Formerly Geo Rail Chapter 6.3 — Railroad Track Subgrade: Special Topics
Source: Herbert, D. and Gee, B. (2021). “Durability and Performance of Geogrid-Stabilized Ballast and Sub-ballast Track Section in Mobile, Alabama.” AREMA 2021 Annual Conference · Coleman, D. M. (1990). Use of Geogrids in Railroad Track: A Literature Review and Synopsis. U.S. Army Engineer Waterways Experiment Station, Misc. Paper GL-90 · Getzner Werkstoffe. Sub-Ballast Mats (product technical brochure)
ASCE (2012) describes the owner’s resident project representative (RPR) as the person or firm that administers the construction contract on the owner’s behalf. RPR duties may include performing or directing QA, monitoring expenditures and progress payments, pushing timely review of submittals by the designer, evaluating and deciding on unforeseen conditions, coordinating owner site activities such as safety monitoring and testing, building the project record, and negotiating change orders.
The Manual divides materials into two classes. In situ materials are the native soil and rock; their suitability is established by laboratory testing and engineering evaluation, and the results and any retesting go into the project file. Procured materials include natural products such as earth fill and aggregates as well as manufactured items. For each procured material the file should record the qualification procedure and acceptance criteria, test type and date, the signature of the person testing, results, any nonconformance reports and, where specified, where in the structure the tested material was placed. Where workmanship is critical, the contractor may build a mock-up that, once accepted, becomes the standard for the remaining work. Substitutions are accepted only after the designer confirms they meet project objectives, and are then formalized by change order.
On unit-price contracts, common where quantities cannot be known precisely, the RPR and contractor jointly measure completed quantities. The Manual acknowledges that unknown soil conditions can change quantities enough that a unit price must be renegotiated, sometimes with a change in contract time. On lump-sum work the RPR checks that the schedule of values is not unbalanced.
For railroad work: Ballast, subballast, geosynthetics and select fill are procured materials and should be accepted against the railroad’s specification with traceable test records tied to stockpile, delivery ticket and placement station. Native subgrade exposed by undercutting is an in situ material whose acceptance (or further undercut) depends on the engineer’s evaluation at the time, which is a natural role for the RPR. A short test section at the start of a subgrade rehabilitation, accepted on proof rolling and density, can serve as the mock-up that sets the standard for the rest of the work.
Source: American Society of Civil Engineers (2012). Quality in the Constructed Project: A Guide for Owners, Designers, and Constructors, 3rd ed. ASCE Manuals and Reports on Engineering Practice No. 73. Reston, VA: ASCE, pp. 169–175. Summarized and paraphrased. Full reference under Supplemental References.
Function analysis is the core of value management. It describes what a project or element must do, as two-word verb–noun pairs, before anyone discusses what it should be. Kelly, Male and Graham have a team brainstorm functions, sort them from high-order needs down to low-order wants, and arrange them in a FAST (Function Analysis System Technique) diagram. Read left to right, the diagram answers “how?”; read right to left, it answers “why?”. A scope line separates the project’s mission from the functions open to brainstorming. In their technical FAST for a river crossing in a park, the mission “facilitate passage across river” leads to the primary function “support people,” with the parallel function “span river” and secondary functions such as “protect people” and “control people.” Design objectives such as “non-slip surface” and “reduce downtime due to flooding” sit above the diagram. Because the team works from functions, the solutions it considers range beyond bridge types: the authors note the answer might be a cable ferry rather than a bridge. For elements, element function analysis has five stages: pick the cost-dominant elements; list every function the element can perform; delete the functions not needed in this context; brainstorm against the functions that remain; and evaluate.

For railroad work: Apply element function analysis to the track substructure before choosing a remedy for a chronic soft spot. The candidate functions of ballast, subballast and subgrade include “distribute load,” “resist shear,” “drain water,” “separate layers,” “restrain track,” “limit frost penetration” and “provide resilience.” Keep only those the investigation shows are failing. If the evidence points to failed “drain water” and “separate layers,” that is, mud-pumping fines with a sound deeper subgrade, the brainstorm should center on drainage and filter or separation solutions, not a deep undercut. If “resist shear” is failing in the subgrade itself, the option set changes. Stating the needed functions explicitly ties the recommendation to the diagnosis and gives reviewers a clear reason why other remedies were set aside.
Source: Kelly, J., Male, S. and Graham, D. (2004). Value Management of Construction Projects. Oxford: Blackwell Science, pp. 62–69, 75–77. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Passeck’s chapter in Jacob and Müller builds earthwork unit prices from the bottom up. The direct cost of each bid item is split into five parts: labor, equipment (including fuel and lubricants), materials, third-party services and transport, and site facilities. Percentage surcharges are then added. The example uses 8% general overhead, 6% site overhead, 3% risk and 3% profit, a total of 20%.
