6.2.8 Preloading and Surcharge Design

Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 6.1.
Authors: Daniel P. Colwell and Mario Ruel
6.2.8 Preloading and Surcharge Design

When predicted settlement S_c exceeds the client's allowable limit, preloading with temporary surcharge fill is the most cost-effective mitigation. The concept: apply a surcharge load greater than the permanent design load, allow consolidation to occur before track placement, then remove the surcharge and install track on a pre-compressed subgrade.

Schematic of the vacuum consolidation process with PVDs, showing the impervious membrane, vacuum pumps, and peripheral trenches
Photo 6.2.8-1. Vacuum Consolidation Process with PVDs, showing the impervious membrane, vacuum gas phase booster and air/water pump, horizontal and vertical vacuum transmission pipes, and peripheral trenches filled with bentonite and polyacrylate. (Figure from Masse et al. 2001)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Sand platform and geotextile being installed at a vacuum preloading site
Photo 6.2.8-2. Sand Platform and Geotextile. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Horizontal drain connections laid in a trench
Photo 6.2.8-3. Horizontal Drain Connection. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Worker welding the vacuum preloading membrane
Photo 6.2.8-4. Installing the Membrane. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Water-filled peripheral sealing trench around a vacuum preloading site
Photo 6.2.8-5. Peripheral Trench. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Row of vacuum pumps at a preloading site
Photo 6.2.8-6. Vacuum Pumps. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Additional fill being placed for membrane protection
Photo 6.2.8-7. Additional Fill Being Placed for Membrane Protection. (Photograph from www.menardusa.com, courtesy of DGI-Menard, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
General layout drawing of the sewage treatment plant site improved by vacuum preloading
Photo 6.2.8-8. Sewage Treatment Plant General Layout, west of Pusan City, South Korea. (Figure from Masse et al. 2001.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Settlement versus time chart showing post-vacuum rebound at the Pusan case history site
Photo 6.2.8-9. Post Vacuum Rebound — recorded settlement approaching the 11.8-ft (3.61 m) target through November–December 1996, showing the brief rebound after the vacuum was stopped and the surcharge removed. (Figure from the Pusan, South Korea case history.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Equation 6.2-18 — Required Surcharge Pressure:

σ'_v0 + Δσ_p + Δσ_s = σ'_v0 × 10^[S_target(1 + e₀)/(C_c H)], where S_target = primary settlement plus expected secondary compression under the permanent load, and Δσ_s is the required surcharge (NC clay)

A simplified approach: select q_surcharge such that primary consolidation under q_surcharge equals the sum of primary consolidation + secondary compression expected under q_permanent over the service life. Make this calculation for bridge approach fills where predicted settlement exceeds about 2 in.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IX-05 Secondary compression ratio C_αUse: Secondary consolidation of soft soils; the ratio holds at a given effective stress level. Limits: Use Cc corresponding to the final stress (Cc varies with stress in structured clays).
Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
Cccompression indexLab testSlope of the virgin e–log σ' curve from a consolidation test (ASTM D2435). Screening: Cc ≈ 0.009(LL − 10).CL 0.10–0.40, CH 0.35–0.90 · by USCS group
Equation 6.2-19 — Time for Surcharge to Achieve U = 90%:

t_surcharge = 0.848 · H_dr² / cv

If t_surcharge is prohibitively long (> 6–12 months on a construction schedule), prefabricated vertical drains (PVDs) are combined with the surcharge to accelerate drainage — addressed in Chapter 7.2 (Ground Improvement).

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
cvcoefficient of consolidationLab test (or field)Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests.CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group
Supplemental reference

Field record: preloading, drains and excavation over peat

Lea and Brawner’s case histories from the Vancouver area test the assumptions behind Eq. 6.2-18 and 6.2-19:

  • Surcharge works. At Lougheed Highway and Boundary Road (1958), about 1,200 ft of road over up to 14 ft of peat was brought to grade plus a 5-ft surcharge, carried traffic on a temporary surface for three months, then was paved. Settlement plates and piezometers controlled the rate of construction. No differential settlement or pavement failure appeared in the first four years.
  • Vertical drains in peat may not perform as calculated. At Maillardville (1954), 18-in. sand drains at 15-ft triangular spacing were calculated to raise the settlement rate at least eightfold; measured primary settlement was only about 15% faster. Check drain performance in peat with a test section before relying on it in the schedule.
  • Rigid structures in a settling fill create bumps. On the same project, culverts on piles did not settle with the grade, and severe bumps formed at every culvert within a few months. The same applies to pile-supported culverts and pipe crossings under a new railroad embankment on soft ground.
  • Excavate-and-replace is only as good as the cleanup. On the Deas Tunnel Throughway, peat 6–11 ft deep was excavated and replaced with dredged sand. Within a year pockets of peat and organic silt left in place caused up to 3 in. of differential settlement over 50 ft.

Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board

Supplemental reference

Lightweight fill: reducing the load instead of waiting for it

When surcharge time is not available, or added fill would cause a stability failure, the alternative is to reduce Δσ itself. Three generations of lightweight fill appear in the library:

Table 12-S3. Lightweight fill options

MaterialKey propertiesDesign notes
Sawdust (historic; Trans-Canada Highway, Burnaby)3–12 ft thick; compressed to 80–90% of placed thickness under about ½ tsf preload; lab φ = 50°Rots and can spontaneously combust above the water table, so the top must end up below groundwater after settlement. Settlement had to be predicted accurately to place it at the right grade.
Expanded shale, clay or slate (ESCS) lightweight aggregateKiln-expanded at 1,900–2,200°F; relative density 1.3–1.6 vs. 2.6–3.0 for normal aggregate (about half the mass per volume); AASHTO M 195 gradationsOpen-graded; still needs compaction (lifts ≤ 12 in. loose with vibratory roller). Density control by a one-point Proctor (modified ASTM D698) plus a method spec.
EPS geofoam (ASTM D6817)EPS 15 / 19 / 22 / 29: minimum density 0.90 / 1.15 / 1.35 / 1.80 pcf; compressive resistance at 10% strain 10.2 / 16.0 / 19.6 / 29.0 psi“Zero net load”: excavate native soil equal in weight to the geofoam plus everything placed on it. It can also replace the active wedge behind an abutment.

Case: US 17 / SC 707, Myrtle Beach, SC. At the nearby Fantasy Harbour project, embankments 10–42 ft high had settled 9 to 67 in. For the US 17 / SC 707 interchange, bridge approach fills over 30–60 ft of soft to firm clay and loose, liquefiable sands were estimated to settle 78 in. at the abutment if built with normal-weight fill (120 pcf). The design combined LWA borrow to cut the magnitude, PVDs with granular surcharge to speed it, and deep soil mixing for seismic slope stability and abutment performance.

Railroad cautions (engineering judgment, not from the sources): lightweight fills must be covered by enough ballast, subballast and soil to spread axle loads and resist buoyancy at flood stage. Geofoam must be protected from petroleum spills (hydrocarbon-resistant membrane) near fueling or derailment-prone areas. Confirm dynamic stiffness under E-80 loading before using any lightweight fill directly under track.

Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board · Speck, J. and Wall, J. Use of Lightweight Aggregate Fill in Highway Projects for Settlement Control and Construction Speed (presentation). Big River Industries / Carolina Stalite Co. · Insulfoam. Geofoam — A Lightweight Fill Alternative (presentation)

Construction sequence using lightweight sawdust fill, sand drains and surcharge over peat and soft clay (Trans-Canada Highway, Burnaby).
Supplemental Figure 12-S2. Construction sequence using lightweight sawdust fill, sand drains and surcharge over peat and soft clay (Trans-Canada Highway, Burnaby). Source: Lea, N. D. and Brawner, C. O. Highway Design and Construction Over Peat Deposits in Lower British Columbia. Highway Research Board.
Project management · Levy (2010)

Schedule Float, Change Orders and Surcharge Hold Times

Levy (2010) explains, from the owner’s side, how changes interact with the contractor’s critical path method (CPM) schedule. The critical path moves as the job proceeds, and a delay to one critical task can cascade into later tasks and push out the completion date. When a change may affect time, owners face the question of whether the delay is real. Levy advises settling time when the change is priced, not later, because once unrelated contractor delays accumulate it becomes hard to separate them from the change. Extended time matters because general conditions costs (supervision, trailers, utilities, rentals) continue, and he cites $20,000 to $40,000 per month as a typical range.

Where time cannot be agreed, he suggests two approaches: issue the change with a statement that the work proceeds while the owner reserves the right to challenge any time extension, or sign the cost proposal provisionally, reserving the right to challenge both cost and time. Change-order forms often require checking whether the change increases, decreases or does not affect the contract end date, and owners should read that box before signing.

On float, Levy notes that schedules carry a cushion of extra days for weather, late equipment or short crews. Unless the contract says otherwise, that float belongs to the contractor. If the owner wants float for its own contingencies, such as late delivery of owner-furnished items, it must reserve it in the contract; otherwise an owner-caused delay that consumes the contractor’s float can become a claim.

