2.5.1 Background and Railroad Context

Clay is the soil whose behavior depends most on water and time: it is strong when dry and weak when wet, it consolidates for years under new fill, it swells and shrinks with the seasons, and in cut slopes it slowly loses strength until it slides.
Author: Daniel P. Colwell
2.5.1 Background and Railroad Context
Table 2.5-1: Clay Deposits Found on Railroad Lines
DepositTypical settingCharacteristic behavior
Soft alluvial and estuarine clayRiver crossings, coastal lines, bridge approachesNormally consolidated, low strength, large and slow settlement; undrained failure under new fill
Glacial lake and marine clayGreat Lakes basin, northern plains, St. Lawrence valley, eastern CanadaVarved or sensitive; quick clays prone to retrogressive flow slides along valleys
Glacial till (lean clay matrix)Northern U.S. and CanadaStiff, overconsolidated, with cobbles and boulders; generally good foundation; perched water in sand lenses
Overconsolidated and fissured clays and clay shalesPlains and Gulf coast (for example Pierre, Bearpaw, Yazoo, Taylor and Eagle Ford formations)Strength loss with time in cuts; expansive; progressive and reactivated landslides
Expansive residual and alluvial claysTexas, Colorado, the Dakotas, the southeast Gulf coast and the prairiesSeasonal heave and shrinkage; track geometry defects; cracking of structures
Residual clay over rockPiedmont, Appalachians, karst regionsVariable thickness over pinnacled rock; may hide voids in karst
Clay fillOlder embankments built from the nearest cutVariable density; softening and shoulder failures; ballast pockets

On an operating railroad, clay problems usually appear first as recurring track surface and alignment defects: soft track that will not hold surface, ballast pockets, bulging shoulders, slow slides in cuts after wet years, or seasonal heave in a dry year followed by a wet one. Chapter 2.3, Section 2.3.5 describes the subgrade failure modes and Chapter 3.8, Section 3.8.3 the slope mechanisms.