.528%CB T8.6, p.185
Plasticity index for expansion potentialExpansive claysCL-CHLow (probable expansion <10% of volume)18%CB T8.6, p.185
Liquid limitClayCL-CH4095150%BUDHU T4.5, p.80
Plastic limitClayCL-CH2537.550%BUDHU T4.5, p.80
Plasticity indexClayCL-CH1557.5100%BUDHU T4.5, p.80
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Consistency, density & SPT (25 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Undrained shear strengthClayCL-CHVery soft251psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHSoft251386.5522psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHFirm5227831,044psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHStiff1,0441,5662,088psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHVery stiff2,0883,1324,177psfLOOK T2.14 / 5.3, p.50
Undrained shear strengthClayCL-CHHard4,177psfLOOK T2.14 / 5.3, p.50
Unconfined compressive strengthCohesive soilCL-CHVery soft (N < 2)0.25tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHSoft (N = 2–4)0.250.3750.5tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHMedium stiff (N = 4–8)0.50.751tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHStiff (N = 8–15)11.52tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHVery stiff (N = 15–30)234tsfIDOT T4.4.6.1.2-2, p.119
Unconfined compressive strengthCohesive soilCL-CHHard (N > 30)468tsfIDOT T4.4.6.1.2-2, p.119
SPT N-valueCohesive soilCL-CHVery soft00.51blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHSoft234blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHMedium stiff56.58blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHStiff91215blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHVery stiff162330blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHHard3145.560blows/ftGEC5 T23, p.137
SPT N-valueCohesive soilCL-CHVery hard60blows/ftGEC5 T23, p.137
Undrained shear strengthClayCL-CHVery soft418psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHSoft418626.5835psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHFirm8351,2001,566psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHStiff1,5662,3503,133psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHVery stiff3,1334,7006,266psfCRAIG T4.1, p.121
Undrained shear strengthClayCL-CHHard6,266psfCRAIG T4.1, p.121
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Shear strength (13 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Friction angleInorganic siltLoose2728.530degCB T6.4, p.159
Friction angleInorganic siltDense3032.535degCB T6.4, p.159
Effective cohesion (peak)Cohesive soilsCL-CH / OL-OHSoft – organic104156.5209psfLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHSoft – organic101520degLOOK T7.9, p.107
Effective cohesion (peak)Cohesive soilsCL-CH / OL-OHSoft – non-organic209313.5418psfLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHSoft – non-organic152025degLOOK T7.9, p.107
Effective cohesion (peak)Cohesive soilsCL-CH / OL-OHStiff4187311,044psfLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHStiff202530degLOOK T7.9, p.107
Effective cohesion (peak)Cohesive soilsCL-CH / OL-OHHard1,0441,5662,088psfLOOK T7.9, p.107
Effective friction angle (peak)Cohesive soilsCL-CH / OL-OHHard2527.530degLOOK T7.9, p.107
Critical-state friction angleClaysCL-CHCritical state1522.530degBUDHU T10.3, p.300
Peak friction angleClaysCL-CHPeak202530degBUDHU T10.3, p.300
Residual friction angleClaysCL-CHResidual51015degBUDHU T10.3, p.300
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Stiffness (modulus & Poisson's ratio) (19 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Young's modulus, short term (undrained)SiltML-CHSoft208.9ksfLOOK T11.7, p.152
Young's modulus, long term (drained)SiltML-CHSoft167.1ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)SiltML-CHStiff208.9313.3417.7ksfLOOK T11.7, p.152
Young's modulus, long term (drained)SiltML-CHStiff167.1240.2313.3ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)SiltML-CHHard417.7ksfLOOK T11.7, p.152
Young's modulus, long term (drained)SiltML-CHHard313.3ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHVery soft62.7ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHVery soft41.8ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHSoft41.894146.2ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHSoft20.962.7104.4ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHFirm104.4177.5250.6ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHFirm83.5125.3167.1ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHStiff208.9365.5522.1ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHStiff146.2281.9417.7ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHVery stiff417.77311,044ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHVery stiff313.3522.1731ksfLOOK T11.7, p.152
Young's modulus, short term (undrained)ClayML-CHHard835.41,2531,671ksfLOOK T11.7, p.152
Young's modulus, long term (drained)ClayML-CHHard626.6939.81,253ksfLOOK T11.7, p.152
Poisson's ratioCohesive soil (settlement analysis)CL-CH0.4–USACE para. 3-9c, p.47
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Compressibility & consolidation (50 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Coefficient of volume compressibilityHard, heavily overconsolidated glacial till, stiff weathered rocks, hard claysCL-CH / OH / PtVery low compressibility0.0024ft²/kipCB T5.1, p.108
Compression indexHard, heavily overconsolidated glacial till, stiff weathered rocks, hard claysCL-CH / OH / PtVery low compressibility0.025–CB T5.1, p.108
Coefficient of volume compressibilityStiff glacial till, marls, very stiff tropical residual claysCL-CH / OH / PtLow compressibility0.00240.00360.0048ft²/kipCB T5.1, p.108
Compression indexStiff glacial till, marls, very stiff tropical residual claysCL-CH / OH / PtLow compressibility0.0250.03750.05–CB T5.1, p.108
Coefficient of volume compressibilityFirm clays, glacial outwash clays, lake deposits, NC clays at depthCL-CH / OH / PtMedium compressibility0.00480.00960.0144ft²/kipCB T5.1, p.108
Compression indexFirm clays, glacial outwash clays, lake deposits, NC clays at depthCL-CH / OH / PtMedium compressibility0.050.10.15–CB T5.1, p.108
Coefficient of volume compressibilityPoorly consolidated alluvial clays (estuarine), sensitive claysCL-CH / OH / PtHigh compressibility0.01440.04310.0718ft²/kipCB T5.1, p.108
Compression indexPoorly consolidated alluvial clays (estuarine), sensitive claysCL-CH / OH / PtHigh compressibility0.150.450.75–CB T5.1, p.108
Coefficient of volume compressibilityHighly organic alluvial clays and peatsCL-CH / OH / PtVery high compressibility0.0718ft²/kipCB T5.1, p.108
Compression indexHighly organic alluvial clays and peatsCL-CH / OH / PtVery high compressibility0.752.8755–CB T5.1, p.108
Recompression indexClaysCL-CH0.0150.18250.35–CB T5.1 text, p.108
Secondary compression ratioPeat0.030.05750.085–USACE T3-14, p.79
Secondary compression ratioMuskeg0.090.0950.1–USACE T3-14, p.79
Secondary compression ratioInorganic soils0.0250.04250.06–USACE T3-14, p.79
Secondary compression ratioOrganic siltsOL0.0350.04750.06–CB T5.4, p.117
Secondary compression ratioAmorphous and fibrous peatPt0.0350.060.085–CB T5.4, p.117
Secondary compression ratioOrganic clays and siltsML-MH0.040.050.06–CB T5.4, p.117
Secondary compression ratioSensitive clay, Portland MECL-CH0.0250.040.055–CB T5.4, p.117
Coefficient of consolidationMedium plasticity claysCL-CH9.69ft²/yrCB T5.3, p.114
Coefficient of consolidationOrganic siltOL6.4619.432.29ft²/yrCB T5.3, p.114
