↑ Parent Menu⌂ Main Menu
← Chapter 6.2 Settlement Analysis
GHRM
Railway Ground Hazard Risk Management · 6.0 · Analysis
Sections · click a car to open it

6.2.7 Total Settlement and Angular Distortion

Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 6.1.
Authors: Daniel P. Colwell and Mario Ruel
6.2.7 Total Settlement and Angular Distortion
Equation 6.2-16 — Total Settlement:

S_total = Si + Sc + Ss

Equation 6.2-17 — Angular Distortion:

α = (S_A − S_B) / L_AB

Where S_A and S_B are predicted settlements at two adjacent structures or reference points, and L_AB is the distance between them (ft). This manual recommends limiting angular distortion at bridge approach transitions to 1/500 for Class 4 track (Table 6.2-1).

Bridge Approach Transition: The most critical angular distortion check in railroad geotechnical practice is at the abutment–embankment interface. A rigid pile-supported abutment settling < 0.1 in. adjacent to an approach fill settling 3.0 in. over 30 ft produces α = 2.9/30 = 0.097 — far exceeding any FRA class limit. AREMA Chapter 8 addresses approach design; use an approach slab or engineered approach fill to limit this transition zone differential.

Supplemental reference

Settlement that consolidation theory does not predict

Repeated and dynamic loads. USACE EM 1110-1-1904 notes that loose sands compact under vibration and that this is a major cause of differential settlement. Cohesionless soils with Dr above about 75% should not settle significantly, although intense dynamic loading can still compact dense sand by 1–2% of the stratum thickness. Dynamic settlement may be insignificant if the combined static and dynamic bearing stress stays below one-half of the allowable bearing capacity. Errors in dynamic-settlement predictions can be 50% or more. For clays under repeated deviator stress (0.1–10 Hz, a typical range for traffic), the manual gives a creep-strain-rate formulation from cyclic triaxial tests but warns it may underestimate settlement because traffic loading is more complex than repeated vertical load.

Collapsible soils. Loess, some alluvial fans and cemented silts lose their bonded structure on wetting. Typical collapsible soils are light-colored, LL < 45, PI < 25, with dry unit weight 65–105 pcf; collapse rarely occurs below 40% porosity. USACE notes that dynamic loading can also break the bonds, “particularly important for roads, airfields, railways.”

Table 12-S2. Wetting that can trigger collapse (EM 1110-1-1904, Table 5-4, condensed)

Type of wettingRailroad exampleResult
Local, shallowBlocked ditch, leaking pipeline crossingSettlement in the upper layer within the wetted area
Intense localIndustry effluent, broken water main, irrigationCan saturate the whole collapsible zone in < 1 year; uneven, damaging settlement
Slow, uniform groundwater riseReservoir or regional water table riseUniform, gradual settlement
Slow increase in water contentReduced evaporation under a paved yard or slabIncomplete, progressive settlement

Collapse potential CP (Jennings and Knight, 1975) is the strain on flooding a consolidometer specimen at 2 tsf: 0–1% negligible, 1–5% moderate trouble, 5–10% trouble, 10–20% severe trouble, > 20% very severe trouble. For design, load the specimen to the anticipated field stress and then inundate it (ASTM D4546, Method B); settlement = [(eo − ec)/(1 + eo)]H. USACE cautions that lab tests can miss soil that later collapses in the field, and the amount depends on how far the wetting front travels — so drainage control is part of the design.

Source: U.S. Army Corps of Engineers (1990). Settlement Analysis. EM 1110-1-1904

How much differential settlement the track itself tolerates

Geometry limits put a practical ceiling on differential settlement under track. European intervention limits for the longitudinal (surface) defect on a 33-ft chord range from about 0.35–0.47 in. at 87–99 mph to 0.55–0.83 in. below 37 mph (Chapter 2.1, §2.1.11). Emergency speed restrictions begin at 0.71 in.. Because the chord is short, these are effectively limits on settlement differences over about 33 ft. Embankment, culvert and transition settlement predictions should be checked against that scale, not only against total settlement.

Figure 6.2-13. Definitions: theoretical vs. real track elevation after maintenance (T = 0) and after traffic T, used to define settlement and longitudinal defect. Profillidis Fig. 16.2.
Figure 6.2-13. Definitions: theoretical vs. real track elevation after maintenance (T = 0) and after traffic T, used to define settlement and longitudinal defect. Profillidis Fig. 16.2.

