2.7.11 Worked Examples

Sand and rock are usually the good ground on a railroad, but each has its own hazards: loose sand settles, scours, runs and liquefies; rock falls, slides on its joints, weathers, slakes and dissolves.
Author: Daniel P. Colwell
2.7.11 Worked Examples
The examples use generic sites and are not taken from any client project. Two are for sand (strength and permeability) and two for rock (planar sliding and rock mass rating). Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 2.7-1: Peak Friction Angle of a Dense Sand

The friction angle of a sand is not a fixed property: it rises with density and falls with confining stress, because dense sand must dilate to shear and high stress suppresses dilation. Bolton’s relative dilatancy index captures both effects in one number.

σ1 σ3 Dense quartz sandDr = 70%p' = 2,000 psfφ′cv = 33°IR = ? φ′peak = ?Givenφ′cv = 33° (subangular quartz)Dr = 70%p' = 2,000 psfpref = 20.9 psf (1 kPa)RequiredRelative dilatancy index IR Peak triaxial friction angleBlack = given; red = required
Given and required for Example 2.7-1.

Given

VariableValueDescription
φ′cv33°Critical-state friction angle, subangular quartz sand
Dr70% (0.70)Relative density
p′2,000 psfMean effective stress
pref20.9 psf (1 kPa)Unit stress for the logarithm, so p′ enters in kPa

Required

  • Relative dilatancy index IR
  • Peak triaxial friction angle

Equations

  1. Eq. 2.7-3a: IR = Dr [10 − ln(p′/pref)] − 1 — Bolton (1986)
  2. Eq. 2.7-3b: φ′ = φ′cv + 3 IR — triaxial compression

Steps

Step 1 · Stress term
ln(2,000 / 20.9) = ln 95.7
4.56
↓
Step 2 · IR (Eq. 2.7-3a)
0.70 (10 − 4.56) − 1 = 0.70 × 5.44 − 1
IR = 2.81
Spot check: IR is limited to 0 to 4; 2.81 is inside the range.
↓
Step 3 · φ′ (Eq. 2.7-3b)
33 + 3 × 2.81
φ′ = 41°
↓
Solution
φ′ = 41° peak, triaxial.

Solution

IR = 2.81 and the peak triaxial friction angle is about 41°.

Eight degrees of the 41° come from dilation, not from friction between grains. For a shallow foundation, adopt a value 2° to 4° lower to allow for scatter and progressive failure; for a problem governed by large strains, the critical-state 33° is the safer value.

Example 2.7-2: Permeability of a Medium Sand for Dewatering

A culvert replacement excavation goes below the water table in clean medium sand. Hazen’s correlation from D10 gives a first estimate of permeability, which decides whether the excavation can be pumped from a sump or needs wellpoints.

1001010.10.01020406080100No. 4No. 200D10 = 0.006 in.k = ? Dewatering?Grain size (mm, log scale)Percent passingGivenD10 = 0.006 in. (0.0152 cm) about the No. 100 sieveClean medium sand (Hazen applies)RequiredEstimated permeability kConsequence for dewateringBlack = given; red = required
Given and required for Example 2.7-2.

Given

VariableValueDescription
D100.006 in. (0.0152 cm), about the No. 100 sieveEffective grain size
SoilClean medium sandHazen applies to clean sands

Required

  • Estimated permeability and its consequence for dewatering

Equations

  1. Eq. 2.7-4: k = C D10² — Hazen; C = 100 with D10 in cm and k in cm/s, or k (ft/day) ≈ 1.8 × 106 D10² with D10 in inches

Steps

Step 1 · k in US form (Eq. 2.7-4)
1.8×106 × 0.006² = 1.8×106 × 3.6×10−5
k ≈ 65 ft/day
↓
Step 2 · Check in cm units
100 × 0.0152² = 0.023 cm/s; × 2,835
≈ 66 ft/day
Spot check: The two forms agree within rounding.
↓
Solution
k ≈ 65 ft/day: plan wellpoints.

Solution

k ≈ 65 ft/day (about 0.02 cm/s).

That is permeable enough that the excavation will meet running sand below the water table unless the water is drawn down first. Plan wellpoints, and confirm k with a pumping or slug test, because Hazen’s estimate can be off by a factor of 2 or more.

Example 2.7-3: Planar Sliding in a Rock Cut

A bedding plane dips toward the track and daylights at the toe of a rock cut. The kinematic check says whether the block can slide; the limit-equilibrium check says how close it is; and solving for anchor force says what it would take to fix it.

TrackH = 30 ftψp = 40°ψf = 70°Bedding plane: c = 200 psf, φ = 30°γ = 160 pcfSliding? FS = ? Bolt force = ?GivenH = 30 ft; ψf = 70°; ψp = 40°γ = 160 pcfc = 200 psf; φ = 30°Dry; no tension crack (U = V = 0)Target FS 1.3 for boltingRequiredIs planar sliding possible?FS of the blockBolt force per foot for FS = 1.3Black = given; red = required
Given and required for Example 2.7-3.

