2.7.7 Rock: Rock Mass Classification and Strength

Sand and rock are usually the good ground on a railroad, but each has its own hazards: loose sand settles, scours, runs and liquefies; rock falls, slides on its joints, weathers, slakes and dissolves.
Author: Daniel P. Colwell
2.7.7 Rock: Rock Mass Classification and Strength

The strength of a rock mass is controlled by its discontinuities. Rock mass classification systems turn core logs and face mapping into a rating used for cut slopes, foundations and tunnels.

Table 2.7-9: Rock Mass Rating, RMR89 (Bieniawski 1989), Summary of Parameters
ParameterRating range
Intact strength (qu)0–15
RQD3–20
Discontinuity spacing5–20
Discontinuity condition (roughness, aperture, infill, weathering, persistence)0–30
Groundwater0–15
Adjustment for discontinuity orientation (slopes, foundations, tunnels)0 to −60

Rock mass classes: 81–100 very good (I); 61–80 good (II); 41–60 fair (III); 21–40 poor (IV); < 21 very poor (V). GSI ≈ RMR89 − 5 for RMR89 > 23 (Hoek 2007).

σ1′ = σ3′ + σci (mb σ3′/σci + s)a

Eq. 2.7-6 (generalized Hoek-Brown criterion; mb, s and a from GSI, mi and disturbance factor D; Hoek, Carranza-Torres and Corkum 2002)

Shear strength of discontinuities

τ = σn tan[φr + JRC log10(JCS/σn)]

Eq. 2.7-7 (Barton and Choubey 1977)

Where:

  • φr = residual friction angle of the joint surface, typically 25° to 35° (lower for clay-coated or weathered joints)
  • JRC = joint roughness coefficient, 0 (smooth, planar) to 20 (very rough, undulating)
  • JCS = joint wall compressive strength (from Schmidt hammer or qu of the wall rock)
  • Cap the total friction angle at about 70°; for joints with clay infill thicker than the asperities, use the infill strength
Table 2.7-10: Typical Friction Angles of Rock Discontinuities
SurfaceFriction angle (deg)
Clean, rough, fresh joints in hard rock35–45 (plus roughness)
Planar, smooth joints and bedding in hard rock28–35
Joints in shale, schist and slate20–30
Joints with thin clay coating15–25
Clay-filled faults and bedding shears in shale8–15 (residual)

After Wyllie and Mah (2004) and Hoek (2007).