The cost components are built up as follows:
Worked haul example (book values converted to US units):
The haul example from Jacob and Müller, in US units. Matching the truck fleet to the loader is the core of an earthwork unit price, and the same arithmetic sizes the haul for undercutting spoil and imported subballast.
| Variable | Value | Description |
|---|---|---|
| QL | 327 BCY/hr | Loader output |
| c | 10.5 BCY per truck | Truck capacity (13.1 LCY at 25% swell) |
| L | 16,400 ft one way | Haul distance |
| v | 13 mph | Haul speed (70% of the 18.6-mph site limit) |
| tload, tdump | 3 min and 2 min | Fixed times per cycle |
Each truck cycles in about 33.6 min and moves 18.7 BCY/hr; 18 trucks keep the loader working.
Travel is 85% of the cycle, which is why haul dominated the unit price in the source. On a railroad the same calculation is made per effective work-window hour, after setup, flagging and clearing, and with on-track or hi-rail haul where trucks cannot cross the live track.
The excavate-haul-place-compact item then added loading (14%), haul (57%), spreading and compaction with one dozer and two rollers (25%), and fine grading (4%). Haul dominated the cost.
The authors stress pricing all earthwork items together, using a mass haul diagram to minimize haul distance and stockpiling, and adjusting manufacturer production figures for soil class, swell and site constraints.

For railroad work: Undercutting and subgrade rehabilitation estimates should be built the same way. The cycle is constrained by track-window length, the number of access points, and on-track or hi-rail haul instead of open haul roads. Haul units cannot cross or foul the live track without protection. Use productivity per effective window hour after setup, flagging and clearing time, not per shift hour. Show spoil disposal (especially fouled ballast) and imported subballast as separate cost lines.
Source: Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn, pp. 36–50. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Pratt prices excavation from productivity and crew cost, and keeps the two separate. Unit cost equals crew-hours per unit times cost per crew-hour. That way a change in wage rates and a change in productivity can each be applied on its own. Applied separately, an 8% wage increase and a 10% productivity loss raise the unit price by 18.8%, not the 18% you get by adding them.
Fixed costs depend heavily on job size. A backhoe that digs 60 CY/h, with $4,000 for transport and set-up, comes to $2.73/CY for equipment on a 3,000-CY job but $14.73/CY on a 300-CY job.
For hauling, Pratt sizes the truck fleet so that the excavator or loader never waits:
Number of trucks = (round-trip travel time + unloading time) / loading time + 1, always rounded up
Loading time is the truck’s bank-measure capacity divided by the loader output. Bank capacity is the loose capacity divided by (1 + swell). In his gravel example, the pit is 16 miles away, trucks average 20 mph and take 5 minutes to unload, so the cycle away from the loader is 101 minutes. A 12-CY truck with 12% swell carries 10.71 bank CY. At 50 BCY/h the loader fills it in 12.85 minutes, so the fleet is 101/12.85 + 1 = 8.86, rounded up to 9 trucks. With a $2.50/CY pit royalty, the delivered gravel costs $16.34 per bank CY. A price quoted per ton is converted using the weight of a compacted cubic yard: $/CY = $/ton × (lb/CY) / 2,000.
Table 2-PM2. Table: Loose and bank weights and compaction factors (after Pratt 2011, Figure 10.2)
| Material | Loose (lb/CY) | Bank (lb/CY) | Compaction factor |
|---|---|---|---|
| Clay, dry | 2,500 | 3,100 | 24.0% |
| Gravel, pit-run, dry | 2,550 | 2,850 | 11.8% |
| Sand, dry | 2,400 | 2,700 | 12.5% |
| Sand and gravel, dry | 2,900 | 3,250 | 12.1% |
For railroad work: on undercutting and subgrade rehabilitation, the track window usually sets the production rate, not the excavator. Estimate the cubic yards that can be removed and replaced per window. Then size the spoil trucks, side-dump cars or ballast cars with Pratt’s formula, so the machine never waits during a window that has already been paid for. On short jobs, fixed costs (mobilization, work-train set-up, flagging) are spread over a small quantity and dominate the unit price, as Pratt’s 300-CY case shows. Price imported subballast in bank measure, with explicit compaction and waste allowances.
Source: Pratt, D. J. (2011). Fundamentals of Construction Estimating, 3rd ed. Clifton Park, NY: Delmar Cengage Learning, pp. 224–235. Summarized and paraphrased. Full reference under Supplemental References.