2.3.6 Track Modulus

Formerly Geo Rail Chapter 6.3 — Railroad Track Subgrade: Special Topics

The track subgrade is the engineered foundation upon which the entire superstructure — rail, ties, ballast, and subballast — rests.
Authors: Daniel P. Colwell and Mario Ruel
2.3.6 Track Modulus

Track modulus (u) characterizes the stiffness of the combined track-subgrade system. It is the support force per unit length of rail per unit of rail deflection (beam on elastic foundation):

Track stiffness: k = P_w / w_max (lb/in.)

Track modulus follows from the measured stiffness (Equation 2.3-4):

u = k^(4/3) / (64 EI)^(1/3) (lb/in./in., often written psi)

where:

  • P_w = wheel load (lb)
  • w_max = maximum rail deflection under wheel load (in.)

Typical track modulus values:

Table 2.3-4. Typical Track Modulus by Condition
Conditionu (lb/in./in.)Rating (Table 2.3-23)
Soft subgrade, worn ballast1,000–2,000Poor
Average track, mixed subgrade2,000–4,000Average
Good track, granular subgrade4,000–6,000Good
High-quality concrete tie, stiff subgrade6,000–8,000Within suggested optimum
Stiff track on a very stiff subgrade> 8,000Stiff; check dynamic loads

Track modulus directly affects bending moment and deflection in the rail. The characteristic length:

l = (4EI / u)^(1/4) (in.)

where:

  • E = rail elastic modulus = 30 × 10⁶ psi
  • I = rail moment of inertia (in.⁴); 136 RE rail: I = 95.0 in.⁴; 141 RE: I = 103.1 in.⁴
  • u = track modulus (psi)

The maximum rail bending moment:

M_max = P_w × l / 4 (in.·lb)

Higher track modulus reduces deflection but increases dynamic impact forces. A modulus of about 2,000 lb/in./in. is the commonly cited minimum for satisfactory performance, and heavy-axle and high-speed owners usually aim higher (Table 2.3-23). Confirm targets with the owner railroad.

Supplemental reference

Measuring trackbed stiffness in the field

McHenry and Rose (2012) reviewed the in-situ tests available for railroad subgrade. Beyond borings and CPT, the options most relevant to track modulus are:

  • Dynamic cone penetrometer (DCP) and PANDA — hand-driven cones that locate ballast/subballast/subgrade interfaces and give a strength profile from the shoulder or crib. The PANDA records blow energy and penetration electronically.
  • Falling weight / light weight deflectometer (FWD, LWD; ASTM D4694) — drop a known weight and back-calculate a layer modulus (EFWD = 0.24P / (dr·r)). Widely used on highway subgrade; LWD is increasingly used on new rail formations in Europe and Asia.
  • Seismic CPT — adds shear-wave velocity, giving a small-strain modulus that better matches the small cyclic strains under train loading than a resilient modulus does.
  • Rail-bound stiffness vehicles — the TTCI Track Loading Vehicle (Pueblo, CO), the Chinese Academy of Railway Sciences two-car system, the University of Nebraska laser deflection system, and the French Portancemètre measure track stiffness continuously. Their output is the best way to pick boring locations on long corridors.
How Does a Railway Track Transfer Train Load to Soil?
How Does a Railway Track Transfer Train Load to Soil?

Source: McHenry, M. and Rose, J. (2012). Railroad Subgrade Performance Indicators — A Review of Available Testing Methods. University of Kentucky

Reaction coefficients, ballast thickness and the stiffness balance

Profillidis expresses stiffness as a reaction coefficient ρ = load / settlement at the level considered (56 kip/in. per t/mm in the source). Typical component values are: rail 280,000–560,000 kip/in.; timber tie 50–80; concrete tie 1,200–1,500; ballast 10–30; rubber pad 560–1,120 kip/in.. The subgrade is the softest element in the chain:

Figure 2.3-33. Elastic line (deflected shape) of a timber tie on rock and on S3, S2 and S1 subgrades under two 11-ton loads. Profillidis Fig. 8.12.
Figure 2.3-33. Elastic line (deflected shape) of a timber tie on rock and on S3, S2 and S1 subgrades under two 11-ton loads. Profillidis Fig. 8.12.
Table 2.3-15. Subgrade reaction coefficients
Subgradeρ (kip/in.)
Silty28–84
Clay84–112
Gravel or rock112–450
Frozen450–560

Existing track with ballast only (no subballast): total ρ = 8.4–56 kip/in., average 17 kip/in.. Bridges: 560–840 kip/in..

Table 2.3-16. Effect of ballast thickness e on subgrade stress and track stiffness (Boussinesq, multilayer elastic)
e (in.)068121620
λ (subgrade stress ratio)10.700.500.350.250.20
ρ / ρ011.402.002.854.005.00

Design should satisfy two principles: stresses reaching the subgrade must stay below failure values, and the track must remain flexible. A rock subgrade is more than three times as stiff as a clay subgrade, so even rock cuts need a full ballast and subballast section. In the finite-element breakdown (Figure 2.3-34), the subgrade supplies about 40–43% of total track elasticity, the track bed 20–22% and the rail pads 25–34%.