After any surfacing, defects grow quickly up to about 2 million tons of traffic and then slowly, roughly with log T, at a rate (0.079–0.24 in. per decade of traffic) that depends mainly on subgrade quality (Chapter 3.8, §3.8.14).

After Profillidis (2014), §16.3, §16.6–16.7, Fig. 16.2. Full reference under Supplemental References.

Settlement of the track section under traffic

Components. Total settlement is the sum of three parts:

  • Ballast strain × ballast thickness.
  • Subballast strain × subballast thickness.
  • Subgrade settlement.

On new track, more than half comes from the ballast. After each tamping the ballast share grows again, because the loosened top ballast starts over.

Use a power law, not a semilog fit. Settlement after N load cycles fits SN = S1 Nb, with b typically 0.10–0.18. A semilog fit increasingly underpredicts at large N, and so overestimates the time to the next surfacing.

Load cycles per MGT. Cm = 106 ÷ (Aa × Na), where Aa is axle load in tons and Na is axles per load cycle. Use Na = 2 per car for ballast. For example, a 39-ton axle gives about 12,800 cycles per MGT.

Table 12-SW1. Settlement relations measured at FAST (T in MGT; site-specific)
LayerRelationAt 100 MGT
Top 12 in. of ballast (strain)ε = 0.026 T0.21ε ≈ 0.068 → 0.8 in.
Subballast (strain)ε = 0.017 T0.16; about 2.6 × 10−5 per MGT beyond ~150 MGTε ≈ 0.036
Subgrade, top 10 ft of moist fine silty sandS (in.) = 0.039 T0.37 (typical); 0.054 T0.52 (worst section)≈ 0.2 in. (typical)
Subgrade, long term0.001–0.0026 in. per MGT, linear beyond ~50 MGT—

The authors evaluated the 100 MGT column from the relations. Rapid compression occurred through the first ~3 MGT, then continued at a slower rate.

Lift and settlement. After a low lift, the track settles back by about the amount it was lifted within roughly a year, so the change does not last. Lifts above about 1 in., which exceed the ballast D50, leave a residual lift. Allow about 0.16 in. of settlement even at zero lift, from wear and compaction.

After Selig & Waters (1994), chs. 8 and 15. Full reference under Supplemental References.

Supplemental reference · Feng (ed.) (2017)

Settlement of Track Over a Tunnel Crossing TN-01

Sewer, water, transit and utility tunnels are often driven beneath operating track. The empirical method of Peck (1969) describes the settlement trough across a single tunnel in open ground as a normal (Gaussian) curve (Aversa et al., in Feng 2017):

Eq. 6.2-27: w(x) = w0 exp(−x2 / 2i2), where x = horizontal distance from the tunnel centerline.

Eq. 6.2-28: w0 = 0.313 V′ D2 / i, where D = tunnel diameter and V′ = volume loss, the trough volume as a fraction of the excavated area πD2/4 per unit length.

Eq. 6.2-29: i = K z0, where i = distance from the centerline to the inflection point of the trough and z0 = depth to the tunnel axis.

Table 6.2-10. Typical volume loss and trough width parameter (after Mair and Taylor 1997 and Chiriotti et al. 2001, as summarized by Aversa et al., in Feng 2017)
Ground and methodVolume loss V′K
Open face in stiff clay1–2%0.4–0.6 (fine-grained soils)
Sprayed concrete lining (sequential excavation) in clay0.5–1.5%0.4–0.6
TBM in sandunder 0.5%about 0.25–0.45 (granular soils)
TBM in soft clay1–2%0.5 or more
Mixed soil and rock face0.5–0.8%0.3–0.7
Discontinuous or weak rockunder 0.2–0.6%0.5 to above 0.7

Ground over a TBM settles in stages: ahead of the face, over the shield, at the tail as the annular gap closes, and over time as clay consolidates. Good face pressure and prompt tail grouting keep V′ at the low end of the table. A second, parallel tunnel generally causes more volume loss than the first.

Example 6.2-7: Track Settlement Over a TBM Crossing

Problem Statement

A city is driving a 12-ft diameter sewer tunnel with an earth pressure balance TBM under a two-track main line of a Class I railroad located in Ohio. The tunnel crosses square to the tracks with its axis 36 ft below top of rail, in stiff clay. The railroad requires a prediction of the settlement of the track profile and will set monitoring triggers from it. The engineer must predict the trough for the design volume loss and for poor face control.