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 30%ML-CHUndisturbed – virgin compression1,292ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 40%ML-CHUndisturbed – virgin compression538.2ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 50%ML-CHUndisturbed – virgin compression215.3ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 60%ML-CHUndisturbed – virgin compression107.6ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 70%ML-CHUndisturbed – virgin compression53.82ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 80%ML-CHUndisturbed – virgin compression32.29ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 90%ML-CHUndisturbed – virgin compression16.15ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 100%ML-CHUndisturbed – virgin compression10.76ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 110%ML-CHUndisturbed – virgin compression9.69ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 30%ML-CHUndisturbed – recompression215.3ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 40%ML-CHUndisturbed – recompression107.6ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 50%ML-CHUndisturbed – recompression53.82ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 60%ML-CHUndisturbed – recompression32.29ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 70%ML-CHUndisturbed – recompression21.53ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 80%ML-CHUndisturbed – recompression10.76ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 90%ML-CHUndisturbed – recompression8.61ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 100%ML-CHUndisturbed – recompression6.46ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 110%ML-CHUndisturbed – recompression5.38ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 30%ML-CHRemolded43.06ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 40%ML-CHRemolded21.53ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 50%ML-CHRemolded16.15ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 60%ML-CHRemolded10.76ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 70%ML-CHRemolded6.46ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 80%ML-CHRemolded4.31ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 90%ML-CHRemolded3.77ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 100%ML-CHRemolded3.23ft²/yrLOOK T8.14, p.122
Coefficient of consolidation vs liquid limitFine-grained soil, LL = 110%ML-CHRemolded2.69ft²/yrLOOK T8.14, p.122
Overconsolidation ratioClaysCL-CHNormally consolidated11.251.5–LOOK T7.10, p.108
Overconsolidation ratioClaysCL-CHLightly overconsolidated1.52.754–LOOK T7.10, p.108
Overconsolidation ratioClaysCL-CHHeavily overconsolidated4–LOOK T7.10, p.108
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Permeability & capillarity (7 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Coefficient of permeabilityInorganic silt, low plasticityML1.0×10⁻⁷1.0×10⁻⁶1.0×10⁻⁵cm/sLOOK T8.4, p.118
Coefficient of permeabilityInorganic silt, high plasticityMH1.0×10⁻⁷1.0×10⁻⁶1.0×10⁻⁵cm/sLOOK T8.4, p.118
Coefficient of permeabilityInorganic clay, low plasticityCL1.0×10⁻⁷1.0×10⁻⁶1.0×10⁻⁵cm/sLOOK T8.4, p.118
Coefficient of permeabilityInorganic clay, high plasticityCH1.0×10⁻⁸1.0×10⁻⁷1.0×10⁻⁶cm/sLOOK T8.4, p.118
Coefficient of permeabilityOrganic silt/clay, low plasticityOL1.0×10⁻⁶1.0×10⁻⁵1.0×10⁻⁴cm/sLOOK T8.4, p.118
Coefficient of permeabilityOrganic silt/clay, high plasticityOH1.0×10⁻⁵1.0×10⁻⁴1.0×10⁻³cm/sLOOK T8.4, p.118
Coefficient of permeabilityPeatPt1.0×10⁻⁴1.0×10⁻³1.0×10⁻²cm/sLOOK T8.4, p.118
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Subgrade support (CBR / IBR) (3 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
California bearing ratio (soaked, design)Inorganic silts, low plasticityMLDrainage: Poor5%LOOK T13.9, p.183
California bearing ratio (soaked, design)Inorganic silts (high plasticity) and claysMH, CL, CHDrainage: Good3%LOOK T13.9, p.183
California bearing ratio (soaked, design)Inorganic silts (high plasticity) and claysMH, CL, CHDrainage: Poor3%LOOK T13.9, p.183
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Laboratory test results (13 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Natural water content (saturated)Soft organic claySaturated, natural80105130%DAS T2-3, p.12
Specific gravity of soil solidsSiltsML-MH2.652.6752.7–DAS T3-1, p.14
Specific gravity of soil solidsClay and silty clayCL-CH2.672.7852.9–DAS T3-1, p.14
Specific gravity of soil solidsOrganic soilOL / OH / Pt2–DAS T3-1, p.14
Pore pressure parameter at failureClays with high sensitivityCL-CHTriaxial (CU with pore pressure)0.751.1251.5–DAS ch. 18 comments, p.134
Pore pressure parameter at failureNormally consolidated claysCL-CHTriaxial (CU with pore pressure)0.50.751–DAS ch. 18 comments, p.134
Pore pressure parameter at failureOverconsolidated claysCL-CHTriaxial (CU with pore pressure)-0.5-0.250–DAS ch. 18 comments, p.134
Pore pressure parameter at failureCompacted sandy clayCL-CHTriaxial (CU with pore pressure)0.50.6250.75–DAS ch. 18 comments, p.134
Expansion indexCompacted fine-grained soilCL-CH / MHVery low expansion potential01020–D4829-19 T1, p.2
Expansion indexCompacted fine-grained soilCL-CH / MHLow expansion potential2135.550–D4829-19 T1, p.2
Expansion indexCompacted fine-grained soilCL-CH / MHMedium expansion potential5170.590–D4829-19 T1, p.2
Expansion indexCompacted fine-grained soilCL-CH / MHHigh expansion potential91110.5130–D4829-19 T1, p.2
Expansion indexCompacted fine-grained soilCL-CH / MHVery high expansion potential130–D4829-19 T1, p.2
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
Field testing (CPT) (9 values)
PropertySoil / materialClassConditionLowTypicalHighUnitsSource
Soil behavior type indexOrganic soils – claySBT zone 23.6–ROB Fig. 22, p.35
Permeability from soil behavior typeOrganic soils – claySBT zone 21.0×10⁻⁸1.0×10⁻⁷1.0×10⁻⁶cm/sROB T6, p.56
CPT–SPT ratio (qc/pa)/N60Organic soils – claySBT zone 21–ROB T5, p.41
Permeability anisotropy kh/kvSoft clay – No or slightly developed macrofabric, essentially homogeneousCL-CH11.251.5–ROB T7, p.57
Permeability anisotropy kh/kvSoft clay – Fairly to well-developed macrofabric (discontinuous permeable lenses)CL-CH234–ROB T7, p.57
Permeability anisotropy kh/kvSoft clay – Varved clays and deposits with continuous permeable layersCL-CH3915–ROB T7, p.57
Cone factor for undrained strengthClaysCL-CHsu = (qt − σvo)/Nkt101418–ROB text, p.43
OCR factor k in OCR = k·QtClaysCL-CHKulhawy & Mayne (1990)0.20.330.5–ROB text, p.46
Assumed effective friction angleClaysCL-CHSmall to medium projects without triaxial data28degROB text, p.49
Open this group in the database, filtered by soil class ↗ (the database filter uses the USCS class only, so it can show fewer rows than this table)
References (12)
  1. BUDHU – Budhu, M. (2011). Soil Mechanics and Foundations, 3rd ed. Wiley.
  2. CB – Carter, M. & Bentley, S.P. (2016). Soil Properties and their Correlations, 2nd ed. Wiley.
  3. CRAIG – Craig, R.F. (2004). Craig's Soil Mechanics, 7th ed. Spon Press.
  4. D4829-21 – ASTM D4829-21, Expansion Index of Soils.
  5. DAS – Das, B.M. (2002). Soil Mechanics Laboratory Manual, 6th ed. Oxford University Press.
  6. DASP – Das, B.M. (2010). Principles of Geotechnical Engineering, 7th ed. Cengage.
  7. GEC5 – Sabatini, P.J. et al. (2002). FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017)), Geotechnical Engineering Circular No. 5: Evaluation of Soil and Rock Properties.
  8. IDOT – Illinois DOT (2015). Geotechnical Manual.
  9. LOOK – Look, B.G. (2007). Handbook of Geotechnical Investigation and Design Tables. Taylor & Francis.
  10. ROB – Robertson, P.K. & Cabal, K.L. (2010). Guide to Cone Penetration Testing for Geotechnical Engineering, 4th ed. Gregg Drilling & Testing.
  11. UFC322020 – U.S. Department of Defense (2025). UFC 3-220-20, Foundations and Earth Structures (NAVFAC DM-7.2), 16 January 2025.
  12. USACE – U.S. Army Corps of Engineers (1990). EM 1110-1-1904, Settlement Analysis.

