↑ Parent Menu⌂ Main Menu
← Chapter 6.2 Settlement Analysis
GHRM
Railway Ground Hazard Risk Management · 6.0 · Analysis
Sections · click a car to open it

6.2.14 Practice Questions and Full Answers

Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 6.1.
Authors: Daniel P. Colwell and Mario Ruel
6.2.14 Practice Questions and Full Answers
Each question is worked in the same five parts as the examples. Question 6.2-4 is a reasoning question.
Question 6.2-1: Settlement of Soft Clay Under a Footing

Problem Statement

A spread footing for a new railroad maintenance building at a Class I yard will add stress to a 10-ft layer of normally consolidated soft clay with the properties shown. The engineer must estimate the consolidation settlement and compare it with the settlement the adjacent Class 4 track can tolerate.

Maintenance building footingSc = ?NC soft clay, 10 ft: Cc = 0.45, e0 = 1.60Sand (drains)At mid-clay: σ′v0 = 500 psf, Δσ = 1,200 psfGivenH = 10 ft NC clayCc = 0.45; e0 = 1.60σ′v0 = 500 psf (mid-clay)Δσ = 1,200 psf (mid-clay)RequiredConsolidation settlement Sc Compare with Class 4 track toleranceBlack = given; red = required
Given and required for Question 6.2-1.

Given

VariableValueDescription
H10 ftClay layer
Cc, e00.45; 1.60
σ′v0500 psfMid-clay
Δσ1,200 psfMid-clay

Required

  • Sc

Equations

  1. Eq. 6.2-5: Sc = [Cc/(1 + e0)] H log[(σ′v0 + Δσ)/σ′v0] — normally consolidated

Steps

Step 1 · Sc
(0.45/2.60) × 10 × log(1,700/500) = 0.1731 × 10 × 0.5315
0.920 ft = 11.0 in.
↓
Solution
Sc = 11.0 in.

Solution

Sc ≈ 11 in.

That is eleven times the 1.0-in. Class 4 limit of Table 6.2-1; ground improvement or a deep foundation is required.

Question 6.2-2: Time to 90% With and Without Wick Drains

Problem Statement

A new embankment for a railroad yard expansion will sit on 15 ft of normally consolidated silty clay drained at top and bottom. The railroad wants to know how long it must wait before laying track. The engineer must compute the time to 90% consolidation without drains and with wick drains at the spacing shown.

Yard embankmentt90 with / without drains = ?NC silty clay, 15 ft: cv = 0.10 ft²/dSand (drains)Given15 ft clay, two-way: Hdr = 7.5 ftcv = 0.10 ft²/dayDrains 4.0-ft triangular; de = 4.2 ftch ≈ 2cv = 0.20 ft²/dayRequiredt90 without drainst90 with drainsBlack = given; red = required
Given and required for Question 6.2-2.

Given

VariableValueDescription
H15 ft, two-way drainageHdr = 7.5 ft
cv0.10 ft²/day
Drains4.0-ft triangular; de = 4.2 ftch ≈ 2cv = 0.20 ft²/day

Required

  • t90 without and with drains

Equations

  1. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848

Steps

Step 1 · Without drains
0.848 × 7.5² / 0.10
477 days = 1.3 years
↓
Step 2 · With drains (rough)
Path ≈ de/2 = 2.1 ft; 0.848 × 2.1² / 0.20
About 19 days
↓
Solution
477 days without drains; about 19 days with them.

Solution

About 477 days (1.3 years) without drains and about 19 days with them, roughly 25 times faster.

The drain estimate ignores smear and well resistance, which slow radial drainage; design with Barron and Hansbo (Chapter 7.2). The comparison shows why drains are specified whenever track must go on within 60 to 90 days of fill completion.

Question 6.2-3: Overconsolidated Clay Crossing the Preconsolidation Stress

Problem Statement

An embankment for a new railroad grade separation will load an overconsolidated clay past its preconsolidation stress. Laboratory tests gave the compression and swelling indices, void ratio and stresses shown. The engineer must compute the consolidation settlement and identify which settlement equation applies.

Grade separation embankmentSc = ? Which equation?OC clay, 8 ft: Cc 0.38, Cs 0.048, e0 0.95Sand (drains)σ′v0 = 1,200 psf; σ′p = 2,800 psf; Δσ = 2,000 psfGivenH = 8 ftCc 0.38; Cs 0.048; e0 0.95σ′v0 1,200; σ′p 2,800 psfΔσ = 2,000 psfRequiredSc Which settlement equation appliesBlack = given; red = required
Given and required for Question 6.2-3.