Track (profile along rail) w₀ = ? TBM (to scale) i = ? z₀ = 36 ft D = 12 ft 62-ft chord (Required: offset) Stiff clay Given D = 12 ft (EPB TBM)z₀ = 36 ft to tunnel axisStiff clay: K = 0.5V′ = 1.0% (design)V′ = 2.0% (poor face control)Tunnel square to track Required(a) i(b) w₀ at V′ = 1%(c) 62-ft midchord offset(d) both at V′ = 2%
Figure 6.2-17. Example 6.2-7: section along the track over a tunnel crossing beneath it, with the Gaussian settlement trough in the track profile (vertical scale exaggerated).

Given

VariableValueDescription
D12 ftExcavated tunnel diameter
z036 ftDepth to tunnel axis below top of rail
K0.5Trough width parameter, stiff clay (Table 6.2-10)
V′1.0% (design); 2.0% (poor face control)Volume loss
Chord62 ftChord used for track profile (surface) measurement, centered over the tunnel

Required

  • (a) Trough width parameter i
  • (b) Maximum settlement w0 at V′ = 1.0%
  • (c) Midchord offset of the track profile on a 62-ft chord centered over the tunnel
  • (d) w0 and the midchord offset at V′ = 2.0%

Equations

  1. Eq. 6.2-29: i = K z0
  2. Eq. 6.2-28: w0 = 0.313 V′ D2 / i
  3. Eq. 6.2-27: w(x) = w0 exp(−x2 / 2i2)
  4. Midchord offset: M = w(0) − w(31 ft) (both chord ends settle equally)

Steps

Step 1 · (a) Trough width
0.5 × 36
i = 18 ft
↓
Step 2 · (b) Maximum settlement at 1.0%
0.313 × 0.010 × 144 / 18 = 0.0250 ft
w0 = 0.30 in.
Spot check: trough volume √(2π) i w0 = 2.507 × 18 × 0.0250 = 1.13 ft3/ft; V′ × πD2/4 = 0.010 × 113.1 = 1.13 ft3/ft ✓.
↓
Step 3 · (c) Settlement at the chord ends
x = 31 ft: exp(−312 / (2 × 182)) = exp(−961/648) = exp(−1.483) = 0.227; w = 0.30 × 0.227
w(31) = 0.07 in.; M = 0.30 − 0.07 = 0.23 in.
↓
Step 4 · (d) At 2.0%
w0 doubles: 2 × 0.30; M = 0.60 × (1 − 0.227)
w0 = 0.60 in.; M = 0.46 in.
↓
Solution
i = 18 ft; about 0.3 in. maximum settlement and a 0.23-in. profile dip at design volume loss, doubling with poor face control.

Solution

(a) i = 18 ft. (b) w0 ≈ 0.30 in. (c) M ≈ 0.23 in. on a 62-ft chord. (d) w0 ≈ 0.60 in. and M ≈ 0.46 in.

Most of the trough (to about 2.5i, or 45 ft, either side) falls within a few rail lengths, so the track sees a short, sharp dip rather than a uniform drop. Both tracks settle about equally because the tunnel is square to them, so cross-level is not affected. On a skewed crossing it would be. Set the railroad’s monitoring triggers from this prediction: for example, review at half the predicted design settlement, and stop the TBM and resurface the track at the design value. Survey the rails before the TBM reaches about 2 to 3 tunnel diameters from the track, then at least daily while the face is within that distance on either side, and afterward until the readings stabilize. Clay continues to consolidate after the TBM passes, so plan follow-up surfacing. Have a tamper and crew on call during the crossing.

For railroad work: Ask the tunnel designer for the predicted trough, the assumed volume loss and the face pressure plan before the railroad agreement is signed. Require monitoring of the rails and of points on the shoulder at the tunnel centerline and at i, 2i and 3i either side, with readings tied to the TBM face position. Slow or stop the drive if the readings approach the triggers. Where track or a bridge foundation lies over a weathered rock or mixed face, volume loss can vary along the drive, so use the upper end of the range for the crossing.

Source: Aversa, Bilotta, Ferrero and Migliazza, “Settlements induced by TBM excavation,” in Feng (ed.) (2017), Ch. 23, summarizing Peck (1969), O’Reilly and New (1982), Mair and Taylor (1997) and Chiriotti et al. (2001). Summarized and paraphrased; units converted. Full reference under S11.

← Previous · 6.0 Analysis Chapter 6.1 — Foundation Engineering: Bearing Capacity
Next · 6.0 Analysis → Chapter 6.3 — Slope Stability Analysis