2.3.8 Subgrade Drainage Design

Formerly Geo Rail Chapter 6.3 — Railroad Track Subgrade: Special Topics

The track subgrade is the engineered foundation upon which the entire superstructure — rail, ties, ballast, and subballast — rests.
Authors: Daniel P. Colwell and Mario Ruel
2.3.8 Subgrade Drainage Design

Poor drainage is the single most common root cause of subgrade problems in North American railroad practice. The geotechnical consultant is responsible for assessing existing drainage adequacy and designing improvements.

Road Drainage Fundamentals
Road Drainage Fundamentals
Culverts
Culverts
2.3.8.1 Drainage Design Criteria

Required drainage capacity:

Q = C × i × A (ft³/s) [Rational Method]

where:

  • C = runoff coefficient (about 0.20–0.40 for railroad yards, FHWA HDS-2; higher where the catchment includes pavement or other impervious areas)
  • i = design rainfall intensity (in./hr) for a duration equal to the time of concentration, at the return period the owner railroad specifies
  • A = drainage catchment area (acres)

Subgrade drainage outlet spacing:

Space outlets to suit the track grade, the ditch or pipe capacity and the owner railroad's standards. Provide an outlet at every sag in the vertical profile.

Inputs for the equations in this section (5)
SymbolWhat it isComes fromHow to get itTypical range
Crunoff coefficient (about 0.20–0.40 for railroad yards, FHWA HDS-2; higher where the catchment includes pavement or other impervious areas)Hydraulic studyFrom the hydraulic model or study (HEC-RAS, FHWA HEC-18), stream gauge records or the drainage design.project-specific
idesign rainfall intensity (in./hrPublished hazard / climate dataNOAA Atlas 14 precipitation-frequency data for the design storm and return period.project-specific
Adrainage catchment area (acres)Hydraulic studyFrom the hydraulic model or study (HEC-RAS, FHWA HEC-18), stream gauge records or the drainage design.project-specific
inetnet lateral hydraulic gradient.Chart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
wwater contentLab testOven-dry water content of samples (ASTM D2216); field check by microwave (D4643) or nuclear gauge (D6938).gravels/sands 3–25%, clays 15–70% · by USCS group
2.3.8.2 Edge Drain Design

Perforated pipe edge drains at the base of the subballast layer are common on new mainline construction; confirm the owner railroad's standard. Design:

Anatomy of a Modern Road — Layers, Geogrid & Subdrainage
Anatomy of a Modern Road — Layers, Geogrid & Subdrainage

Pipe diameter: 4 in. minimum perforated HDPE; 6 in. for grades < 0.5%

Filter requirements: size the geotextile wrap with the FHWA geosynthetic filter criteria (Holtz et al., FHWA-NHI-07-092):

AOS (O₉₅) ≤ B × D₈₅ of the retained soil, with B = 1 as a conservative value (retention)

k_geotextile ≥ 10 × k_soil for critical applications, ≥ k_soil otherwise (permeability)

Groundwater depth, crossfall and geotextile filters

UIC guidance is that the groundwater level should be at least 2.6 ft below the top of subgrade. Where it is not, it must be lowered with ditches or deep drains. Individual railways set their own minimum depths below rail or formation (Figure 2.3-37). Even where groundwater is deep enough, hydrogeological conditions are not rated “good” unless drainage devices are provided and the top of subgrade has a 3–5% crossfall. Sites with large seasonal groundwater fluctuation need a separate study, where a sand filter or geotextile may be warranted.

Figure 2.3-37. Minimum depth of groundwater below a reference level for “good” hydrogeological conditions, by railway (DB, SBB, SJ, VR, NSB, OBB, SNCF, BR). Profillidis Fig. 9.3.
Figure 2.3-37. Minimum depth of groundwater below a reference level for “good” hydrogeological conditions, by railway (DB, SBB, SJ, VR, NSB, OBB, SNCF, BR). Profillidis Fig. 9.3.
Figure 2.3-38. Drainage devices along the railway subgrade: crossfall to side drains, base drainage. Profillidis Fig. 9.4.
Figure 2.3-38. Drainage devices along the railway subgrade: crossfall to side drains, base drainage. Profillidis Fig. 9.4.

Geotextiles (polypropylene or polyester, 0.016–0.12 in. thick, woven or non-woven) separate, reinforce, filter and drain. They go under the subballast, never directly under the ballast. They do not replace ballast or subballast for load spreading: railways that laid a geotextile and also cut ballast thickness or omitted subballast saw the ballast puncture the fabric and lost the crossfall. A finite-element study found about a 10% reduction in stress at the top of subgrade from the geotextile. Filter permeability criteria quoted by the book:

Figure 2.3-39. Finite-element mesh used to assess the reinforcing effect of a geotextile under a track bed. Profillidis Fig. 9.20.
Figure 2.3-39. Finite-element mesh used to assess the reinforcing effect of a geotextile under a track bed. Profillidis Fig. 9.20.
non-cohesive soils: kg ≥ tg·ks / (5·d50)     cohesive soils: kg > 100·ks

where kg = geotextile permeability (ft/day), tg = geotextile thickness (in.), ks = soil permeability (ft/day) and d50 = soil 50% passing size (in.).

