↑ Parent Menu⌂ Main Menu
← Chapter 2.3 Track Substructure: Ballast, Subballast and Subgrade
GHRM
Railway Ground Hazard Risk Management · 2.0 · The Underworld
Sections · click a car to open it

2.3.7 Ballast Fouling Index

Formerly Geo Rail Chapter 6.3 — Railroad Track Subgrade: Special Topics

The track subgrade is the engineered foundation upon which the entire superstructure — rail, ties, ballast, and subballast — rests.
Authors: Daniel P. Colwell and Mario Ruel
2.3.7 Ballast Fouling Index

Ballast fouling reduces drainage capacity and increases subgrade stress. The Fouling Index (FI) quantifies fouling:

Figure 2.3-65. A failed area: new ballast on top, almost none functionally present beneath.
Figure 2.3-65. A failed area: new ballast on top, almost none functionally present beneath.

FI = P₄ + P₂₀₀

where:

  • P₄ = percent passing No. 4 sieve (%)
  • P₂₀₀ = percent passing No. 200 sieve (%)
Table 2.3-5. Ballast Fouling Categories (AREMA MRE Ch. 1, Table 1-2-3; recommended actions are this manual's)
FI ValueFouling ConditionRecommended Action
< 1CleanNo action; monitor
1–10Moderately cleanMonitor; plan maintenance
10–20Moderately fouledSchedule ballast cleaning
20–40FouledImmediate ballast cleaning
> 40Highly fouledBallast undercutting; possible subgrade work

Many railroads track fouling condition through periodic ballast sampling programs. Include fouling index data in geotechnical reports for mainline rehabilitation projects. GPR can estimate fouling condition non-destructively (Section 2.3.9).

Supplemental reference

Where the fouling actually comes from

Selig and Waters (1994) examined the source of fouling material at a large set of sites. Breakdown of the ballast itself was the major source at 76% of sites; upward migration from an underlying granular layer (usually old roadbed mixed in at the interface) was the major source at 13%. Contamination pumped up from the subgrade was rare. Li et al. point out that muddy ballast is often wrongly blamed on subgrade pumping when it is really ballast abraded under traffic in the presence of water — which changes the remedy from subgrade treatment to ballast renewal and drainage.

Field-friendly fouling criteria

The Selig fouling index depends on the percent passing the No. 200 sieve, which is hard to measure reliably in the field. The railroad uses the percent passing the ¾-in. sieve instead; Sussmann et al. (2012) matched the two scales:

Table 2-S4. Selig & Waters fouling index vs. A Class I railroad ¾-in. sieve criterion

CategoryFouling index (Selig & Waters)% passing ¾ in.
Clean< 1–
Moderately clean1 to < 10< 25
Moderately fouled10 to < 2025–40
Fouled20 to < 4040–50
Highly fouled> 40> 50

Table 2-S5. Ballast cleaning intervention limits used by different agencies

Agency / sourceCriterionLimitBasis
Selig & WatersFouling index40 / 30Highly fouled / drainage reduction
SpoornetFISpoornet = 0.4P19 + 0.3P6.7 + 0.2P1.18 + 0.1P0.1580Gradation change
Class I% passing ¾ in. (¾ in.)40%Highly fouled
UIC% passing ½ in. (½ in.)30%–
ERRI% passing ⅞ in. (⅞ in.)30%–

For field sampling programs, the single-sieve Class I railroad criterion lets the crew classify a sample at the tie end without shipping it to the lab; reserve full gradations (and FI) for representative samples and design stations.

Figure 2.3-66. Full undercutter in operation.
Figure 2.3-66. Full undercutter in operation.

Source: Li, D., Hyslip, J., Sussmann, T. and Chrismer, S. (2016). Railway Geotechnics. CRC Press / Taylor & Francis

Ballast cleaning trigger, renewal cycle and reuse

  • Cleaning trigger: ballast cleaning machines are used when grains smaller than 0.87 in. make up more than 30% of the ballast volume. The cleaner removes all stone smaller than 1.4 in. to a depth of 10 in. below the tie, at about 1,300 ft of track per hour.
  • Cycles on main lines: tamping every 3–5 years; ballast replacement every 15–30 years depending on stone strength and traffic (15–20 years on high-speed lines, against about 50 years for concrete ties and rail). Ballast stone tolerates only a limited number of tamping cycles.
  • Longer life: harder stone, a wider ballast section and more uniform compaction lengthened the Swiss tamping interval from 4 to 7 years and cut maintenance cost by 40% over 10 years.
  • Reuse: fouled ballast removed from track weighs about 106 pcf against 94 pcf new. If strength remains, washed spent ballast can be reused as subballast or formation layer on secondary lines, or as ballast on lines under 87 mph after treatment. France removes about 1 million tons per year this way; disposal costs (up to €60/t) often make reuse economic.
  • Vegetation contaminates ballast with debris that blocks drainage, accelerates tie decay by root expansion and hides defects from visual inspection.
Figure 2.3-67. Twelve inches of clean ballast beneath the ties, correctly profiled.
Figure 2.3-67. Twelve inches of clean ballast beneath the ties, correctly profiled.