Full database  ·  Laboratory tests  ·  Download Excel  ·  Library documents for this chapter  ·  Calculators for this chapter

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
2.6.0 Executive Summary

Organic soils contain enough decomposed plant matter to change their engineering behavior. Organic silts and clays (USCS OL and OH) have roughly 5% to 30% organic content; peat (PT) is mostly organic matter, usually more than 50% by dry weight, and can hold 5 to 15 times its dry weight in water.

The engineering problems are:

  • Very large settlement. Peat can compress 20% to 50% of its thickness under a few feet of fill, much of it as secondary compression that continues for decades.
  • Low strength. Undrained strength is typically 100 to 500 psf, so fills fail by bearing or sliding unless they are built slowly or supported.
  • Low and variable track modulus. Track over peat deflects more under load, so ballast, ties and rail deteriorate faster and track geometry is hard to hold.
  • Lateral spreading and bog bursts. Fill placed on peat squeezes it sideways; older lines often sit on fill that has punched deep into the bog.
  • Changes with time and drainage. Lowering the water table lets peat oxidize and shrink; acidic water corrodes steel and concrete.

This chapter gives typical values, equations and design options for organic soils and peat. First-pass values are also listed in Appendix D, Section D.5.

Use of the values in this chapter. Peat properties vary over short distances and with fiber content, decomposition and depth. Values here are for screening and preliminary design; site testing governs.
2.6.1 Background and Railroad Context

Peat forms where plant growth outpaces decay in permanently wet ground: bogs, fens, marshes and muskeg. Organic silts and clays form in quiet water with organic input: estuaries, oxbow lakes and backswamps.

Table 2.6-1: Organic Deposits Found on Railroad Lines
DepositTypical settingRailroad experience
Muskeg and bog peatCanadian Shield, northern Minnesota, Wisconsin and Michigan, Maine, AlaskaLines built across bogs on log corduroy or brush mats; continued settlement and repeated raising with ballast and fill
Coastal and estuarine organic clay and peatAtlantic and Gulf coasts, Florida, Louisiana, Pacific NorthwestLong bridge approaches and causeways; slow settlement of approach fills
Floodplain organic silt and backswamp depositsMississippi and other large river valleysSoft organic layers within alluvium; differential settlement at bridges
Buried peat lensesGlacial terrain, old lake and pond basinsUnexpected soft spots found by track defects; often missed between borings
Organic fill and topsoil left under old embankmentsOlder lines built without strippingLong-term settlement and soft shoulders

Track over peat typically shows a long, irregular sag that needs repeated surfacing, low track modulus and visible pumping of the track structure under passing trains. Older embankments over bogs can be many times thicker than they appear because decades of raising have driven fill into the peat.

2.6.2 Identification and Classification
Table 2.6-2: Classification by Organic Content (ASTM D2974 ash content)
Organic content (% of dry mass)ClassificationUSCS
< 5Mineral soil with organic tracesNormal group with “with organic” descriptor
5–30Organic silt or organic clayOL (LL < 50) or OH (LL ≥ 50)
30–75Very organic soil or sapric (amorphous) peatPT or OH
> 75PeatPT

USCS identifies organic silt and clay by the liquid limit of the oven-dried sample being less than 0.75 times that of the natural sample (ASTM D2487). Organic content is measured by loss on ignition at 824°F (440°C) (ASTM D2974).

Table 2.6-3: Peat Classification by Fiber Content (ASTM D4427)
Peat typeFiber content (% by dry mass)DescriptionEngineering behavior
Fibric> 67Least decomposed; plant structure visibleHigh permeability initially; high apparent friction; very large but rapid primary compression
Hemic33–67Partly decomposedIntermediate
Sapric< 33Most decomposed; amorphous, smoothLow permeability; behaves like organic clay; slower consolidation

Fiber content per ASTM D1997. The von Post humification scale (H1 to H10) is a field equivalent: H1–H3 fibric, H4–H6 hemic, H7–H10 sapric.

Field identification

Organic soils are dark brown to black, have a distinct odor (often hydrogen sulfide in coastal deposits), feel spongy, and change color on exposure to air. Peat floats or nearly floats in water when dried. Probing with a steel rod or a hand vane is the fastest way to map peat thickness between borings.