After Profillidis (2014), §9.4, §9.14.1, §9.15, Eqs. 9.13–9.14, Figs. 9.3, 9.4, 9.20. Full reference under Supplemental References.

Internal drainage on multiple tracks, and why it blocks

On double track, each track drains laterally away from the centerline. On three or more tracks, the outside tracks drain outward and the inner tracks drain into longitudinal trench drains, with the subgrade and sub-ballast surfaces sloped to suit. Ballast-deck bridges need their own designed drainage. Lateral drainage blocks when there is no cross-slope, when ballast pockets have formed, or when material and vegetation build up between the ballast toe and the ditch. Water trapped in the ballast is the leading cause of mud-fouled ballast. Groundwater seepage, where the subgrade sits at or below a fluctuating water table, is the second.

Cross-section diagram of a prefabricated geocomposite edge drain in a trench, showing a 25 to 50 millimeter drainage core width and a 0.3 to 0.45 meter trench d
Photo 2.3.8-1. Prefabricated geocomposite edge drain (PGED). Koerner et al. (1996).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Black-and-white photograph of a truck spraying prime coat onto a roadway surface, with hills and trees in the background
Photo 2.3.8-2. Prime coat application on top of geocomposite membrane. From Elseifi, M., Al-Qadi, I., Loulizi, A., and Wilkes, J. (2001), Transportation Research Record 1772, Figure 2, p. 169. Copyright, National Academy of Sciences, Washington, D.C., 2001. Reproduced with permission of the Transportation Research Board.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
An edge drain trench lined with geotextile and filled with aggregate along a roadway under construction, with a bulldozer and bridge visible in the distance
Photo 2.3.8-3. Geotextile in pavement drainage. From National Highway Institute Lecture notes.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Figure 2.3-70. Double track: each track drains away from the centerline.
Figure 2.3-70. Double track: each track drains away from the centerline.
Figure 2.3-71. Three or more tracks: inner tracks drain to longitudinal trench drains.
Figure 2.3-71. Three or more tracks: inner tracks drain to longitudinal trench drains.
Figure 2.3-72. Blocked lateral drainage: no cross-slope, ballast pockets, or buildup at the toe.
Figure 2.3-72. Blocked lateral drainage: no cross-slope, ballast pockets, or buildup at the toe.
Figure 2.3-73. Water trapped in the ballast layer.
Figure 2.3-73. Water trapped in the ballast layer.
  • Move water away from below the ties as quickly as possible.
  • Keep ballast and shoulders clean and permeable.
  • Keep the subgrade dry; drain ballast water pockets.
  • Do not let water pond in ditches, especially in side-hill cuts.

After Geotechnology for Railroaders Program, Module 4; §03, §05–06. Full reference under Supplemental References.

Can the ballast section drain the design storm?

Three requirements. Track drainage works only if all three are met:

  • The ballast is clean enough to pass water as fast as it enters.
  • The subballast and subgrade surfaces slope to the sides.
  • An outlet carries the water away. A section with no outlet is a bathtub.

Size the system for the highest inflow expected over its design life, not the average.

The center of the track ponds first. On a low-permeability subgrade, water flows mostly sideways. About two-thirds of it leaves through the shoulders. The zone within about 12 in. of the track centerline has the longest flow path and saturates first, so it sets the critical rainfall rate.

Table 2-SW5 gives the critical rainfall rate for several ballast conditions. The cases assume 12 in. of ballast below the tie and 6 in. of silty-sand subballast on an impermeable subgrade.

Table 2-SW5. Rainfall rate that saturates the center of the track section (Parsons cases)
Ballast conditionCritical rate, in./hr
Clean5.9
Clean shoulders; fouled (FI 30) below1.4
Undercut, over FI 30 ballast0.33
Undercut, over FI 40 ballast0.31
Fouled throughout (FI 30)0.06
Clean shoulders; highly fouled (FI 40) below0.02
Highly fouled throughout (FI 40)0.001

Double track that drains to one side only has about half these critical rates.

How to use it.

  • Compare the critical rate with the design rainfall intensity over the planned cleaning cycle to set an allowable fouling index.
  • For moderately fouled track, shoulder cleaning beats undercutting.
  • For highly fouled track, undercutting is better, because water under the center would otherwise have to pass through fouled ballast to reach the cleaned shoulders.
  • Full cleaning is best.

After Selig & Waters (1994), ch. 13. Full reference under Supplemental References.

Case study: 2.3.18.2 Rail formation on broken hard rock: ruts after a week, tests all passed (Look 2023), in Section 2.3.18 Case Studies.