Figure 2.3-34. Contribution of each component to total track elasticity, timber vs. concrete ties. Profillidis Fig. 8.16.
Figure 2.3-34. Contribution of each component to total track elasticity, timber vs. concrete ties. Profillidis Fig. 8.16.

After Profillidis (2014), §8.2.2–8.2.3, §8.4.9, §8.8, Table 8.1, Figs. 8.12, 8.16. Full reference under Supplemental References.

Measuring track modulus: method, slack and nonlinearity

Track modulus lumps the fastenings, ties, ballast, subballast and subgrade into one spring. It cannot be calculated from the components. It has to be measured. Selig and Waters describe three methods:

  • Single point load (preferred). Measure the maximum rail deflection under one load: u = [P / (2 ymax)]4/3 / (4 EI)1/3 = ¼ (EI)−1/3 (P / ymax)4/3. This follows from ymax = Pβ / (2u) with β = [u / (4 EI)]1/4 (Winkler beam on elastic foundation; Hetényi 1946; Selig and Waters 1994, Ch. 14).
  • Deflection basin (Talbot). The load equals u times the area of the deflection basin. This averages over a length of track.
  • Multi-axle vehicle. Convenient, but it relies on superposition.

Remove slack. With all three methods, use the difference between a light seating load and a heavy load. This removes gaps and slack under the ties. Load–deflection curves are strongly nonlinear, and more so as track settles, so always report the load levels with the modulus.

Field values and correlation. At eight U.S. sites, u ranged from 2,200 to 7,000 psi. CPT soundings to at least 16 ft below the tie, back-analyzed with a multilayer model, gave a subgrade resilient modulus of about Er ≈ 14 qc for all the data, or about 21 qc with outliers removed. This makes CPT a practical way to estimate track stiffness along a corridor.

Sensitivity. In the model, fastener stiffness had the largest effect on u, but it varies little in real track (about 10%). Ballast modulus, ballast depth, tie spacing and rail section each changed u by 10–20%. The subgrade remains the most influential variable in the field.

After Selig & Waters (1994), chs. 5 and 10. Full reference under Supplemental References.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-18 Shear-wave velocity from CPT VₛUse: Young, uncemented Holocene–Pleistocene soils. Limits: Underpredicts Vs in aged or cemented soils. Measure Vs directly for seismic site class.
  • RK-10 UCS from point load index σ꜀Use: Hard, isotropic rock; quick strength index in field. Limits: K varies widely with rock type and anisotropy; calibrate with lab UCS. Unreliable in weak rock (σc < ~3,600 psi).
2.3.6.1 Track Modulus and Rail Deflection

Track modulus u is the support force per unit length of rail per unit of rail deflection. It lumps the fasteners, ties, ballast, subballast and subgrade into one spring bed under the rail. The beam-on-elastic-foundation model that defines it is too simple to give stresses inside the substructure (Chapter 2.1 uses a multilayer model for that), but u remains the standard single number for track support, and it can be measured directly from rail deflection under a known load.

2.3.6.1.1 Method

Equation 2.3-3. Beam on elastic foundation (one wheel load P)

β = [u/(4EI)]1/4   δ0 = Pβ/(2u)   M0 = P/(4β)   q0 = uδ0

Away from the load: δ(x) = (Pβ/2u)e−βx(cosβx + sinβx) and M(x) = (P/4β)e−βx(cosβx − sinβx); wheels are superposed.

Equation 2.3-4. Track stiffness and modulus from a measured deflection

k = P/δ0   u = k4/3/(64EI)1/3

Track stiffness k includes the rail's bending rigidity; track modulus u does not.

Table 2.3-22. Rail moments of inertia (North American sections)
Rail100 RE115 RE132 RE136 RE140 RE
I (in.4)49.065.688.294.996.8
Table 2.3-23. Track modulus as a measure of support
Track modulus (lb/in./in.)Rating
Below 2,000Poor; 2,000 is the commonly cited minimum for satisfactory performance
2,000 to 4,000Average
Above 4,000Good
5,000 to 10,000Suggested optimum range

Parametric studies show the subgrade modulus dominates: raising it from about 2,000 to 20,000 psi raised the track modulus roughly eightfold, while granular layer thickness and modulus had a much smaller effect. A thicker soft subgrade over rock lowers the modulus. Below about 4,000 lb/in./in., deflections and subgrade stresses rise steeply, which is why soft-subgrade sites show up first in track geometry records.

2.3.6.1.2 Worked example: 136 RE rail, two-wheel truck

Table 2.3-24. 39-kip wheels at 70 in., u = 3,000 lb/in./in., ties at 19.5 in. (calculator output)
ResultValue
Characteristic length 1/β44.1 in.
Rail deflection under a wheel (both wheels acting)0.177 in.
Rail bending moment under a wheel340.9 kip-in.
Rail-seat load10.4 kips
Measured case: 20 kips gives 0.10 in. deflection; track modulus2,063 lb/in./in.