Given

VariableValueDescription
H30 ftCut height
ψf70°Face angle
ψp40°Dip of the bedding plane toward the track
γ160 pcfRock unit weight
c, φ200 psf; 30°Bedding plane strength
WaterDry; no tension crackU = V = 0
FStarget1.3For bolting

Required

  • Whether planar sliding is possible
  • FS of the block
  • Bolt force per foot for FS = 1.3

Equations

  1. Kinematics: φ < ψp < ψf — plane daylights and is steeper than its friction angle
  2. Eq. 1: W = ½ γ H² (cotψp − cotψf) — block weight per foot
  3. Eq. 2: A = H / sinψp — plane length per foot
  4. Eq. 2.7-8: FS = [cA + (W cosψp + T) tanφ] / (W sinψp) — Hoek and Bray, U = V = 0, bolt force T normal to the plane

Steps

Step 1 · Kinematics
30° < 40° < 70°
Planar sliding is possible
↓
Step 2 · Weight and plane length (Eq. 1, 2)
½ × 160 × 900 × (1.192 − 0.364); 30 / 0.643
W = 59,600 lb/ft; A = 46.7 ft
↓
Step 3 · Resisting and driving forces
cA = 200 × 46.7 = 9,340; W cosψ tanφ = 59,600 × 0.766 × 0.577 = 26,360; W sinψ = 59,600 × 0.643 = 38,310
Resisting 35,700 lb/ft; driving 38,310 lb/ft
↓
Step 4 · FS (Eq. 2.7-8, T = 0)
35,700 / 38,310
FS = 0.93
Spot check: With c = 0, FS = tan30°/tan40° = 0.577/0.839 = 0.69: the cohesion is carrying the block.
↓
Step 5 · Bolt force for FS = 1.3 (Eq. 2.7-8)
T = [1.3 × 38,310 − 35,700] / tan30° = 14,100 / 0.577
T ≈ 24,400 lb per foot of cut
↓
Solution
FS = 0.93; about 24,400 lb/ft of bolting for FS = 1.3.

Solution

Planar sliding is possible and FS = 0.93. Bolts normal to the plane must supply about 24,400 lb per foot of cut to reach FS = 1.3.

The block stands today only because of 200 psf of cohesion on the bedding, which weathering and a single freeze-thaw cycle can destroy. Water would make it worse: add horizontal drains so a tension crack full of water cannot cancel the bolting, and check the wedges formed where cross joints intersect the bedding.

Example 2.7-4: Rock Mass Rating From a Core Log

The core log gives each of the five RMR parameters; the rating is their sum. The same log gives GSI, which feeds the Hoek-Brown strength used in slope and foundation design.

Slightly weathered limestone coreRQD = 65%RMR89 = ? Class = ? GSI = ?Givenqu = 12,000 psi (83 MPa)RQD = 65%Joint spacing 1 to 2 ftSlightly rough, aperture < 1/25 in.Slightly weathered walls; dampTable 2.7-15 (Bieniawski 1989)RequiredRMR89 before orientation adjustmentRock mass classGSIBlack = given; red = required
Given and required for Example 2.7-4.

Given

VariableValueDescription
qu12,000 psi (83 MPa)Slightly weathered limestone
RQD65%
Spacing1 to 2 ft (300 to 600 mm)Joint spacing
ConditionSlightly rough, aperture under 1/25 in., slightly weathered walls
WaterDamp
Rating tablesTable 2.7-15 (Bieniawski 1989)Strength, RQD, spacing, condition, groundwater and orientation ratings

Required

  • RMR89 before orientation adjustment, and class
  • GSI

Equations

  1. Eq. 1: RMR89 = R1 + R2 + R3 + R4 + R5
  2. Eq. 2.7-9: GSI ≈ RMR89(groundwater rating 15) − 5 — Section 2.7.17

Steps

Step 1 · Ratings
83 MPa → 7; RQD 65% → 13; 300–600 mm → 10; condition → 25; damp → 10
7, 13, 10, 25, 10
↓
Step 2 · RMR89
7 + 13 + 10 + 25 + 10
65: Class II, good rock
↓
Step 3 · GSI (Eq. 2.7-9)
Recompute with groundwater 15: 70; minus 5
GSI ≈ 65
↓
Solution
RMR89 = 65 (Class II); GSI ≈ 65.

Solution

RMR89 = 65, Class II (good rock), before the orientation adjustment; GSI ≈ 65.

The orientation adjustment, applied for the actual cut or foundation, can lower the class substantially, as Example 2.2-3 showed. GSI deliberately excludes water and orientation, because Hoek-Brown analyses handle those explicitly.