2.5.12 Worked Examples

Clay is the soil whose behavior depends most on water and time: it is strong when dry and weak when wet, it consolidates for years under new fill, it swells and shrinks with the seasons, and in cut slopes it slowly loses strength until it slides.
Author: Daniel P. Colwell
2.5.12 Worked Examples
The examples use generic sites and are not taken from any client project. They cover the three clay questions that decide most railroad designs: how high can fill go, how much will it settle and how fast, and will the clay swell. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 2.5-1: Maximum Embankment Height on Soft Clay

A siding embankment is to be built on soft clay. Before any detailed analysis, the undrained bearing capacity of a strip load gives the height the clay can carry in one placement at the end of construction, which is when an embankment on soft clay is weakest.

Soft clay, su = 400 psf (vane-corrected)Fill γ = 125 pcfHmax = ?Nc = 5.14Givensu = 400 psfγ = 125 pcf (fill)FS = 1.3 end of constructionNc = 5.14RequiredMaximum one-stage height Hmax Black = given; red = required
Given and required for Example 2.5-1.

Given

VariableValueDescription
su400 psfField-vane-corrected undrained strength, fairly uniform with depth
γ125 pcfFill unit weight
FS1.3Required end-of-construction factor of safety
Nc5.14Bearing capacity factor, strip load, φ = 0

Required

  • Maximum height Hmax that can be built in one stage

Equations

  1. Eq. 2.5-10: Hmax = Nc su / (γ FS) — bearing capacity of a strip load on undrained clay

Steps

Step 1 · Capacity Nc su
5.14 × 400
2,056 psf
↓
Step 2 · Demand per foot of fill, with FS
125 × 1.3
162.5 psf per ft
↓
Step 3 · Hmax (Eq. 2.5-10)
2,056 / 162.5
Hmax = 12.7 ft
Spot check: 12.7 × 125 = 1,588 psf; 2,056 / 1,588 = 1.29.
↓
Solution
Hmax = 12.7 ft.

Solution

The clay can carry about 12.7 ft of fill in one stage at FS = 1.3.

A 16-ft embankment would need staged construction (Section 2.5.7.2), berms or ground improvement. The screen ignores the crust, the strength increase with depth and the actual side slopes, so confirm it with a limit-equilibrium analysis of the real geometry and strength profile (Section 6.3.3).

Example 2.5-2: Settlement of a Lightly Overconsolidated Clay

The settlement of a clay depends strongly on where the new stress sits relative to the preconsolidation stress. Below it the clay is stiff (recompression index); above it the clay is soft (compression index). This example shows how much the measured preconsolidation stress changes the answer.

New fill: Δσ = 1,500 psfClay 12 ft, drained top and bottome0 = 1.05; Cc = 0.45; Cr = 0.06; cv = 0.5 ft²/dσ′v0 = 1,200; σ′p = 1,800 psf (OCR 1.5)Sc with / without σ′p = ? t50, t90 = ?GivenH = 12 ft, two-way drainagee0 1.05; Cc 0.45; Cr 0.06cv = 0.5 ft²/dayσ′v0 1,200; σ′p 1,800 psfΔσ = 1,500 psfRequiredSc with and without σ′p Times to 50% and 90%Black = given; red = required
Given and required for Example 2.5-2.

Given

VariableValueDescription
H12 ft, drained top and bottomClay layer
e01.05Initial void ratio
Cc, Cr0.45 and 0.06Compression and recompression indices
cv0.5 ft²/dayCoefficient of consolidation
σ′v01,200 psfEffective stress at mid-layer
σ′p1,800 psf (OCR = 1.5)Preconsolidation stress
Δσ1,500 psfStress increase from new fill

Required

  • Consolidation settlement, with and without the measured σ′p
  • Times to 50% and 90% consolidation

Equations

  1. Eq. 2.5-8: S = [H/(1 + e0)][Cr log(σ′p/σ′v0) + Cc log(σ′f/σ′p)] — for σ′f = σ′v0 + Δσ > σ′p
  2. Eq. 2.5-9: t = Tv Hdr² / cv — T50 = 0.197; T90 = 0.848

