Silts and fine sands under track pump: wet fines are worked up into the ballast under each axle, the ballast fouls, the track goes soft and the surface fails, as in the mud spring under a western main line described in one of the conference papers. The subballast layer is the defense. It must be graded so that the subgrade cannot wash up into it and the ballast cannot punch down into it, which is the filter rule used for earth dams. AREMA Chapter 1, Part 2, sets out the method: plot the subgrade gradation, apply the filter ratios to its D15 and D50 to get the allowable band for the subballast, then size the combined ballast and subballast thickness with Talbot's equation.
| Character of subballast | R50 = D50 subballast / D50 subgrade | R15 = D15 subballast / D15 subgrade |
|---|---|---|
| Uniform gradation (Cu 3 to 4) | 5 to 10 | – |
| Well to poorly graded, subrounded grains | 12 to 58 | 12 to 40 |
| Well to poorly graded, angular particles (crushed stone) | 9 to 30 | 6 to 18 |
Also: maximum subballast size not larger than the largest ballast particle; no more than 5% passing the No. 200 sieve; crushed stone with a uniformity coefficient not over 15. Where the subgrade can pipe, keep subballast D15 below 5 times subgrade D85 and use a well-graded subballast.
Equation 2.4-27. Ballast plus subballast depth (Talbot)
pa = average pressure under the tie (psi), pc = allowable subgrade pressure including safety factor (psi), h in inches below the tie. AREMA keeps 12 in. of ballast below the tie so tamping does not reach the subballast; the rest of h is subballast.
| Check | Result |
|---|---|
| D50 band (9 to 30 × 0.24 mm) | 2.16 to 7.2 mm; subballast 4.75 mm |
| D15 band (6 to 18 × 0.046 mm) | 0.28 to 0.83 mm; subballast 0.675 mm |
| Uniformity coefficient | 14.2 |
| Passing No. 200 | 3.0 % |
| Ballast + subballast depth for pa = 55 psi, pc = 18 psi | 23.4 in. |
| Subballast thickness under 12 in. of ballast | 11.4 in. |
The bands and the 23.4 in. depth match the AREMA example (Figure 1-2-5 and Article 3.10.2.3).
Most dense-graded aggregate base specifications fall near this band, but each source should be checked against the actual subgrade, because a silt with D15 near 0.01 mm needs a much finer subballast than a sandy silt. Where suitable subballast is not available, a geotextile separator can supplement it.
Open the subballast filter calculator →
AREMA filter ratios for D15 and D50, maximum size, fines, uniformity and piping checks, and the Talbot thickness of ballast plus subballast.
This is the AREMA example of Table 1.5-20, worked by hand. A subballast over silt must satisfy two filter ratios so the silt cannot pump up into it, and then the ballast plus subballast must be thick enough to bring the subgrade pressure down to its allowable value.
| Variable | Value | Description |
|---|---|---|
| D15,s, D50,s | 0.046 mm and 0.24 mm | Subgrade gradation |
| Subballast | Crushed stone: D15 = 0.675 mm, D50 = 4.75 mm, Cu = 14.2, 3.0% passing No. 200 | Proposed material |
| Ratios | R50 9 to 30; R15 6 to 18 | Table 2.4-19, angular particles |
| pa | 55 psi | Average pressure under the tie |
| pc | 18 psi | Allowable subgrade pressure including safety factor |
| Ballast | 12 in. below the tie | AREMA minimum |
The crushed stone fits both filter bands and the gradation limits. The ballast plus subballast must be 23.4 in. deep, so 11.4 in. of subballast goes under 12 in. of ballast.
The results match the AREMA example (Figure 1-2-5 and Article 3.10.2.3). The bands scale with the subgrade: a silt with D15 near 0.01 mm would need a much finer subballast than this sandy silt, so each source must be checked against the actual subgrade. Where suitable subballast is not available, a geotextile separator can supplement it.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.