6.2.11 Worked Calculation Examples

Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 6.1.
Authors: Daniel P. Colwell and Mario Ruel
6.2.11 Worked Calculation Examples
The three examples cover the three settlement cases a railroad engineer meets most often: soft normally consolidated clay under new fill, the time a preload must stay on, and a stiff overconsolidated clay under a slab. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 6.2-1: Embankment Settlement Over Soft Clay

A new siding on a Class I railroad located in coastal Georgia (Brunswick) puts 10 ft of fill on 14 ft of soft, normally consolidated fat clay over rock. The example estimates how much the clay will compress, how long it will take with drainage only upward, and how much secondary compression follows, and compares the post-construction settlement with the limit for the track.

10 ftFill 10 ft, γ = 120 pcf, B = 40 ftSp, Ss, t90 = ?CH, 14 ft: Cc = 0.56, e0 = 1.82, cv = 0.004 ft²/dRock (impervious)GWT ▽GivenFill 10 ft; γ = 120 pcf; B = 40 ftClay 14 ft CH; γ = 110 pcfCc 0.56; e0 1.82; Cα 0.022cv 0.004 ft²/day; Hdr 14 ftGWT 2 ft below original groundWick drains: primary done at 180 dLimit 1.0 in. post-construction; 50 yrRequiredPrimary and secondary settlementTime to 90% consolidationMeets the 1.0-in. limit?Black = given; red = required
Given and required for Example 6.2-1.

Given

VariableValueDescription
FillH = 10 ft; γ = 120 pcf; B = 40 ft at base
Clay14 ft CH; Cc = 0.56; e0 = 1.82; cv = 0.004 ft²/day; Cα = 0.022; γ = 110 pcfOn rock: one-way drainage, Hdr = 14 ft
zw2 ft below original ground
Limit1.0 in. post-construction (assumed, Class 4)
Wick drainsAssumed to finish primary at t1 = 180 days
Service50 years

Required

  • Primary and secondary settlement
  • Time to 90% consolidation
  • Compliance with the limit

Equations

  1. Eq. 1: Δσ = q B/(B + z) — 2:1 spread to mid-clay
  2. Eq. 6.2-5: Sc = [Cc/(1 + e0)] H log[(σ′v0 + Δσ)/σ′v0] — normally consolidated
  3. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848
  4. Eq. 3: Ss = [Cα/(1 + ep)] H log(t2/t1) — secondary compression
  5. Eq. 4: ep = e0 − Cc log(σ′f/σ′v0) — void ratio at end of primary

Steps

Step 1 · σ′v0 at mid-clay (7 ft)
2(110) + 5(110 − 62.4) = 220 + 238
458 psf
↓
Step 2 · Δσ (Eq. 1)
1,200 × 40/(40 + 7)
1,021 psf
↓
Step 3 · Sc (Eq. 6.2-5)
(0.56/2.82) × 14 × log(1,479/458) = 0.1986 × 14 × 0.509
Sc = 1.42 ft = 17.0 in.
↓
Step 4 · t90, no drains (Eq. 2)
0.848 × 14² / 0.004
41,500 days = 114 years
↓
Step 5 · Ss, 180 days to 50 years (Eq. 3, 4)
ep = 1.82 − 0.56 × 0.509 = 1.535; (0.022/2.535) × 14 × log(18,250/180) = 0.00868 × 14 × 2.006
Ss = 0.244 ft = 2.9 in.
↓
Step 6 · Post-construction settlement
10% of primary + secondary = 1.7 + 2.9
4.6 in. >> 1.0 in.
↓
Solution
Sc = 17 in.; 114 years undrained; 4.6 in. after construction: ground improvement required.

Solution

Primary settlement is about 17 in., which would take over a century to finish with drainage to one face. Even with wick drains finishing primary in 180 days, about 4.6 in. would remain after construction against a 1.0-in. limit.

Wick drains change the time, not the amount. The options are a surcharge preload that drives primary consolidation past the final load before track is laid, accepting the secondary settlement as maintenance, or column support (deep soil mixing or rigid inclusions) that bypasses the clay (Chapter 7.2). The 2:1 stress at mid-clay is used here as a conservative centerline value; a full analysis divides the clay into sublayers.

Example 6.2-2: Preload Duration for a Bridge Approach Fill

A bridge approach fill on a Class I railroad located in southern Manitoba sits on soft, normally consolidated silty clay drained by sand above and below. The question is how long a preload must stay in place for the remaining settlement to be within the allowable after track is laid.

18 ftFill 18 ftSc, U, t = ?CL-ML, 20 ft: Cc = 0.35, e0 = 1.25, cv = 0.08 ft²/dSand (drains)GWT ▽drain option (dashed)GivenFill 18 ft; Δσ = 1,440 psf mid-clayClay 20 ft; γsat = 115 pcfTwo-way drainage, Hdr = 10 ftGWT at original groundLimit 1.5 in. residualDrains: 5-ft triangular, de = 5.25 ftRequiredPrimary settlementU and time for 1.5 in. residualEffect of wick drainsBlack = given; red = required
Given and required for Example 6.2-2.

