Formerly Geo Rail Chapter 6.3 — Railroad Track Subgrade: Special Topics
Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S13 under Supplemental References.
Related section: 2.3.4 Subballast Requirements and Blanket Layer Design
In a 2008 rail project, residual soils in Cut No. 5 (about 40,500 yd³) had their highest CBR in the middle of the cutting, not at depth. Strength does not necessarily increase with depth. Using the CBR 10 material at subgrade level would have reduced layer thickness and the imported capping layer, here the subballast, so it was stockpiled for reuse.
Checks on the stockpile found inconsistent CBR, and inspection showed it had been mixed with poorer material, visible as a change in color. Look’s shorthand for the result: CBR 10 + CBR ≤ 5 ≠ CBR 7; the mix behaves more like CBR 5.
For railroad work: selective excavation and zoning can cut subballast quantities, but only with stockpile control: separate, marked piles, a haul plan, and verification testing of the stockpile before it is placed. Without that, design the subballast for the poorer material.


Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §14.15, pp. 552–554. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Related section: 2.3.8 Subgrade Drainage Design
On a 3.7 mi rail alignment around 2008, a short cutting (under 490 ft) hit very high-strength volcanic rock near the surface. With small volumes and no other large cuts, the contractor used a rock breaker, and the work took more than six months. The broken rock surface was uneven and out of tolerance for the required vertical grade. High-quality fill was compacted into the voids to even it out before the capping layer was placed.
Rain followed soon after. No ponding showed at the surface, but water collected in the hollows of the impermeable rock below and could not drain. About a week after completion, construction traffic rutted the formation, although the density and plate load tests had passed. With water trapped in these “bowls”, Skempton’s B is about 1, so each truck pass generated high excess pore pressure. Look’s lessons:
For railroad work: the same trapped-water mechanism produces mud pumping and track geometry defects where subballast sits on an irregular rock or old hard-pan surface. Shape the rock formation to drain, or level it with lean concrete, before placing subballast.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §14.13, pp. 548–550. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.