Eq. 2.7-4 (Hazen, with C = 100 in cm units; valid for clean sand with D10 about 0.004 to 0.1 in. and Cu < 5)
| Material | D10 (in.) | k (ft/day) | Drainage |
|---|---|---|---|
| Clean gravel (GP) | > 0.1 | > 3,000 | Excellent |
| Coarse sand (SP) | 0.02–0.04 | 300–3,000 | Excellent |
| Medium sand (SP) | 0.008–0.02 | 30–300 | Good |
| Fine sand (SP) | 0.003–0.008 | 3–30 | Good to fair |
| Silty sand (SM) | < 0.003 | 0.03–3 | Poor |
| Clayey sand (SC) | — | 0.0003–0.03 | Practically impervious |
Hazen is an order-of-magnitude estimate; field pumping or slug tests govern dewatering design (Chapter 2.8, Section 2.8.4).
Subballast and drainage layers must be permeable enough to drain and fine enough to filter the subgrade. Apply the filter criteria in Chapter 2.4, Section 2.4.7 (retention D15F ≤ 4 to 5 d85B for sandy base soils, permeability D15F ≥ 4 to 5 d15B).