Given

VariableValueDescription
H8 ft
Cc, Cs, e00.38; 0.048; 0.95
σ′v0, σ′p1,200 and 2,800 psf
Δσ2,000 psf

Required

  • Sc, and which equation applies

Equations

  1. Eq. 6.2-7: Sc = [Cs/(1 + e0)] H log(σ′p/σ′v0) + [Cc/(1 + e0)] H log(σ′f/σ′p) — OC crossing σ′p

Steps

Step 1 · Which case?
1,200 + 2,000 = 3,200 > 2,800
Crossing σ′p: Eq. 6.2-7
↓
Step 2 · Recompression part
(0.048/1.95) × 8 × log 2.333
0.0724 ft
↓
Step 3 · Virgin part
(0.38/1.95) × 8 × log 1.143
0.0904 ft
↓
Step 4 · Total
0.163 ft = 1.95 in.
Spot check: Treated as NC: (0.38/1.95) × 8 × log 2.667 = 0.664 ft = 8.0 in., a 4.1× overestimate.
↓
Solution
Sc = 1.95 in. (Eq. 6.2-7).

Solution

Sc ≈ 1.95 in., from Eq. 6.2-7.

Missing the overconsolidation would have overestimated the settlement fourfold and could have triggered ground improvement that was not needed.

Question 6.2-4: Why Angular Distortion Governs at Bridge Approaches

Problem Statement

A pile-supported railroad bridge abutment does not settle, but the approach fill behind it has settled 1 to 3 in. within 30 ft and the track shows a dip at the bridge end. The engineer must explain why angular distortion, rather than total settlement, governs the approach and state the limit used for Class 4 track.

Abutment on pilesApproach fillas built1 to 3 in. within 30 ft30 ftWhy angular distortion governs? Class 4 limit = ?GivenAbutment on piles: settlement ≈ 0Approach fill: 1 to 3 in. in 30 ftTrack dip at the bridge endTable 6.2-1: Class 4 limitRequiredWhy angular distortion, not total settlement, is criticalThe Class 4 limitBlack = given; red = required
Given and required for Question 6.2-4.

Given

VariableValueDescription
AbutmentPile supported; settlement ≈ 0
Approach fill1 to 3 in. within 30 ft
Limit1/500 for Class 4 trackTable 6.2-1

Required

  • Why angular distortion, not total settlement, is the critical measure
  • The Class 4 limit

Equations

  1. Eq. 1: α = ΔS / L — angular distortion

Steps

Step 1 · What does the rail feel?
The change in elevation along the track: a ramp at the abutment, not the absolute settlement.
↓
Step 2 · What does FRA measure?
Surface deviation over a 62-ft chord, which a sharp ramp exceeds.
↓
Step 3 · Limit (Eq. 1)
1/500 × 25 ft = 0.05 ft; 1/500 × 62 ft = 0.124 ft
0.6 in. over 25 ft; 1.5 in. over 62 ft
↓
Solution
Distortion governs; limit 1/500 for Class 4.

Solution

Because the rail responds to the rate of elevation change, not the total. This manual limits approach distortion to 1/500 for Class 4 track, about 0.6 in. over 25 ft.

Approach slabs, sleeper slabs and geosynthetic-reinforced approach zones spread the change over a longer distance; AREMA Chapter 8 approach slab design should be cross-referenced whenever the predicted embankment settlement at the abutment exceeds 0.5 in.

Question 6.2-5: Degree of Consolidation for a Passenger Corridor Embankment

Problem Statement

A passenger corridor is adding a track on a new embankment over soft clay, and the railroad (assumed) allows only 0.375 in. of primary settlement after the track is laid. The predicted primary settlement is 8.0 in. The engineer must find the degree of consolidation required before track laying and the time to reach it with and without wick drains.

New passenger track embankmentU required = ? t = ?Soft clay: cv = 0.006 ft²/d, Hdr = 12 ftRock (impervious)GivenSc = 8.0 in. primarySs = 1.5 in. in 50 yr (maintenance)Limit 0.375 in. residual primarycv 0.006 ft²/day; Hdr 12 ftDrains: path 1.5 ft; ch ≈ 0.012 ft²/dayRequiredDegree of consolidation UTime without and with drainsBlack = given; red = required
Given and required for Question 6.2-5.