After Profillidis (2014), §12.7, §16.8–16.9, §16.12, §9.16, Figs. 9.21, 16.10. Full reference under Supplemental References.

Fouling sources, the failure zone, and choosing a repair

Fouling comes mainly from particle breakdown under traffic, plus abraded tie material, spilled lading (coal, grain), wind-blown sand and silt, slurry pumped up from the subgrade, chemical weathering, and maintenance tools (tamping accelerates breakdown). Gradation testing shows a failure zone. Once material finer than ¾ in. passes about 25% (the ideal point to undercut) and heads toward 40% (action mandatory), degradation accelerates sharply, typically within 500 MGT. Ballast next to an active mud spot is usually near its own failure zone. Visual inspection is not enough; use sieve analysis or GPR.

Table 2.3-19. Ballast repair options when ballast is fouled
MethodCost / durationResult
TampingLow cost, very short termLow efficiency: “tamping mud”
Skin liftLow short-term costOut of the mud temporarily
Major liftMediumLonger term, but the problem may return
Shoulder cleaningMediumBetter if ballast is not too fouled; can extend ballast life
Full-depth undercuttingHighGreatest gain in internal drainage and bearing; about 15 years at 50 MGT/year

Undercut to about 12 in. below the ties, with the bar inclined to leave a 2% slope that drains to ditches or shoulders. Plan depths so every track drains on multiple-track territory, and place waste where it neither blocks drainage nor loads the shoulder. Undercutting without restoring lateral drainage gives minimal benefit. Watch for buried fiber. A documented move from reactive to planned ballast management cut ballast-related slow orders from over 600 to under 20 per year, ballast derailments from about 8 to about 0, and spending from over $250M to under $100M per year.

Figure 2.3-35. Ballast profiling machine restoring the shoulder section. Profillidis Fig. 16.10.
Figure 2.3-35. Ballast profiling machine restoring the shoulder section. Profillidis Fig. 16.10.
Figure 2.3-36. Track zones for vegetation control: inter-track (A), ballast (B), shoulder (C1, C2), walkway (D1, D2), slope (E), drainage channel (F). Profillidis Fig. 9.21.
Figure 2.3-36. Track zones for vegetation control: inter-track (A), ballast (B), shoulder (C1, C2), walkway (D1, D2), slope (E), drainage channel (F). Profillidis Fig. 9.21.
Figure 2.3-68. Ballast problems under reactive maintenance.
Figure 2.3-68. Ballast problems under reactive maintenance.
Figure 2.3-69. The same metrics after criteria-based planned maintenance.
Figure 2.3-69. The same metrics after criteria-based planned maintenance.

After Geotechnology for Railroaders Program, Module 3; §06–07, §13. Full reference under Supplemental References.

What fouling does to drainage and settlement, and how to limit it

Table 2-SW4. Ballast hydraulic conductivity by fouling index (after Parsons)
ConditionFouling indexkh, in./skh, mm/s
Clean< 11–225–50
Moderately clean1–90.1–12.5–25
Moderately fouled10–190.06–0.11.5–2.5
Fouled20–390.0002–0.060.005–1.5
Highly fouled≥ 40< 0.0002< 0.005

Settlement. In box tests, settlement increased with fouling index. A small gap under the tie (0.039–0.16 in. of lift-off between loads) increased settlement by about an order of magnitude and accelerated both fouling and tie wear. Highly fouled ballast that settles quickly after tamping is a sign that it needs cleaning.

Sources vary by railway. British Rail attributed its fouling as follows:

  • External sources (spillage, airborne): 52%.
  • Attrition: 21%.
  • Tamping: 20%.
  • Delivered with the ballast: 7%.

North American sites were dominated by ballast breakdown (see above). Sample before assuming the source. In BR tests, 20 tamping insertions broke 15–45% of the 1½–2-in. particles, and each tamp produced 4–9 lb of material finer than ½ in.

Not all fines are equal. Sand and gravel fouling is tolerable. Silt forms an abrasive slurry. Clay fouling may require 100% ballast replacement.

Figure 2.3-64. Fouled ballast: fines filling the voids that should drain water.
Figure 2.3-64. Fouled ballast: fines filling the voids that should drain water.

Six ways to limit fouling:

  • Deliver ballast clean.
  • Limit spillage from cars.
  • Tamp only when geometry requires it.
  • Specify attrition-resistant stone.
  • Keep the ballast drained.
  • Provide a blanket over fine-grained subgrade.

Undercut or clean at a fouling index of about 40 if the ballast is cleanable. Plow or sled it out if it is fouled with wet, plastic fines.

After Selig & Waters (1994), chs. 8, 13 and 16. Full reference under Supplemental References.

← Previous · 2.0 The Underworld Chapter 2.2 — Soil and Rock Classification
Next · 2.0 The Underworld → Chapter 2.4 — Silts: Properties, Typical Values and Liquefaction