Fill placed dry of optimum and at low density can collapse when it is first saturated, by rising water or by a flood against the embankment. Section 2.4.10 gives the collapse potential from a single flooding test. Two findings from compacted-soil research refine that check for embankments.
Equation 2.4-28. Collapse settlement from the saturated compression curve
e0,i = as-placed void ratio of layer i; esat,i = void ratio on the saturated oedometer curve at the layer's vertical stress after flooding.
A centrifuge model of an embankment built at about 82% of maximum dry density on the dry side, flooded in two stages, confirmed the method for the zone away from the slopes. Scaled to the field, a 66-ft (20-m) embankment flooded to 16 ft (5 m) would settle about 3.3 ft (1 m). The prediction depends mainly on the height of capillary rise (how high the fill becomes saturated) and on the dry density profile before flooding; near the slopes, rotation of the stresses adds movement. The method is not suited to high-plasticity clays (Thorel et al., 2011, pp. 191–193).
Old end-dumped clay embankments went through this collapse when first wetted after construction, and the settlement was made up with ash and ballast (Chapter 2.5, Section 2.5.18). New fill, widenings and grade raises have not: specify placement density and moisture so that the saturated curve lies close to the as-placed state.
A 10-ft layer of sandy clay fill in a siding embankment was placed dry of optimum and lightly compacted. A flood is expected to saturate it. A saturated oedometer test on a specimen at the as-placed density gives the compression curve.
| Variable | Value | Description |
|---|---|---|
| H | 10 ft | Layer thickness |
| e0 | 0.62 | As-placed void ratio |
| σ′v | 1,200 psf | Vertical stress at mid-layer after flooding |
| esat | 0.55 | Void ratio on the saturated oedometer curve at 1,200 psf |
The layer will settle about 5 in. the first time it is saturated, on top of any consolidation of the foundation. Under track that is enough to need surfacing and possibly a slow order after the flood.
For a new or rebuilt embankment the cheaper fix is at placement: compact closer to optimum and to a higher density so that e0 sits near the saturated curve. For an existing fill, raise the flood protection or plan inspection and surfacing after high water.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.