Given

VariableValueDescription
Sc8.0 in.Primary
Ss1.5 in. over 50 yearsHandled by maintenance
Limit0.375 in. residual primary (assumed)
cv, Hdr0.006 ft²/day; 12 ft
DrainsEffective path 1.5 ft; ch ≈ 0.012 ft²/day

Required

  • U required
  • Time without and with drains

Equations

  1. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848

Steps

Step 1 · U required
(1 − U) × 8.0 ≤ 0.375
U ≥ 95.3%
↓
Step 2 · Tv
−0.933 log(0.047) − 0.085
1.154
↓
Step 3 · Without drains
1.154 × 144 / 0.006
27,700 days = 76 years
↓
Step 4 · With drains
1.154 × 1.5² / 0.012
About 216 days, 7 months
↓
Solution
U ≥ 95.3%: 76 years undrained, about 7 months with drains.

Solution

U must reach 95.3%. That takes about 76 years with natural drainage, which is infeasible, and about 7 months with wick drains.

High-speed track leaves almost no room for residual settlement, so drains, a surcharge to speed the last few percent, and settlement plates to prove it are normally all required.

Question 6.2-6: How Far Short of the Sand Can the Drains Stop?

Problem Statement

A Class I railroad located in Mississippi is building a siding extension on an embankment over 50 ft of soft clay underlain by clean sand, which drains the clay from below. Vertical drains on a 4.5-ft triangular pattern are specified over a 2,000-ft by 100-ft area. The contractor asks whether the drains really need to reach the sand. The engineer must find the optimum unimproved thickness at the bottom of the clay and the drain length it would save.

Embankment and surcharge Soft clay Sand (free-draining) PVDs, triangular 4.5 ft Required: Hc 50 ft Givendw = 0.196 ftds/dw = 4kh/ks = 3ch/cv = 2Area 2,000 × 100 ft Requiredμ, Hc, drainlength saved
Figure 6.2-16. Question 6.2-6: drains in clay over sand.

Given

VariableValueDescription
H50 ftClay thickness, drained top and bottom
s4.5 ft triangularDrain spacing
dw0.196 ftEquivalent drain diameter
ds/dw, kh/ks4 and 3Smear zone size and permeability ratio
ch/cv2
Area2,000 ft × 100 ftTreated area

Required

  • (a) Drain resistance factor μ
  • (b) Optimum unimproved thickness Hc
  • (c) Total drain length saved

Equations

  1. Eq. 1: De = 1.05 s (triangular)
  2. Eq. 2: μ = ln(n/sr) + (kh/ks) ln sr − 0.75, n = De/dw, sr = ds/dw (Hansbo, Chapter 7.2, Section 7.2.3)
  3. Eq. 6.2-25: Hc = 1 / [64/H² + 2.5 ch/(μ De² cv)]0.5
  4. Eq. 3: number of drains = area / (0.866 s²)

Steps

Step 1 · De and n
1.05 × 4.5; 4.725/0.196
De = 4.73 ft; n = 24.1
↓
Step 2 · (a) μ
ln(24.1/4) + 3 ln 4 − 0.75 = 1.80 + 4.16 − 0.75
μ = 5.21
↓
Step 3 · (b) Hc
64/2,500 = 0.0256; 2.5 × 2/(5.21 × 22.3) = 0.0430; 1/(0.0686)0.5
Hc = 3.8 ft
Spot check: Units: each term is 1/ft², so the square root gives feet. Hc cannot exceed H/8 = 6.25 ft.
↓
Step 4 · (c) Drains and length saved
200,000 / (0.866 × 20.25) = 11,400 drains; 11,400 × 3.8 ft
About 43,000 ft of drain saved
↓
Solution
μ = 5.2; drains can stop about 3.8 ft above the sand; about 43,000 ft of drain saved.

Solution

(a) μ ≈ 5.2. (b) Hc ≈ 3.8 ft. (c) About 43,000 linear feet of drain.

Stopping the drains about 4 ft above the sand gives almost the same overall rate of consolidation as full penetration, because the bottom 4 ft drains quickly into the sand. The saving is about 8% of the drain length. Confirm the sand is continuous and free-draining with the borings or CPTs (a clay lens in the sand changes the answer), and if vacuum is added later, the drains must stop short of the sand anyway so the vacuum does not leak into it (Section 6.2.18).

← Previous · 6.0 Analysis Chapter 6.1 — Foundation Engineering: Bearing Capacity
Next · 6.0 Analysis → Chapter 6.3 — Slope Stability Analysis