The three examples cover the three settlement cases a railroad engineer meets most often: soft normally consolidated clay under new fill, the time a preload must stay on, and a stiff overconsolidated clay under a slab. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 6.2-1: Embankment Settlement Over Soft Clay
A new siding on a Class I railroad located in coastal Georgia (Brunswick) puts 10 ft of fill on 14 ft of soft, normally consolidated fat clay over rock. The example estimates how much the clay will compress, how long it will take with drainage only upward, and how much secondary compression follows, and compares the post-construction settlement with the limit for the track.
Given and required for Example 6.2-1.
Given
Variable
Value
Description
Fill
H = 10 ft; γ = 120 pcf; B = 40 ft at base
Clay
14 ft CH; Cc = 0.56; e0 = 1.82; cv = 0.004 ft²/day; Cα = 0.022; γ = 110 pcf
Sc = 17 in.; 114 years undrained; 4.6 in. after construction: ground improvement required.
Solution
Primary settlement is about 17 in., which would take over a century to finish with drainage to one face. Even with wick drains finishing primary in 180 days, about 4.6 in. would remain after construction against a 1.0-in. limit.
Wick drains change the time, not the amount. The options are a surcharge preload that drives primary consolidation past the final load before track is laid, accepting the secondary settlement as maintenance, or column support (deep soil mixing or rigid inclusions) that bypasses the clay (Chapter 7.2). The 2:1 stress at mid-clay is used here as a conservative centerline value; a full analysis divides the clay into sublayers.
Example 6.2-2: Preload Duration for a Bridge Approach Fill
A bridge approach fill on a Class I railroad located in southern Manitoba sits on soft, normally consolidated silty clay drained by sand above and below. The question is how long a preload must stay in place for the remaining settlement to be within the allowable after track is laid.
Given and required for Example 6.2-2.
Given
Variable
Value
Description
Fill
18 ft; Δσ = 1,440 psf at mid-clay
Clay
20 ft CL-ML; Cc = 0.35; e0 = 1.25; cv = 0.08 ft²/day; γsat = 115 pcf
Two-way drainage, Hdr = 10 ft
zw
At the original ground surface
Limit
1.5 in. residual (assumed)
Drains option
5-ft triangular spacing; de = 5.25 ft
Required
Primary settlement
Degree of consolidation and time needed for 1.5 in. residual
Spot check: At 90%: t = 0.848 × 1,250 = 1,060 days, leaving 2.1 in.; 93% needs a further six months.
↓
Step 5 · With wick drains (rough)
Drainage path about de/2 = 2.6 ft; 1,241 × (2.6/10)²
About 84 days
↓
Solution
U ≥ 93%: 3.4 years without drains, about 3 months with them.
Solution
Primary settlement is about 21 in. The preload must reach 93% consolidation, which takes about 3.4 years with the natural drainage, or roughly 3 months with wick drains at 5-ft spacing.
The drain estimate is a rough analogy that ignores smear and well resistance; design the drains with Barron and Hansbo radial theory (Chapter 7.2). Tell the railroad’s project engineer the timeline early, and confirm it in the field with settlement plates at about 500-ft intervals read monthly: the plates, not the calculation, decide when the preload comes off.
Example 6.2-3: Settlement of an Overconsolidated Clay Under a Crane Slab
A crane rail pavement slab for an intermodal expansion on a Class I railroad located in Kansas City sits on stiff, overconsolidated fat clay. Because the new stress stays below the preconsolidation stress, only the stiff recompression branch is used, and the secondary compression ratio must match that branch too.
Spot check: Using Cα = 0.04 Cc = 0.017 would give 3.6 in., an eightfold overestimate.
↓
Solution
0.60 in. primary in a month; 0.43 in. over 50 years: no improvement needed.
Solution
Primary settlement 0.60 in., essentially complete within about a month; secondary about 0.4 in. over 50 years; about 1.0 in. in all.
The primary settlement can be taken out before the crane rail is set. The long-term part is small and nearly uniform in a uniform layer, so the differential depends on lateral variation in the clay between borings; check it against the 0.125 in. per 20 ft limit and provide rail adjustment in the crane rail design. Ground improvement is not needed for settlement alone.