2.6.3 Typical Index and Physical Properties
Table 2.6-4: Typical Properties of Organic Soils and Peat
PropertyOrganic silt/clay (OL/OH)Sapric (amorphous) peatFibric peat
Organic content (%)5–3050–7575–98
Natural water content, w (%)40–200200–600500–1,500
Bulk unit weight, γ (pcf)85–10562–7558–68
Specific gravity, Gs2.30–2.651.6–2.01.4–1.7
Initial void ratio, e01.5–54–108–20
Liquid limit (natural sample)40–150150–500Not meaningful
Permeability, k (ft/day), initial0.0003–0.030.003–0.30.3–30 (falls by 100 to 1,000 times under load)
pH5–74–63.5–6

Ranges compiled from Mesri and Ajlouni (2007), Edil and den Haan (1994), MacFarlane (1969) and Landva and Pheeney (1980).

Water content and unit weight

Below the water table peat is close to saturated, so its unit weight is barely above that of water (62.4 pcf). The effective stress in a peat layer is therefore very small: under 10 ft of peat with the water table at the surface, the effective stress at the base is only about 25 to 125 psf. That is why even a few feet of fill increases the effective stress many times over and causes large settlement.

γsat = Gs (1 + w) γw1 + w Gs

Eq. 2.6-1 (saturated soil; w as a decimal)

For fibric peat with Gs = 1.5 and w = 800%, Eq. 2.6-1 gives γsat ≈ 65 pcf. Gas from decomposition often keeps peat below full saturation, so measure the unit weight of samples rather than computing it.

2.6.4 Compressibility and Secondary Compression

Peat compresses in three overlapping stages: immediate compression as gas and free water are expelled, primary consolidation (often complete in days to weeks because fibric peat is initially permeable) and secondary compression that continues at a nearly constant rate per log cycle of time for decades. In design, secondary compression of peat is often as large as the primary settlement.

Table 2.6-5: Typical Compressibility of Organic Soils and Peat
ParameterOrganic silt/clayAmorphous peatFibric peat
Compression ratio, Cc/(1 + e0)0.15–0.350.30–0.500.35–0.60
Compression index, Cc0.4–1.52–64–15
Cα/Cc0.05 ± 0.010.06 ± 0.010.06 ± 0.01
Cα/(1 + ep), secondary compression ratio0.008–0.020.015–0.030.02–0.04
Time to end of primary in the fieldMonths to yearsWeeks to monthsDays to weeks

After Mesri and Godlewski (1977), Mesri, Stark, Ajlouni and Chen (1997) and Mesri and Ajlouni (2007). Cα/Cc is the most stable parameter and is used to estimate Cα from Cc at the final stress.

Cc ≈ 0.0115 wn (organic soils)     Cc ≈ 0.01 wn (peat), wn in %

Eq. 2.6-2 (after Mesri and Ajlouni 2007 and Holtz, Kovacs and Sheahan 2011)

Sp = H Cc1 + e0 log σ′v0 + Δσσ′v0      Ss = H Cα1 + ep log ttp

Eq. 2.6-3 (primary and secondary settlement)

  • Strains in peat are large (20% to 50%), so small-strain log formulas overpredict at very large stress ratios. Compute layer by layer in sublayers no thicker than 2 to 3 ft, and check results against large-strain consolidation tests.
  • Submergence: as the fill settles below the water table, the submerged part becomes buoyant and the load on the peat decreases. Iterate: settlement reduces the effective fill load by about γw times the settlement below the water table.
  • Surcharging reduces long-term secondary compression: removing a surcharge after primary consolidation under the higher load leaves the peat effectively overconsolidated, and secondary compression restarts slowly.
  • Secondary compression continues regardless of drainage; wick drains speed primary consolidation but not secondary compression.
2.6.5 Shear Strength

Peat strength is low and difficult to measure. Fibers act as reinforcement, so laboratory friction angles of 40° to 60° are commonly measured in fibric peat, but those values are not usable directly in stability analysis because the strain needed to mobilize them is far larger than the fill can tolerate.

Table 2.6-6: Typical Strength Parameters of Organic Soils and Peat
ParameterOrganic silt/clayAmorphous peatFibric peat
Undrained strength, su (psf), natural ground150–600100–400100–300 (field vane; often unreliable)
su/σ′v0 (normally consolidated)0.25–0.350.3–0.50.3–0.6
Effective friction angle, φ′ (deg), design25–3228–3530–40 (laboratory values higher)
Sensitivity, St2–52–52–10

Ranges compiled from Mesri and Ajlouni (2007), Edil and den Haan (1994) and Landva and Pheeney (1980). The strength ratio of peat is commonly reported higher than that of inorganic clay; confirm for each site with field vane and laboratory tests.

Bearing check for fill on peat

Hmax = 5.14 suγfill FS

Eq. 2.6-4 (wide fill, undrained; same form as Eq. 2.5-10)