Given

VariableValueDescription
Fill18 ft; Δσ = 1,440 psf at mid-clay
Clay20 ft CL-ML; Cc = 0.35; e0 = 1.25; cv = 0.08 ft²/day; γsat = 115 pcfTwo-way drainage, Hdr = 10 ft
zwAt the original ground surface
Limit1.5 in. residual (assumed)
Drains option5-ft triangular spacing; de = 5.25 ft

Required

  • Primary settlement
  • Degree of consolidation and time needed for 1.5 in. residual
  • Effect of wick drains

Equations

  1. Eq. 6.2-5: Sc = [Cc/(1 + e0)] H log[(σ′v0 + Δσ)/σ′v0] — normally consolidated
  2. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848

Steps

Step 1 · σ′v0 at mid-clay
10 × (115 − 62.4)
526 psf
↓
Step 2 · Sc (Eq. 6.2-5)
(0.35/2.25) × 20 × log(1,966/526) = 0.1556 × 20 × 0.573
Sc = 1.78 ft = 21.4 in.
↓
Step 3 · U needed
(1 − U) × 21.4 ≤ 1.5
U ≥ 93%
↓
Step 4 · Tv and t (Eq. 2)
−0.933 log(0.070) − 0.085 = 0.993; t = 0.993 × 10²/0.08
t = 1,241 days = 3.4 years
Spot check: At 90%: t = 0.848 × 1,250 = 1,060 days, leaving 2.1 in.; 93% needs a further six months.
↓
Step 5 · With wick drains (rough)
Drainage path about de/2 = 2.6 ft; 1,241 × (2.6/10)²
About 84 days
↓
Solution
U ≥ 93%: 3.4 years without drains, about 3 months with them.

Solution

Primary settlement is about 21 in. The preload must reach 93% consolidation, which takes about 3.4 years with the natural drainage, or roughly 3 months with wick drains at 5-ft spacing.

The drain estimate is a rough analogy that ignores smear and well resistance; design the drains with Barron and Hansbo radial theory (Chapter 7.2). Tell the railroad’s project engineer the timeline early, and confirm it in the field with settlement plates at about 500-ft intervals read monthly: the plates, not the calculation, decide when the preload comes off.

Example 6.2-3: Settlement of an Overconsolidated Clay Under a Crane Slab

A crane rail pavement slab for an intermodal expansion on a Class I railroad located in Kansas City sits on stiff, overconsolidated fat clay. Because the new stress stays below the preconsolidation stress, only the stiff recompression branch is used, and the secondary compression ratio must match that branch too.

Crane slab, net Δσ = 800 psfcrane railsOC clay CH, 12 ft: Cc 0.42, Cs 0.05, e0 0.88σ′v0 = 1,850 psf; σ′p = 4,200 psfDrainage both faces, Hdr = 6 ftSp + 50-yr Ss = ? Improvement needed?GivenΔσ = 800 psfClay 12 ft; Cc 0.42; Cs 0.05; e0 0.88σ′v0 1,850; σ′p 4,200 psf (OCR 2.27)cv 1.0 ft²/d; Hdr 6 ftCα/Cr = 0.04Limit 0.125 in. per 20 ft (rail)RequiredPrimary and 50-yr secondaryIs ground improvement needed?Black = given; red = required
Given and required for Example 6.2-3.

Given

VariableValueDescription
Δσ800 psfNet load from slab and crane
Clay12 ft CH; Cc = 0.42; Cs = 0.05; e0 = 0.88
σ′v0, σ′p1,850 and 4,200 psfOCR = 2.27
cv1.0 ft²/day (assumed); Hdr = 6 ft
Cα/Cr0.04Mesri, recompression range
Limit0.125 in. per 20 ft differential (assumed)Crane rail

Required

  • Primary and 50-year secondary settlement
  • Whether ground improvement is needed

Equations

  1. Eq. 6.2-6: Sc = [Cs/(1 + e0)] H log[(σ′v0 + Δσ)/σ′v0] — overconsolidated, σ′f < σ′p
  2. Eq. 2: t = Tv Hdr² / cv; Tv = −0.933 log(1 − U) − 0.085 for U > 60% — time rate; T50 = 0.197, T90 = 0.848
  3. Eq. 3: Ss = [Cα/(1 + ep)] H log(t2/t1) — secondary compression

Steps

Step 1 · Which case?
1,850 + 800 = 2,650 < 4,200
Recompression only (Eq. 6.2-6)
↓
Step 2 · Sc
(0.05/1.88) × 12 × log 1.432 = 0.0266 × 12 × 0.156
0.050 ft = 0.60 in.
↓
Step 3 · End of primary (Eq. 2)
0.848 × 36 / 1.0
t1 ≈ 31 days
↓
Step 4 · Ss (Eq. 3)
Cα = 0.04 × 0.05 = 0.002; ep = 0.872; (0.002/1.872) × 12 × log(18,250/31) = 0.00107 × 12 × 2.770
0.036 ft = 0.43 in.
Spot check: Using Cα = 0.04 Cc = 0.017 would give 3.6 in., an eightfold overestimate.
↓
Solution
0.60 in. primary in a month; 0.43 in. over 50 years: no improvement needed.

Solution

Primary settlement 0.60 in., essentially complete within about a month; secondary about 0.4 in. over 50 years; about 1.0 in. in all.

The primary settlement can be taken out before the crane rail is set. The long-term part is small and nearly uniform in a uniform layer, so the differential depends on lateral variation in the clay between borings; check it against the 0.125 in. per 20 ft limit and provide rail adjustment in the crane rail design. Ground improvement is not needed for settlement alone.