2.4.7 Hydraulic Behavior: Erosion, Piping and Pumping

Silt sits between sand and clay: too fine to drain freely, too coarse and too weakly plastic to hold together when wet. That combination makes it the soil most often behind track pumping, frost heave, piping, sloughing cut slopes, collapsing loess and liquefaction of fine-grained ground.
Author: Daniel P. Colwell
2.4.7 Hydraulic Behavior: Erosion, Piping and Pumping

Silt is the most erodible natural soil. Its grains are too light to resist flowing water as sand does and too weakly bonded to hold together as clay does. On railroads this shows up as surface erosion of cut slopes and ditches, internal erosion (piping) along culverts and through embankments, and mud pumping under the track.

Critical hydraulic gradient and piping

ic = Gs − 11 + e      FSpiping = iciexit

Eq. 2.4-13 and Eq. 2.4-14

Where:

  • ic = critical (heave) gradient, about 0.9 to 1.0 for most silts
  • iexit = exit gradient at the seepage face, from a flow net or seepage model (Chapter 2.8, Section 2.8.5)
  • Target FSpiping ≥ 3 for silt where the exit is unprotected; a properly designed filter controls piping regardless of gradient

Silt exits are rarely protected by a gradient margin alone; they need a filter. The most common railroad cases are culvert outlets, the downstream toe of embankments that pond water, and seepage faces in cuts.

Filter criteria for silt base soils

Table 2.4-10: Filter Criteria for Protecting Silt (after NRCS NEH Part 633, Chapter 26)
Base soil categoryFines content of base soil (passing No. 200)Retention criterion for filter D15F
1> 85%D15F ≤ 9 × d85B, but not less than 0.008 in.
240–85%D15F ≤ 0.028 in.
315–39%D15F ≤ [(40 − A)/(40 − 15)](4 d85B − 0.028 in.) + 0.028 in.; A = % passing No. 200

The filter must also be more permeable than the base soil (D15F ≥ 4 to 5 × d15B, minimum 0.004 in.) and internally stable. Grain sizes are after regrading the base soil on the No. 4 sieve as the NRCS procedure requires.

For geotextile filters against silt, FHWA NHI-07-092 gives retention criteria of O95 ≤ D85 for wovens and O95 ≤ 1.8 D85 for nonwovens, with an apparent opening size no larger than a No. 50 sieve (0.012 in.) for soils with more than 50% fines. Gap-graded or dispersive silts need filtration testing (ASTM D5101 gradient ratio).

Dispersive and slaking silts

Some low-plasticity silts and silty clays deflocculate in fresh water and erode at very low velocity. Suspect dispersion where culverts or embankments show tunnels and jug-shaped holes after the first heavy rains. Screen with the crumb test (ASTM D6572), the double hydrometer (ASTM D4221) and the pinhole test (ASTM D4647).

Track pumping over silt subgrade

Under repeated wheel loads, a saturated silt subgrade surface softens, slurries and is pumped up into the ballast. The result is fouled ballast, loss of surface and recurring soft track. The remedies are those of Chapter 2.3, Section 2.3.5: drain the subgrade, install a subballast or sand blanket that meets the filter criteria above (or a separation geotextile), and keep the subballast sloped to the ditches. Undercutting and replacing ballast without fixing the subgrade drainage only resets the problem.