6.2.5 Time Rate of Consolidation

Settlement analysis is the serviceability companion to the bearing capacity calculations developed in Chapter 6.1.
Authors: Daniel P. Colwell and Mario Ruel
6.2.5 Time Rate of Consolidation
6.2.5.1 Terzaghi One-Dimensional Theory

The degree of consolidation U (fraction of ultimate settlement completed at time t) is governed by the dimensionless time factor T_v:

Karl Von Terzaghi
Karl Von Terzaghi
Equation 6.2-11 — Time Factor:

Tv = cv · t / H_dr²

Where:

  • c_v = coefficient of vertical consolidation (ft²/day; from ASTM D2435 consolidation test)
  • t = elapsed time (days)
  • H_dr = length of drainage path (ft): H_dr = H/2 for two-way drainage (sand above and below clay); H_dr = H for one-way drainage (clay bounded by impermeable rock)
Table 6.2-3 — Time Factor T_v vs. Average Degree of Consolidation U
U (%)T_v (simplified)T_v (exact)
100.0080.008
200.0310.031
300.0710.071
400.1260.126
500.1970.197
600.2870.287
700.4030.403
800.5670.567
900.8480.848
951.1631.129
99—1.781

For U ≤ 60%:

Tv = π/4 · (U/100)² (simplified parabolic approximation)

For U > 60%:

Tv = −0.933 · log(1 − U/100) − 0.085

Inputs: where each value comes from (4)
SymbolWhat it isComes fromHow to get itTypical range
Tvintermediate value computed on this pageAnother equationComputed: Tv = cv · t / H_dr²project-specific
cvcoefficient of vertical consolidation (ft²/dayLab test (or field)Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests.CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group
telapsed time (days)TimeElapsed test time (recorded) or the analysis time chosen for design.project-specific
Hdrlength of drainage path (ft): H_drAnother equationComputed: H_dr = H/2 for two-way drainage (sand above and below clay)project-specific
Drained vs Undrained Analysis
Drained vs Undrained Analysis
Equation 6.2-12 — Settlement at Time t:

S(t) = U · Sc,total

Equation 6.2-13 — Time to Achieve Target Degree of Consolidation:

t = Tv · H_dr² / cv

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
cvcoefficient of consolidationLab test (or field)Consolidation test (ASTM D2435 or D4186), log-time or root-time fit at the design stress range. ch from CPTu dissipation tests.CL 0.05–1, CH 0.005–0.2 ft²/day · by USCS group
6.2.5.2 Typical c_v Values
Table 6.2-4 — Typical Coefficient of Consolidation c_v (English Units)
Soil Typec_v (ft²/day)c_v (ft²/year)Notes
Soft organic clay0.0005–0.0050.2–2Coastal Georgia; Manitoba
Soft marine clay0.005–0.052–18Tidewater Virginia; Northeast passenger corridor
Medium clay0.05–0.218–73Kansas and Nebraska
Stiff clay0.2–1.073–365Appalachian residual soils
Very stiff clay1.0–10365–3,650Quick-draining; settle rapidly
Silty clay (CL-ML)0.1–0.537–183the Canadian Prairie provinces
Why Soil Consolidation Happens
Why Soil Consolidation Happens
Soil Consolidation Testing
Soil Consolidation Testing

Multiplying path length squared by unit conversion: if c_v in ft²/day and H_dr in ft, time t is in days.

Supplemental reference · Carter & Bentley (2016), §5.2

Estimating cv From the Liquid Limit

Before consolidation tests are available, the U.S. Navy chart of cv against liquid limit (NAVFAC DM-7, 1982) gives a first estimate of how fast a clay will drain. Carter and Bentley fitted its three trend lines with power functions that reproduce the chart within about 12% (cv in cm²/s, LL in %):

  • Undisturbed, recompression range (lower limit): cv = 25,000 / LL3.9. Values in recompression lie above this line.
  • Undisturbed, virgin compression range: cv = 80 / LL2.8.
  • Completely remolded (upper limit): cv = 1 / LL2.0. Remolded values lie below this line.

To convert cm²/s to ft²/yr multiply by 33,950 (to ft²/day, by 93).

Table 6.2-14. Coefficient of consolidation cv (ft²/yr) from liquid limit, from the curve fits to the NAVFAC chart
Liquid limit (%)3040506080100
Recompression, lower limit1,470480200993214
Virgin compression200894829136.8
Remolded, upper limit3821149.45.33.4

cv also depends strongly on structure, fissuring, sand partings and stress level, so the correlation gives only the likely order of magnitude. The virgin-compression values agree broadly with Table 6.2-4 for medium and stiff clays.

For railroad work: The roughly fivefold drop from the recompression to the virgin line is the important point. A fill that takes an overconsolidated clay past its preconsolidation stress both settles more and settles more slowly. Use the virgin line for preload and surcharge planning, and the remolded line for clay that has been disturbed by wick-drain installation (the smear zone, Section 6.2.8) or by construction traffic. Confirm the design cv with consolidation tests or CPTu dissipation tests, which also capture horizontal drainage through sand layers.

Source: Carter, M. and Bentley, S. P. (2016). Soil Properties and their Correlations, 2nd ed., §5.2 and Fig. 5.7, after U.S. Navy (1982). Summarized; table values computed from the fitted equations and converted to ft²/yr. Full reference under Supplemental References.