  • With su = 200 psf, γfill = 120 pcf and FS = 1.3, Hmax ≈ 6.6 ft. Most fills on peat therefore need staged construction, berms, reinforcement or lightweight fill.
  • Strength increases quickly as peat consolidates because its strength ratio is high and fibric peat drains fast; staged construction with short hold periods works well when monitored with piezometers.
  • The field vane in fibric peat can be distorted by fibers; correct and interpret with care, and use CPTu and back-analysis of trial fills where possible.
2.6.6 Railroad Design Options Over Peat
Table 2.6-7: Options for Track and Embankments Over Peat and Organic Soil
OptionHow it worksBest forCautions
Excavate and replaceRemove peat and backfill with granular soilPeat less than about 10 to 15 ft thick; new alignmentsTrack outage; dewatering; disposal of peat; soft bottom
DisplacementPush fill through the peat by end-dumping, sometimes with blastingShallow bogs with a firm basePeat pockets left in the fill cause long-term settlement
Preloading and surchargingPlace fill above grade, wait for primary consolidation, then remove the surchargeMost cases where time is availableStability during loading; monitoring; secondary compression continues
Lightweight fillReduce the added load with expanded polystyrene (EPS) geofoam (1 to 2 pcf), expanded shale or clay aggregate (about 45 to 65 pcf), tire-derived aggregate (about 45 to 60 pcf) or wood chipsWidening and raising existing track; limiting settlementEPS buoyancy and fuel resistance; cover thickness; tire-derived aggregate layer limits for heating
Basal geosynthetic reinforcementHigh-strength geotextile or geogrid at the base spreads the load and resists spreadingFills where stability governsDoes not reduce settlement
Column-supported embankmentPiles, rigid inclusions or deep mixed columns with a load transfer platformHigh fills; tight settlement limits; bridge approachesCost; drag on piles
Mass stabilizationMix binder (cement or cement with slag) into the peat in placeShallow peat up to about 15 to 20 ftLaboratory mix design required; high binder demand in fibric peat
Floating track on matsDistribute load with log corduroy, timber or geosynthetic matsHistoric practice; temporary accessOngoing settlement and maintenance
CAD drawing sheet showing preferred bricklayer and herringbone GEOTERRA mat layout patterns, a side-to-side temporary layout, the GEOTERRA material specificatio
Photo 2.6.6-1. Typical GEOTERRA Mat Layouts — including the Material Specification table and Unit Dimensions diagram. Presto Geosystems, GEOTERRA–A1.DWG.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
CAD drawing sheet showing the PadLoc connection device detail, the GEOTERRA earth anchor detail, and a labeled GEOTERRA system cross-section
Photo 2.6.6-2. GEOTERRA System Components — PadLoc® Connection Device detail, Earth Anchor detail, and system cross-section. Presto Geosystems, GEOTERRA–B1.DWG.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
CAD drawing sheet showing five labeled GEOTERRA typical cross-section designs, from a basic non-woven geotextile layer up to a full drainage-cell assembly with
Photo 2.6.6-3. GEOTERRA Design Guidelines — five typical cross-section designs, from Design 1 (units and connection device only) up to Design 5 (units, drainage cell, and dual high-strength/non-woven geotextile layers), with their typical applications. Presto Geosystems, GEOTERRA–C1.DWG.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Photograph of the T-handled Torsion Tool, a long thin metal rod with a slotted end and a perpendicular T-shaped handle
Photo 2.6.6-4. Torsion Tool. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Photograph of the Earth Anchor Drive Rod, a long thin metal rod with a red protective cap at the striking end
Photo 2.6.6-5. Earth Anchor Drive Rod. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Photograph of the Earth Anchor Set Tool, a T-handled rod with a length of chain ending in a hook
Photo 2.6.6-6. Earth Anchor Set Tool. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
CAD drawing sheet showing four GEOTERRA pre-assembled mat sections being connected together with connector units for truck or container transportation, plus mat
Photo 2.6.6-7. GEOTERRA Pre-Assembled Mats for Truck/Container Transportation — connecting pre-assembled mat sections with connector units, plus mat laying dimensions. Presto Geosystems, GEOTERRA–D1.DWG.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Installation of a Ringtrac geotextile encased sand column
Photo 2.6.6-8. Completed Ringtrac® geotextile encased sand column. (Photograph courtesy of Huesker, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Ringtrac geotextile encased sand columns at Muhlenberger Loch
Photo 2.6.6-9. Ringtrac® geotextile encased sand columns at Mühlenberger Loch. (Photograph courtesy of Huesker, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
VCC vibratory rig
Photo 2.6.6-10. VCC vibratory rig. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Full view of vibratory rig
Photo 2.6.6-11. Full view of vibratory rig. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
VCC installation
Photo 2.6.6-12. VCC installation. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Successive installation of VCCs
Photo 2.6.6-13. Successive installation of VCCs. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Withdrawal of vibratory probe during VCC installation
Photo 2.6.6-14. Withdrawal of vibratory probe during VCC installation. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

See Chapter 7.2 and the ground improvement technology library (Section 7.2.16) for details of each method.

Compensated fill

Where settlement must be limited, design the new load to replace the weight of material removed or to keep the added stress small:

Δσnet = Σ γi hi (new fill) − γremoved hremoved

Eq. 2.6-5 (net added stress on the peat)

For example, replacing 4 ft of soil fill (120 pcf, 480 psf) with 4 ft of lightweight aggregate (55 pcf, 220 psf) cuts the added stress by more than half; see Example 2.6-2.

2.6.7 Other Hazards of Organic Soils
HazardRecognitionEngineering response
Oxidation and shrinkage on drainageLowering the water table (new ditches, dewatering) exposes peat to airExpect continuing subsidence, commonly about 0.5 to 2 in. per year, at the surface of drained peat; avoid deep ditches next to track on peat
GasMethane and hydrogen sulfide; bubbling in borings; low unit weightVentilate excavations and confined spaces; account for low saturation in unit weight
Acidic, corrosive waterpH below 5; high sulfateCorrosion protection for steel piles and culverts; sulfate-resistant concrete
Bog bursts and lateral spreadingBulging of peat beyond the toe; tension cracks in the fillToe berms; slow loading; reinforcement
Peat firesDried peat can smolder undergroundKeep peat wet; fire watch during dry-season maintenance near bogs
FreezingFrozen peat is strong in winter and weak after thaw; peat insulates permafrostSchedule work to frozen ground conditions where possible; in permafrost regions, preserve the insulating peat layer
2.6.8 Summary of Equations
Table 2.6-8: Equations for Organic Soils in This Chapter
Eq.QuantityExpressionUse and limits
22-1Saturated unit weightγsat = Gs(1 + w)γw/(1 + wGs)Gas lowers actual value
22-2Compression indexCc ≈ 0.0115 wn (organic); 0.01 wn (peat)Screening
22-3Primary and secondary settlementSp = H Cc/(1+e0) log(σ′f/σ′0); Ss = H Cα/(1+ep) log(t/tp)Thin sublayers; large-strain check
22-4Fill height on peatHmax = 5.14 su/(γ FS)Wide fill, undrained
22-5Net added stressΔσnet = Σγh (new) − γh (removed)Compensated and lightweight fill
2.6.9 Worked Examples
The examples use generic sites and are not taken from any client project. Example 2.6-1 estimates the settlement of a track widening over peat; Example 2.6-2 shows how much lightweight fill reduces it. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 2.6-1: Settlement of a Track Widening Over Peat

A second track will be built beside a main line that crosses a bog. The existing track has sat on its fill for decades and has already consolidated the peat beneath it; the new track has not. The settlement under the new track is therefore almost all differential settlement between two tracks that must stay level with each other.

Dense sandAmorphous peat 10 ft, γ = 65 pcfCc/(1+e0) = 0.45; Cα/Cc = 0.06Existing 4-ft fillNew 4-ft fill, 120 pcfSp, Ss (30 yr) = ? Differential OK?GivenExisting fill 4 ft, 120 pcfPeat 10 ft, 65 pcf, GWT at topΔσ = 480 psfCc/(1+e0) = 0.45; Cα/Cc = 0.06tp ≈ 1 yr; t = 30 yrRequiredPrimary and secondary settlementIs the differential acceptable?Black = given; red = required
Given and required for Example 2.6-1.

