Each question is worked in the same five parts as the examples. Question 6.2-4 is a reasoning question.
Question 6.2-1: Settlement of Soft Clay Under a Footing
Problem Statement
A spread footing for a new railroad maintenance building at a Class I yard will add stress to a 10-ft layer of normally consolidated soft clay with the properties shown. The engineer must estimate the consolidation settlement and compare it with the settlement the adjacent Class 4 track can tolerate.
That is eleven times the 1.0-in. Class 4 limit of Table 6.2-1; ground improvement or a deep foundation is required.
Question 6.2-2: Time to 90% With and Without Wick Drains
Problem Statement
A new embankment for a railroad yard expansion will sit on 15 ft of normally consolidated silty clay drained at top and bottom. The railroad wants to know how long it must wait before laying track. The engineer must compute the time to 90% consolidation without drains and with wick drains at the spacing shown.
Given and required for Question 6.2-2.
Given
Variable
Value
Description
H
15 ft, two-way drainage
Hdr = 7.5 ft
cv
0.10 ft²/day
Drains
4.0-ft triangular; de = 4.2 ft
ch ≈ 2cv = 0.20 ft²/day
Required
t90 without and with drains
Equations
Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848
Steps
Step 1 · Without drains
0.848 × 7.5² / 0.10
477 days = 1.3 years
↓
Step 2 · With drains (rough)
Path ≈ de/2 = 2.1 ft; 0.848 × 2.1² / 0.20
About 19 days
↓
Solution
477 days without drains; about 19 days with them.
Solution
About 477 days (1.3 years) without drains and about 19 days with them, roughly 25 times faster.
The drain estimate ignores smear and well resistance, which slow radial drainage; design with Barron and Hansbo (Chapter 7.2). The comparison shows why drains are specified whenever track must go on within 60 to 90 days of fill completion.
Question 6.2-3: Overconsolidated Clay Crossing the Preconsolidation Stress
Problem Statement
An embankment for a new railroad grade separation will load an overconsolidated clay past its preconsolidation stress. Laboratory tests gave the compression and swelling indices, void ratio and stresses shown. The engineer must compute the consolidation settlement and identify which settlement equation applies.
Given and required for Question 6.2-3.
Given
Variable
Value
Description
H
8 ft
Cc, Cs, e0
0.38; 0.048; 0.95
σ′v0, σ′p
1,200 and 2,800 psf
Δσ
2,000 psf
Required
Sc, and which equation applies
Equations
Eq. 6.2-7: Sc = [Cs/(1 + e0)] H log(σ′p/σ′v0) + [Cc/(1 + e0)] H log(σ′f/σ′p) — OC crossing σ′p
Steps
Step 1 · Which case?
1,200 + 2,000 = 3,200 > 2,800
Crossing σ′p: Eq. 6.2-7
↓
Step 2 · Recompression part
(0.048/1.95) × 8 × log 2.333
0.0724 ft
↓
Step 3 · Virgin part
(0.38/1.95) × 8 × log 1.143
0.0904 ft
↓
Step 4 · Total
0.163 ft = 1.95 in.
Spot check: Treated as NC: (0.38/1.95) × 8 × log 2.667 = 0.664 ft = 8.0 in., a 4.1× overestimate.
↓
Solution
Sc = 1.95 in. (Eq. 6.2-7).
Solution
Sc ≈ 1.95 in., from Eq. 6.2-7.
Missing the overconsolidation would have overestimated the settlement fourfold and could have triggered ground improvement that was not needed.
Question 6.2-4: Why Angular Distortion Governs at Bridge Approaches
Problem Statement
A pile-supported railroad bridge abutment does not settle, but the approach fill behind it has settled 1 to 3 in. within 30 ft and the track shows a dip at the bridge end. The engineer must explain why angular distortion, rather than total settlement, governs the approach and state the limit used for Class 4 track.
Given and required for Question 6.2-4.
Given
Variable
Value
Description
Abutment
Pile supported; settlement ≈ 0
Approach fill
1 to 3 in. within 30 ft
Limit
1/500 for Class 4 track
Table 6.2-1
Required
Why angular distortion, not total settlement, is the critical measure
The Class 4 limit
Equations
Eq. 1: α = ΔS / L — angular distortion
Steps
Step 1 · What does the rail feel?