Steps

Step 1 · Final stress
1,200 + 1,500
σ′f = 2,700 psf > σ′p: the clay passes into virgin compression
↓
Step 2 · Settlement with measured σ′p (Eq. 2.5-8)
(12/2.05)[0.06 log(1.5) + 0.45 log(1.5)] = 5.85 [0.0106 + 0.0792]
S = 0.53 ft = 6.3 in.
Spot check: log 1.5 = 0.176 appears in both terms because 1,800/1,200 and 2,700/1,800 are both 1.5.
↓
Step 3 · Settlement if assumed normally consolidated
5.85 × 0.45 × log(2,700/1,200) = 5.85 × 0.45 × 0.352
S = 0.93 ft = 11.1 in.
↓
Step 4 · Time (Eq. 2.5-9)
Hdr = 6 ft; t50 = 0.197 × 36 / 0.5; t90 = 0.848 × 36 / 0.5
t50 = 14 days; t90 = 61 days
↓
Solution
S = 6.3 in. (11.1 in. if assumed NC); t90 = 61 days.

Solution

Settlement 6.3 in., 90% complete in about 61 days. Assuming the clay normally consolidated would give 11.1 in.

Measuring the preconsolidation stress nearly halves the estimate. That is the strongest argument for consolidation tests on undisturbed samples: a correlation for Cc alone would have missed the stiff recompression range entirely. With drainage at both faces the settlement is largely complete within one construction season.

Example 2.5-3: Screening an Expansive Clay Subgrade

A cut for a new connecting track exposes high-plasticity clay. Before swell tests are run, three screens are used to decide whether the clay should be treated as expansive: activity, the Chen classification from index data and blow count, and the Seed et al. swell estimate.

102030405060708090102030405060A-lineU-lineCLCHMLMH or OHLL = 50Liquid limit, LL (%)Plasticity index, PI (%)Cut CH: LL 68, PI 45Activity, swell class = ?GivenCH; LL 68, PI 45F = 97%; CF = 52%N = 22Chen (1988) tableRequiredActivityExpansion class and swell potentialRecommended treatmentBlack = given; red = required
Given and required for Example 2.5-3.

Given

VariableValueDescription
SoilCHExposed in the cut
LL, PI68 and 45Atterberg limits
F97%Passing the No. 200 sieve
CF52%Clay fraction, finer than 2 μm
N22SPT blow count
Chen (1988)Fines > 95%, LL > 60, N 20 to 30: high to very high expansionClassification table (Section 2.5.9)

Required

  • Activity
  • Expansion class and estimated swell potential
  • Recommended treatment

Equations

  1. Eq. 2.5-2: A = PI / CF — Skempton activity
  2. Eq. 2.5-11: S (%) = 2.16 × 10−3 PI2.44 — Seed, Woodward and Lundgren, compacted soil

Steps

Step 1 · Activity (Eq. 2.5-2)
45 / 52
A = 0.87: normal activity
↓
Step 2 · Chen classification
F = 97% > 95%; LL = 68 > 60; N = 22
High to very high expansion
↓
Step 3 · Swell potential (Eq. 2.5-11)
2.16×10−3 × 452.44 = 2.16×10−3 × 10,800
S ≈ 23% for compacted soil
Spot check: ln 45 = 3.81; 2.44 × 3.81 = 9.29; e9.29 ≈ 10,800.
↓
Solution
Treat as highly expansive.

Solution

Activity 0.87 (normal), but Chen rates the clay high to very high and the Seed et al. estimate is about 23% swell. Treat it as highly expansive.

Normal activity does not clear a clay with a PI of 45: the amount of clay matters as much as its mineral. Run ASTM D4546 swell tests at the design overburden, test for sulfates before choosing lime, and plan lime stabilization of the top 12 to 18 in. of subgrade with shoulder moisture control. Do not use this CH as embankment fill near the subgrade surface.