Given

VariableValueDescription
Existing fill4 ft, γ = 120 pcfLow fill under the widening
Peat10 ft amorphous peat, γ = 65 pcf, over dense sandCompressible layer
zwAt the top of the peatWater table
Δσ4 ft × 120 pcf = 480 psfNew fill
Cc/(1 + e0)0.45Compression ratio of the peat
Cα/Cc0.06Secondary to primary ratio
tpAbout 1 yearEnd of primary consolidation
t30 yearsDesign life for secondary settlement

Required

  • Primary and secondary settlement under the new track
  • Whether the differential is acceptable

Equations

  1. Eq. 1: σ′v0 = Σ γh above the water table + Σ (γ − γw)h below — effective stress at mid-peat
  2. Eq. 2.6-3a: Sp = H [Cc/(1 + e0)] log[(σ′v0 + Δσ)/σ′v0] — primary settlement
  3. Eq. 2.6-3b: Ss = H [Cα/(1 + ep)] log(t/tp) — secondary settlement

Steps

Step 1 · σ′v0 at mid-peat (Eq. 1)
4(120) + 5(65 − 62.4) = 480 + 13
σ′v0 = 493 psf
Spot check: The submerged peat adds only 2.6 pcf per foot; nearly all the effective stress comes from the fill.
↓
Step 2 · Primary settlement (Eq. 2.6-3a)
10 × 0.45 × log(973/493) = 4.5 × 0.295
Sp = 1.33 ft (16 in.)
↓
Step 3 · Secondary ratio
Cα/(1 + ep) ≈ 0.06 × 0.45
0.027
↓
Step 4 · Secondary settlement, 1 to 30 years (Eq. 2.6-3b)
10 × 0.027 × log 30 = 0.27 × 1.48
Ss = 0.40 ft (5 in.)
↓
Step 5 · Total
16 + 5
About 21 in. under the new track
↓
Solution
About 21 in. under the new track; almost none under the old.

Solution

About 16 in. of primary and 5 in. of secondary settlement, about 21 in. in all, under the new track and almost none under the existing one.

That differential is not acceptable for parallel tracks. One layer is used here for illustration; peat compresses so much that a design calculation should use 2-ft sublayers, which usually gives a somewhat smaller total. Example 2.6-2 shows the first step toward reducing it.

Example 2.6-2: Lightweight Fill to Limit Settlement

Settlement on peat is driven by the added stress, so the most direct control is to add less weight. This example repeats Example 2.6-1 with lightweight aggregate in place of soil fill.

Dense sandAmorphous peat 10 ft, γ = 65 pcfCc/(1+e0) = 0.45; Cα/Cc = 0.06Existing 4-ft fillLightweight fill 4 ft, 55 pcfΔσ, Sp with LWA = ?Givenσ′v0 = 493 psf; H = 10 ftCc/(1+e0) = 0.45γLWA = 55 pcf; h = 4 ftRequiredAdded stressPrimary settlement with lightweight fillBlack = given; red = required
Given and required for Example 2.6-2.

Given

VariableValueDescription
SiteAs Example 2.6-1σ′v0 = 493 psf; H = 10 ft; Cc/(1 + e0) = 0.45
γLWA55 pcfExpanded shale lightweight aggregate
h4 ftNew fill thickness

Required

  • Added stress and primary settlement with lightweight fill

Equations

  1. Eq. 2.6-5: Δσnet = Σ γihi − γremovedhremoved — net added stress
  2. Eq. 2.6-3a: Sp = H [Cc/(1 + e0)] log[(σ′v0 + Δσ)/σ′v0] — primary settlement

Steps

Step 1 · Added stress (Eq. 2.6-5)
4 × 55
Δσ = 220 psf, against 480 psf for soil fill
↓
Step 2 · Primary settlement (Eq. 2.6-3a)
4.5 × log(713/493) = 4.5 × 0.160
Sp = 0.72 ft (9 in.)
Spot check: About half of Example 2.6-1, though the stress is less than half, because settlement follows the logarithm of the stress ratio.
↓
Solution
Sp = 9 in., about half of the soil-fill case.

Solution

Primary settlement falls to about 9 in., roughly half of Example 2.6-1. Secondary settlement continues at the same rate.

Lightweight aggregate alone does not bring the differential to an acceptable level. Further reduction needs EPS geofoam, with enough soil and ballast cover to resist buoyancy and spread the wheel load, or column support. The choice depends on the track outage available and the settlement tolerance between the tracks.

2.6.10 Representative Data Table
Table 2.6-9: Representative Design Values for Organic Soils and Peat
Materialw (%)γ (pcf)su (psf)φ′ design (deg)Cc/(1+e0)Cα/(1+ep)k (ft/day)
Organic silt (OL)40–10090–105200–60028–320.15–0.250.008–0.0150.0003–0.03
Organic clay (OH)60–20085–100150–50025–300.20–0.350.01–0.020.0003–0.003
Amorphous (sapric) peat200–60062–75100–40028–350.30–0.500.015–0.030.003–0.3
Fibric peat500–1,50058–68100–30030–400.35–0.600.02–0.040.3–30

Starting values only; replace with test data.

2.6.11 Practical Recommendations
  • Map the extent and thickness of organic soils with probing, closely spaced borings or CPTu and ground-penetrating radar; one boring is not representative of a bog.
  • Run organic content (ASTM D2974) and moisture content on every sample; classify peat by fiber content.
  • Run consolidation tests with long load increments to measure secondary compression; report Cα/Cc.
  • Compute settlement in thin sublayers and account for submergence of the fill.
  • For widenings, design for differential settlement between old and new tracks, not just total settlement.
  • Use lightweight fill, surcharging or column support where settlement must be limited; basal reinforcement only for stability.
  • Do not lower the water table next to track on peat without estimating oxidation settlement.
  • Monitor fills on peat with settlement plates, piezometers and inclinometers, and expect settlement to continue after construction.
2.6.12 Peat and Organic Soil Investigation and Design Checklist

Checklist · Part X · Problem Soils

Peat and Organic Soil Investigation and Design Checklist

Investigation0 of 5
Laboratory Testing0 of 5
Analysis and Design0 of 5
Construction and Reporting0 of 4
Ticks are saved in this browser.
2.6.13 Practice Questions
Each question is worked in the same five parts as the examples.
Question 2.6-1: Classify a Peat Sample

Problem Statement

A Class I railroad is extending a passing track across a bog, and a sample from beneath the alignment has the organic content and fiber content shown. The engineer must classify the peat and say what the classification means for compressibility and drainage under the new track.

Sapric < 33%Hemic 33–67%Fibric > 67%0100%Fiber contentsample: 45%Organic content 62% (ASTM D2974); peat if > 30%Classification = ? Compressibility and drainage?GivenOC = 62% (ash content)Fiber = 45%Peat: OC > 30%Fibric > 67; hemic 33–67; sapric < 33RequiredClassificationMeaning for compressibility and drainageBlack = given; red = required
Given and required for Question 2.6-1.