The change in elevation along the track: a ramp at the abutment, not the absolute settlement.
↓
Step 2 · What does FRA measure?
Surface deviation over a 62-ft chord, which a sharp ramp exceeds.
↓
Step 3 · Limit (Eq. 1)
1/500 × 25 ft = 0.05 ft; 1/500 × 62 ft = 0.124 ft
0.6 in. over 25 ft; 1.5 in. over 62 ft
↓
Solution
Distortion governs; limit 1/500 for Class 4.
Solution
Because the rail responds to the rate of elevation change, not the total. This manual limits approach distortion to 1/500 for Class 4 track, about 0.6 in. over 25 ft.
Approach slabs, sleeper slabs and geosynthetic-reinforced approach zones spread the change over a longer distance; AREMA Chapter 8 approach slab design should be cross-referenced whenever the predicted embankment settlement at the abutment exceeds 0.5 in.
Question 6.2-5: Degree of Consolidation for a Passenger Corridor Embankment
Problem Statement
A passenger corridor is adding a track on a new embankment over soft clay, and the railroad (assumed) allows only 0.375 in. of primary settlement after the track is laid. The predicted primary settlement is 8.0 in. The engineer must find the degree of consolidation required before track laying and the time to reach it with and without wick drains.
Given and required for Question 6.2-5.
Given
Variable
Value
Description
Sc
8.0 in.
Primary
Ss
1.5 in. over 50 years
Handled by maintenance
Limit
0.375 in. residual primary (assumed)
cv, Hdr
0.006 ft²/day; 12 ft
Drains
Effective path 1.5 ft; ch ≈ 0.012 ft²/day
Required
U required
Time without and with drains
Equations
Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848
Steps
Step 1 · U required
(1 − U) × 8.0 ≤ 0.375
U ≥ 95.3%
↓
Step 2 · Tv
−0.933 log(0.047) − 0.085
1.154
↓
Step 3 · Without drains
1.154 × 144 / 0.006
27,700 days = 76 years
↓
Step 4 · With drains
1.154 × 1.5² / 0.012
About 216 days, 7 months
↓
Solution
U ≥ 95.3%: 76 years undrained, about 7 months with drains.
Solution
U must reach 95.3%. That takes about 76 years with natural drainage, which is infeasible, and about 7 months with wick drains.
High-speed track leaves almost no room for residual settlement, so drains, a surcharge to speed the last few percent, and settlement plates to prove it are normally all required.
Question 6.2-6: How Far Short of the Sand Can the Drains Stop?
Problem Statement
A Class I railroad located in Mississippi is building a siding extension on an embankment over 50 ft of soft clay underlain by clean sand, which drains the clay from below. Vertical drains on a 4.5-ft triangular pattern are specified over a 2,000-ft by 100-ft area. The contractor asks whether the drains really need to reach the sand. The engineer must find the optimum unimproved thickness at the bottom of the clay and the drain length it would save.
Figure 6.2-16. Question 6.2-6: drains in clay over sand.
Given
Variable
Value
Description
H
50 ft
Clay thickness, drained top and bottom
s
4.5 ft triangular
Drain spacing
dw
0.196 ft
Equivalent drain diameter
ds/dw, kh/ks
4 and 3
Smear zone size and permeability ratio
ch/cv
2
Area
2,000 ft × 100 ft
Treated area
Required
(a) Drain resistance factor μ
(b) Optimum unimproved thickness Hc
(c) Total drain length saved
Equations
Eq. 1: De = 1.05 s (triangular)
Eq. 2: μ = ln(n/sr) + (kh/ks) ln sr − 0.75, n = De/dw, sr = ds/dw (Hansbo, Chapter 7.2, Section 7.2.3)
μ = 5.2; drains can stop about 3.8 ft above the sand; about 43,000 ft of drain saved.
Solution
(a) μ ≈ 5.2. (b) Hc ≈ 3.8 ft. (c) About 43,000 linear feet of drain.
Stopping the drains about 4 ft above the sand gives almost the same overall rate of consolidation as full penetration, because the bottom 4 ft drains quickly into the sand. The saving is about 8% of the drain length. Confirm the sand is continuous and free-draining with the borings or CPTs (a clay lens in the sand changes the answer), and if vacuum is added later, the drains must stop short of the sand anyway so the vacuum does not leak into it (Section 6.2.18).