The second wheel adds about a fifth to the deflection but reduces the moment, because at 70 in. it sits beyond the point where the moment under a single wheel changes sign. The measured case (20 kips producing 0.10 in.) back-calculates to about 2,060 lb/in./in., at the bottom of the average range.

Open the track modulus calculator →
Rail deflection, moment and rail-seat load for one or two wheels from an assumed track modulus, or track stiffness and modulus from a measured load and deflection.

Example 2.3-7: Rail Deflection, Moment and Track Modulus for a Two-Wheel Truck

Table 2.3-24 gives calculator output for 136 RE rail. Worked by hand, the example shows how a second wheel adds to the deflection under the first but reduces the moment, and how a measured deflection gives the track modulus.

Ties at s = 19.5 in.; field: 20 kips → 0.10 in.P = 39 kipsP = 39 kipsa = 70 in.springs: track modulus ul, ymax, Mmax, rail-seat load = ?u from measured case = ?GivenTwo-wheel truck, 39 kips per wheelWheel spacing a = 70 in.EI = 30×10⁶ × 94.9 in.⁴ (136 RE)Assumed u = 3,000 lb/in./in.Tie spacing 19.5 in.Measured: 20 kips gives 0.10 in.RequiredCharacteristic length, deflection,moment, rail-seat loadTrack modulus from field caseBlack = given; red = required
Given and required for Example 2.3-7.

Given

VariableValueDescription
P39 kips per wheelWheel load
a70 in.Wheel spacing
E I30 × 106 psi × 94.9 in.4136 RE rail (Table 2.3-22)
u3,000 lb/in./in.Assumed track modulus
s19.5 in.Tie spacing
Measured20 kips gives 0.10 in.Field load and deflection for the back-calculation

Required

  • Characteristic length, deflection, moment and rail-seat load
  • Track modulus from the measured case

Equations

  1. Eq. 1 (Equation 2.3-3): 1/β = (4EI / u)1/4 — characteristic length
  2. Eq. 2: δ = (Pβ / 2u)[1 + e−βa(cosβa + sinβa)] — deflection under one wheel with the second superposed
  3. Eq. 3: M = (P / 4β)[1 + e−βa(cosβa − sinβa)] — moment under one wheel
  4. Eq. 4: q = u δ s — rail-seat load
  5. Eq. 5 (Equation 2.3-4): k = P/δ0; u = k4/3 / (64EI)1/3 — track stiffness and modulus from a measurement

Steps

Step 1 · Characteristic length (Eq. 1)
(4 × 30×106 × 94.9 / 3,000)1/4 = (3.80×106)1/4
1/β = 44.1 in.
↓
Step 2 · Second-wheel term
Uses: βa = 70 / 44.1 = 1.59
e−1.59 = 0.205; cos 1.59 = −0.015; sin 1.59 = 1.000
Deflection multiplier 1 + 0.202 = 1.20; moment multiplier 1 − 0.208 = 0.79
↓
Step 3 · Deflection (Eq. 2)
39,000 / (2 × 3,000 × 44.1) = 0.147 in. × 1.20
δ = 0.177 in.
↓
Step 4 · Moment (Eq. 3)
39,000 × 44.1 / 4 = 430 kip-in. × 0.79
M = 341 kip-in.
↓
Step 5 · Rail-seat load (Eq. 4)
3,000 × 0.177 × 19.5
q = 10.4 kips
Spot check: About 27% of the wheel load, typical for this tie spacing.
↓
Step 6 · Track modulus from the measurement (Eq. 5)
k = 20,000 / 0.10 = 200,000 lb/in.; u = 200,0004/3 / (64 × 30×106 × 94.9)1/3 = 1.168×107 / 5,670
u = 2,060 lb/in./in.
↓
Solution
δ = 0.177 in.; M = 341 kip-in.; q = 10.4 kips; measured u = 2,060.

Solution

1/β = 44.1 in.; deflection 0.177 in.; moment 341 kip-in.; rail-seat load 10.4 kips. The measured case gives u = 2,060 lb/in./in.

The second wheel sits beyond the point where the single-wheel moment changes sign, so it adds about a fifth to the deflection but takes about a fifth off the moment. The measured modulus of about 2,060 is at the bottom of the average range of Table 2.3-23; soft subgrade is the usual reason, and it is the first thing to check before more ballast is added.

2.3.6.1.3 Sources in the library

These documents are in the reference library. The method summaries above are paraphrased; equations are standard or published forms.

  • Railway Geotechnics (Li, Hyslip, Sussmann and Chrismer, 2016), Chapter 4: beam on elastic foundation, track stiffness and modulus, GEOTRACK parametric study, modulus as a measure of support.Find source ↗
  • Track Geotechnology and Substructure Management (Selig and Waters, 1994), Chapter 2: rail section properties.Find source ↗Library entry
  • Qualitative Analysis for Dynamic Behavior of Railway Ballasted Track (thesis), Ballast folder.Find source ↗Library entry