Given

VariableValueDescription
OC62%Organic content by ash content (ASTM D2974)
Fiber45%Fiber content
CriteriaTable 2.6-2 and the von Post/ASTM fiber classesPeat: organic content > 30%; fibric > 67%, hemic 33 to 67%, sapric < 33% fibers

Required

  • Classification

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · Organic soil or peat?
62% is between 30% and 75%
Peat (USCS PT)
↓
Step 2 · Degree of decomposition
45% fibers is between 33% and 67%
Hemic
↓
Solution
Hemic peat (PT).

Solution

Hemic peat, USCS PT.

Hemic peat is moderately decomposed: more compressible and less permeable than fibrous (fibric) peat, but less so than amorphous (sapric) peat. The class guides the choice of starting values in Table 2.6-9 until tests are available.

Question 2.6-2: Single-Stage Fill Height on Peat

Problem Statement

A Class I railroad needs to place fill on peat for a new siding across a bog. The peat has the undrained strength shown, and the required factor of safety is 1.3. The engineer must find the maximum fill height that can be placed in one stage.

The strip bearing screen of Example 2.5-1 applied to peat.

Peat bog, su = 250 psfFill γ = 120 pcfHmax = ?Givensu = 250 psfγ = 120 pcf (fill)FS = 1.3RequiredMaximum single-stage fill heightBlack = given; red = required
Given and required for Question 2.6-2.

Given

VariableValueDescription
su250 psfUndrained strength
γ120 pcfFill
FS1.3Required

Required

  • Maximum single-stage fill height

Equations

  1. Eq. 2.6-4: Hmax = 5.14 su / (γ FS) — wide fill, undrained; same form as Eq. 2.5-10

Steps

Step 1 · Hmax (Eq. 2.6-4)
5.14 × 250 / (120 × 1.3) = 1,285 / 156
Hmax = 8.2 ft
↓
Solution
Hmax = 8.2 ft.

Solution

About 8.2 ft of fill in one stage.

Higher fills need staged construction or lightweight fill. On peat the screen is only a starting point: peat strength varies widely over short distances, and lateral squeeze can occur before bearing failure, so the fill should be placed with settlement plates and toe inclinometers.

Question 2.6-3: Secondary Settlement of Peat Over 25 Years

Problem Statement

A railroad embankment across a peat bog completed primary consolidation six months after construction. The railroad wants to know how much more the track will settle over the next 25 years to plan surfacing. The engineer must estimate the secondary settlement of the 8-ft peat layer.

Secondary compression continues long after the excess pore pressure is gone, and in peat it is a large part of the total.

0.1110100Time (years, log)Settlementtp = 6 months25 yrSs = ?Peat H = 8 ft; Cα/(1+ep) = 0.03GivenH = 8 ftCα/(1+ep) = 0.03tp = 6 monthst = 25 yearsRequiredSecondary settlement from 6 months to 25 yearsBlack = given; red = required
Given and required for Question 2.6-3.

Given

VariableValueDescription
H8 ftPeat thickness
Cα/(1 + ep)0.03Secondary compression ratio
tp6 monthsEnd of primary consolidation
t25 yearsEnd of the period

Required

  • Secondary settlement between 6 months and 25 years

Equations

  1. Eq. 2.6-3b: Ss = H [Cα/(1 + ep)] log(t/tp) — secondary settlement

Steps

Step 1 · Time ratio
25 / 0.5
50
↓
Step 2 · Ss (Eq. 2.6-3b)
8 × 0.03 × log 50 = 0.24 × 1.70
Ss = 0.41 ft (about 5 in.)
↓
Solution
About 5 in. of secondary settlement.

Solution

About 0.41 ft (5 in.) between 6 months and 25 years.

Because settlement follows the logarithm of time, half of it (about 2.5 in.) occurs in the first 3.5 years after primary consolidation and the rest over the following 21 years. Track over peat should be expected to need surfacing for decades.

2.6.14 Cross-References
TopicRefer To
Subgrade failure modes and track modulusChapter 2.3, Sections 2.3.5–2.3.6
Consolidation settlement and preloadingChapter 6.2, Sections 6.2.4–6.2.8
Construction monitoringChapter 5.3
Ground improvement methodsChapter 7.2, Section 7.2.16
Clays (soft clay behavior)Chapter 2.5
Typical valuesAppendix D, Section D.5
2.6.15 Mass Stabilization of Peat Beside and Beneath Track

Mass stabilization mixes a dry binder, usually portland cement, into peat or soft organic soil in place, turning it into a stiff cement-modified soil without excavation. It was developed in Scandinavia and is now used in the northern United States and Canada. The track applications described in a 2014 conference paper include treated zones along both sides of an embankment to confine it, treated pads that act as working platforms for pile rigs, column walls that damp train vibration, and treated embankment beside a lake to carry heavier freight. Excavator-mounted power mixers with a pressure feeder suit railway work to about 25 ft; crane-supported augers go deeper. High-rail excavators allow spot treatment along an operating line.

2.6.15.1 Design quantities

Table 2.6-10. Published mass stabilization data
ItemValue
Binder addition rate, typical range100 to 350 lb per cu yd
Peat and silt beside a high-speed line, sulfate-resistant cement170 lb/cu yd (100 kg/m³) gave about 5 psi (40 kPa) shear strength
Working platform for 55-ton (50-tonne) pile rigs, ordinary cement340 lb/cu yd (200 kg/m³), 15 ft thick
Embankment beside a lake500 ft long, 30 ft wide, 23 ft deep
Binder share of project cost50 to 70%

Dry injection uses the water already in the soil and generally needs less cement than wet grout mixing, whose water-cement ratio must exceed 1 to be pumpable.

The addition rate is set by a bench-scale mix design: several binders and rates are mixed into samples of the actual soil, cured and tested for strength and, where needed, permeability. Because binder dominates the cost, the cheapest mix that meets the strength target is chosen. GPS-guided mixing heads with metered binder feed record each block for quality control.

2.6.15.2 Worked example: treated strip beside an embankment

Table 2.6-11. 500 ft × 30 ft × 23 ft deep at 170 lb/cu yd (calculator output)
ResultValue
Treated volume12,778 cu yd
Cement1,086 tons
Per foot of track2.17 tons/ft
Addition rate101 kg/m³

About 1,100 tons of cement for 500 ft of track shows why the binder rate must come from testing rather than a rule of thumb: each 10 lb/cu yd saved removes about 64 tons here. Settlement of untreated peat under fill is covered in Chapter 6.2; the alternative of floating the track on helical piles is described in a 2018 conference paper listed below.