For railroad work: Preload and surcharge programs for embankment widening or approach fills put a waiting period directly on the critical path, and its true length depends on measured consolidation rather than on the design estimate. Specify in the contract who owns float in the hold period, how the hold may be extended or shortened on the basis of settlement plate and piezometer data, and how extended time will be paid. Write the decision rule (for example, release when the monitored settlement rate falls below a stated value) into the special provisions so that a longer hold is a defined outcome rather than a dispute.

Settlement Plate Installation
Settlement Plate Installation

Source: Levy, S. M. (2010). Construction Process Planning and Management: An Owner’s Guide to Successful Projects. Burlington, MA: Butterworth-Heinemann (Elsevier), pp. 215–216. Summarized and paraphrased. Full reference under Supplemental References.

6.2.8.1 Precompression: Surcharging to Remove Settlement Before Track Is Built

Where a new track, siding or yard sits on soft clay, the cheapest way to avoid years of resurfacing is often to make the clay settle before the track goes down. A surcharge, extra fill above the final grade, is placed over the permanent fill. It speeds consolidation, and it is removed once the settlement the permanent load would eventually cause has occurred. Das's Advanced Soil Mechanics (Section 11.7, after Johnson) gives the design. To be safe, the degree of consolidation is taken at mid-depth of the drainage path, not as an average. If the surcharge comes off when only the average has been reached, the clay near mid-depth keeps settling while the clay near the drainage boundaries swells. Where wick drains are used (Chapter 7.2), Das replaces the mid-depth value with the average degree of consolidation for combined drainage.

6.2.8.1.1 Method

Equation 6.2-22. Degree of consolidation needed under permanent load plus surcharge (Das Eq. 11.25)

U(f+s) = log(1 + σf/σ′0) / log{1 + (σf/σ′0)[1 + σs/σf]}

σs/σf = [(1 + σf/σ′0)1/U − 1]/(σf/σ′0) − 1;   t = TvH2/cv

Das reads U from a chart; the calculator computes it from the Terzaghi series at mid-depth and solves Equation 6.2-22 directly for the surcharge ratio. For Das's Example 11.7 the calculator gives Tv = 0.497, U = 62.7% and σs/σf = 1.11. That example is 15 ft (4.5 m) of normally consolidated clay under 5 ft (1.5 m) of sand, a 1,210 psf (58 kPa) permanent load and six months available. Das, reading his charts, gets Tv = 0.497, U ≈ 0.62 and σs/σf = 1.17. The 5% difference in surcharge comes from reading the charts.

Table 6.2-8. Das Example 11.7 in English units: published and calculated
QuantityDasCalculator
σ′0 at clay mid-depth47.17 kPa (985 psf)985 psf
Tv for 6 months0.4970.497
U(f+s) at mid-depth≈ 0.62 (chart)0.627
σs/σf1.17 (chart)1.11
Surcharge σs67.86 kPa (1,417 psf)1,345 psf

6.2.8.1.2 Worked example

Applied to a siding on Das's profile, the permanent load of 1,211 psf would cause about 9.2 in. of primary settlement. To take all of it out in six months without drains takes a surcharge of 1,345 psf, about 11.2 ft of extra fill. The surcharge comes off when the settlement plates read 9.2 in., not on a calendar date. If that much fill would make the embankment unstable, combine a smaller surcharge with wick drains, or build in stages (Chapter 2.5).

The surcharge is usually the most critical stability case, because it is the heaviest load the soft clay will ever see. Check it with the Bishop calculator (Chapter 6.3), and monitor settlement plates and piezometers so the surcharge is removed on measured settlement.

Open the precompression surcharge calculator →
Effective stress at clay mid-depth, degree of consolidation in the time available (mid-depth or average), the surcharge ratio and fill height to remove primary settlement, and the settlement to wait for before removal.

6.2.8.1.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated values are standard or published. Individual railroads, clients and projects are not named.

  • B.M. Das, Advanced Soil Mechanics, 4th edition: Section 11.7 precompression (Eqs. 11.21 to 11.26, Example 11.7) and Section 11.8 precompression with sand drainsFind source ↗
  • R.F. Craig, Craig's Soil Mechanics, 7th edition: consolidation theory and the degree of consolidation with depthFind source ↗Library entry
  • M. Budhu, Soil Mechanics and Foundations, 3rd edition: one-dimensional consolidationFind source ↗