Settlement predictions for an embankment on soft clay are only as good as the soil model, its parameters and how the construction is simulated. Chai and Carter (2011) summarize methods, checked against test embankments and case histories, for predicting deformations of soft ground improved by vertical drains, vacuum consolidation and soil-cement columns. The points below are those most useful for railroad embankments, widenings and approach fills.
6.2.18.1 Check the model against the measured strength
Before trusting a numerical model, compare the undrained shear strength profile it implies with field vane, unconfined compression or UU triaxial results. The model, its parameters and the initial stresses (including OCR) together control the strength the model uses; a mismatch here means the predicted settlement and stability will both be wrong. Correct field vane strengths for strain rate (Bjerrum).
6.2.18.2 Large settlement changes the problem
- Fill placed to grade. When the foundation settles during construction, more fill is needed to reach grade, and that fill is extra load. A model that keeps the original fill geometry under-predicts the load; one that does not keep the fill following the settlement over-predicts it.
- Stability. Settlement during construction lowers the effective height of the embankment, replaces some soft soil with stronger fill, and shortens drainage paths so that strength gains faster. For a test embankment built to failure in Malaysia, including these effects raised the computed factor of safety by about 0.1.
- Buoyancy. Where the water table is near the surface, settling fill and soil move below it and become buoyant, which reduces the effective load. For a test embankment in Japan, including buoyancy reduced the predicted final settlement by about 13%.
6.2.18.3 Vertical drain parameters
- Smear zone. Diameter ds = 2 to 3 times the equivalent mandrel diameter dm; use 3dm when there are no data. Base kh/ks on laboratory values multiplied by a field factor Cf that reflects stratification: close to 1 for a homogeneous deposit and much larger where thin sand or silt seams are present.
- Discharge capacity. Well resistance is usually unimportant when qw exceeds about 3,500 ft³/yr (100 m³/yr), but discharge capacity drops with time from confining pressure, kinking as the clay settles, and clogging.
- Sand mat. A drainage blanket at least about 1.6 ft thick with hydraulic conductivity above about 30 ft/day is close to free-draining. Clayey sand blankets slow consolidation.
- Partial penetration in a two-way draining layer. Where a sand layer underlies the clay, stopping the drains short of the sand gives almost the same rate of consolidation as full penetration. The optimum unimproved thickness at the bottom is Hc = 1 / [ 64/H² + 2.5 ch / (μ De² cv) ]0.5 (Eq. 6.2-25), where H is the clay thickness, De the drain influence diameter and μ the Hansbo drain resistance factor (Chapter 7.2, Section 7.2.3). It applies to deposits up to about 65 ft thick; use thickness-weighted ch and cv in layered ground. Example: H = 40 ft, ch/cv = 2, μ = 3, De = 5 ft gives Hc = 1/(0.040 + 0.067)0.5 = 1/0.327 ≈ 3 ft, so the drains could stop about 3 ft above the sand. The first term caps Hc at H/8, so the saving is modest but free.
6.2.18.4 Vacuum consolidation
- Vacuum adds an equal all-round consolidation stress and so tends to pull the ground inward. Inward lateral movement occurs where |σvac| > K0 σ′v0 / (1 − K0) (Eq. 6.2-26). With K0 = 0.5 and a vacuum of about 1,670 psf (11.6 psi), that is wherever the initial vertical effective stress is below about 1,670 psf, which in soft clay with a submerged unit weight of about 35 pcf extends to roughly 45 ft. Inward movement is therefore the normal case near the surface and through much of a typical soft deposit.
- Where inward movement occurs, vacuum produces less settlement than a fill surcharge of the same pressure, and tension cracks can open near the edge of the treated area.
- In a layer drained at both top and bottom, the vacuum cannot be held at the bottom boundary; the final vacuum distribution is triangular and settlement is less than with one-way drainage. Drains must stop short of a bottom sand layer, or the vacuum leaks into it; an optimum depth applies here too.
- Combining vacuum with fill surcharge offsets the inward movement against the outward push of the fill and is common practice.
6.2.18.5 Soil-cement columns
- Fully penetrating columns. Use the equilibrium method for settlement of the soil between columns, or the composite modulus method for average settlement. Because the columns are much stiffer than the clay, they also speed up consolidation even though their permeability is similar.
- Floating columns (columns ending in the soft layer). Stress carried by the columns varies with the area ratio α, the depth ratio β and depth. Chai and Carter treat the lower part of the improved zone as effectively unimproved and calculate the soft layers below the columns as a separate layer; much of the settlement then comes from below the column tips (Section 7.2.5).
- Installation movement. Injecting slurry or powder under pressure expands the ground like a cavity and pushes it sideways. Cavity-expansion methods predict this displacement using a soil modulus (E/Su of about 100 to 200 in soft clay) and the volume injected.
For railroad work: When soft ground under a track widening or approach fill is improved, the existing embankment and track beside it move too. Vacuum pulls the edge of the existing embankment inward and can crack it; column installation pushes it outward; both should be predicted, monitored with inclinometers and track geometry surveys, and controlled by sequence and distance from the operating track. When settlement is made up with extra fill or ballast to hold top-of-rail grade, count that fill as load, and remember that fill sinking below the water table becomes buoyant. Check that the drains stop short of an underlying sand where vacuum is used.
Source: Chai and Carter (2011), Chapters 2–5. Full reference under Supplemental References.