Open the mass stabilization calculator →
Treated volume, binder tonnage at a chosen addition rate, binder per foot of track, and an order-of-magnitude cost from the binder share.

Example 2.6-3: Binder Quantity for a Mass-Stabilized Strip

This is the strip of Table 2.6-11, worked by hand. Binder is 50 to 70% of the cost of mass stabilization, so the quantity, and how sensitive it is to the addition rate, is the first number an owner needs.

Mass-stabilizedblockW = 30 ftD = 23 ftL = 500 ftVolume = ? Cement tons, per ft, metric = ?Binder r = 170 lb/cu ydGivenL × W × D = 500 × 30 × 23 ftr = 170 lb/cu ydRequiredTreated volumeCement tonnage, per ft of track, and in metric unitsBlack = given; red = required
Given and required for Example 2.6-3.

Given

VariableValueDescription
L × W × D500 ft × 30 ft × 23 ftTreated block beside the embankment
r170 lb/cu ydBinder addition rate

Required

  • Treated volume
  • Cement tonnage, per foot of track, and in metric units

Equations

  1. Eq. 1: V = L W D / 27 — cubic yards
  2. Eq. 2: B = V r / 2,000 — tons of binder
  3. Eq. 3: 1 lb/cu yd = 0.593 kg/m³ — unit conversion

Steps

Step 1 · Volume (Eq. 1)
500 × 30 × 23 / 27 = 345,000 / 27
V = 12,778 cu yd
↓
Step 2 · Binder (Eq. 2)
12,778 × 170 / 2,000
B = 1,086 tons; 1,086 / 500 = 2.17 tons/ft
↓
Step 3 · Metric rate (Eq. 3)
170 × 0.593
101 kg/m³
↓
Step 4 · Sensitivity
12,778 × 10 / 2,000
Each 10 lb/cu yd changes the binder by about 64 tons
↓
Solution
12,778 cu yd; 1,086 tons of cement; 2.17 tons per foot.

Solution

12,778 cu yd treated; 1,086 tons of cement, or 2.17 tons per foot of track, at 101 kg/m³.

At this scale every 10 lb/cu yd saved removes about 64 tons of cement, which is why the addition rate is set by a bench-scale mix design on the actual peat rather than by a rule of thumb.

2.6.15.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • AREMA conference paper (2014): stabilization of marginal soil in new and existing right-of-way (mass stabilization, Finnish rail projects).Find source ↗
  • AREMA conference paper (2015): rapid subgrade stabilization by injection on high-volume main line over peat and organic silt.Find source ↗
  • AREMA conference paper (2018): track support on a floating soil beam carried by helical piles.Find source ↗
  • AREMA conference paper (2012): settlement of a passenger maintenance yard built on fill over bay mud.Find source ↗
  • AREMA Manual for Railway Engineering, Chapter 1 Roadway and Ballast (2012, Volume 1), Part 1, Section 1.6 Alternative ground improvement methods.Official page ↗
Author and Sources

Author: Daniel P. Colwell. This chapter was written and compiled by Daniel P. Colwell for Railway Ground Hazard Risk Management from the published sources below; credit for that material belongs to their authors and publishers. It contains no client- or project-specific data.

Sources

  • Edil, T. B. and den Haan, E. J. (1994). “Settlement of Peats and Organic Soils.” Vertical and Horizontal Deformations of Foundations and Embankments, ASCE GSP 40Find source ↗
  • FHWA (2017). Ground Modification Methods Reference Manual, GEC 13, FHWA-NHI-16-027/028Find source ↗
  • Holtz, R. D., Kovacs, W. D. and Sheahan, T. C. (2011). An Introduction to Geotechnical Engineering, 2nd ed. PearsonFind source ↗
  • Landva, A. O. and Pheeney, P. E. (1980). “Peat Fabric and Structure.” Canadian Geotechnical Journal, 17(3)Find source ↗
  • MacFarlane, I. C. (ed.) (1969). Muskeg Engineering Handbook. University of Toronto PressFind source ↗
  • Mesri, G. and Godlewski, P. M. (1977). J. Geotech. Eng. Div., 103(GT5)Find source ↗
  • Mesri, G., Stark, T. D., Ajlouni, M. A. and Chen, C. S. (1997). “Secondary Compression of Peat with or without Surcharging.” J. Geotech. Geoenviron. Eng., 123(5)Find source ↗
  • Mesri, G. and Ajlouni, M. (2007). “Engineering Properties of Fibrous Peats.” J. Geotech. Geoenviron. Eng., 133(7)Find source ↗
  • ASTM D1997, D2487, D2974, D4427, D2435Official page ↗

Photograph credits

The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.

  1. Photo 2.6.6-1 — Typical GEOTERRA Mat Layouts — including the Material Specification table and Unit Dimensions diagram. Presto Geosystems, GEOTERRA–A1.DWG. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  2. Photo 2.6.6-2 — GEOTERRA System Components — PadLoc® Connection Device detail, Earth Anchor detail, and system cross-section. Presto Geosystems, GEOTERRA–B1.DWG. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  3. Photo 2.6.6-3 — GEOTERRA Design Guidelines — five typical cross-section designs, from Design 1 (units and connection device only) up to Design 5 (units, drainage cell, and dual high-strength/non-woven geotextile layers), with their typical applications. Presto Geosystems, GEOTERRA–C1.DWG. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  4. Photo 2.6.6-4 — Torsion Tool. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  5. Photo 2.6.6-5 — Earth Anchor Drive Rod. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  6. Photo 2.6.6-6 — Earth Anchor Set Tool. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  7. Photo 2.6.6-7 — GEOTERRA Pre-Assembled Mats for Truck/Container Transportation — connecting pre-assembled mat sections with connector units, plus mat laying dimensions. Presto Geosystems, GEOTERRA–D1.DWG. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  8. Photo 2.6.6-8 — Completed Ringtrac® geotextile encased sand column. (Photograph courtesy of Huesker, Inc.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  9. Photo 2.6.6-9 — Ringtrac® geotextile encased sand columns at Mühlenberger Loch. (Photograph courtesy of Huesker, Inc.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  10. Photo 2.6.6-10 — VCC vibratory rig. (Photograph courtesy of James Collin.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  11. Photo 2.6.6-11 — Full view of vibratory rig. (Photograph courtesy of James Collin.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  12. Photo 2.6.6-12 — VCC installation. (Photograph courtesy of James Collin.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  13. Photo 2.6.6-13 — Successive installation of VCCs. (Photograph courtesy of James Collin.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗
  14. Photo 2.6.6-14 — Withdrawal of vibratory probe during VCC installation. (Photograph courtesy of James Collin.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.GeoTechTools.org ↗