7.3.6 Subgrade Preparation and Compaction Criteria

Pavement subgrade evaluation for railroad facilities encompasses two distinct but related infrastructure domains: (1) paved surfaces within railroad right-of-way —…
Authors: Daniel P. Colwell and Mario Ruel
7.3.6 Subgrade Preparation and Compaction Criteria
7.3.6.1 Compaction Standards

Subgrade preparation specifications reference ASTM D698 (Standard Proctor) or ASTM D1557 (Modified Proctor):

RC = γd,fieldγd,max × 100%
Table 7.3-6: Subgrade Compaction Criteria
RailroadTest MethodMin RC (Top 12 in.)Min RC (Below 12 in.)Moisture RangeNotes
TypicalASTM D69895%90%±3%Common practice; confirm with owner
Proctor Compaction Test
Proctor Compaction Test
Why Moisture Content Matters Before Compaction
Why Moisture Content Matters Before Compaction
7.3.6.2 Subgrade Stabilization

When in-situ subgrade does not meet minimum CBR or M_r criteria, stabilization options include:

  • Lime stabilization: Add 3–8% hydrated lime (ASTM C977) to reduce PI and increase M_r. PI reduction target: PI_final < 12 for CL, CH soils. M_r improvement: typically 1.5–3× improvement over unstabilized value.
  • Cement stabilization: Add 4–8% Portland cement (ASTM C150) to achieve unconfined compressive strength q_u ≥ 300 psi at 7 days (ASTM D1633, withdrawn 2026). This yields a_i = 0.23 per Table 7.3-4.
  • Geosynthetic reinforcement: Biaxial geogrids (ASTM D6637; aperture size 1.0–1.5 in.) placed at subgrade/subbase interface to improve bearing and reduce differential settlement. Aperture Stability Modulus (ASM) ≥ 0.24 ft·lb/deg preferred for heavy container crane loads.
  • Full subgrade replacement: Remove and replace F3/F4 materials to frost depth or 5 ft below finished grade, whichever governs.
Yellow hydraulic excavator scooping soil from a deep excavation pit, revealing distinct soil layers, with a shopping center visible in the background
Photo 7.3.6-1. Excavation of unsuitable soil using hydraulic excavator in Columbus, Mississippi. Photograph courtesy of David M. Coleman.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Four cross-section diagrams labeled Case 1 through Case 4, showing complete, partial-depth, center-portion, and toe-portion excavation and replacement of soft m
Photo 7.3.6-2. Typical use of excavation and replacement methods for improving site conditions. Rollings and Rollings (1996).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Hydraulic excavator working atop an excavation pit backfilled with granular material and geogrid reinforcement
Photo 7.3.6-3. After excavation, geogrid and granular replacement fill, Columbus, Mississippi. From the files of David M. Coleman.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Muddy roadway cut through a forested hillside showing an area requiring excavation and replacement, with construction equipment in the distance
Photo 7.3.6-4. Area requiring excavation and replacement, Sandlake-Galloway Road Project. From Tillamook County, Oregon.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Black geosynthetic fabric being unrolled into an excavated roadway trench alongside standing water, with a worker and construction equipment present
Photo 7.3.6-5. Excavation and geosynthetic placement prior to replacement, Sandlake-Galloway Road Project. From Tillamook County, Oregon.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Self-propelled yellow pan scraper hauling excavated soil on a highway construction site
Photo 7.3.6-6. Self-propelled pan scraper on Stage C of Highway 14, Waseca, MN. From EquipmentImages.net.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Tractor towing two tandem pan scrapers loaded with soil on a highway construction site
Photo 7.3.6-7. Towed scrapers on Stage C of Highway 14, Waseca, MN. From EquipmentImages.net.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A steel-wheel roller compacting granular fill over a geosynthetic laid across a gravel road under construction, with a bulldozer and parked vehicles in the back
Photo 7.3.6-8. Placement of geosynthetic in roadway. Courtesy of National Highway Institute.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
An excavator and dump truck placing granular fill over a geosynthetic laid across a sandy road alignment under construction
Photo 7.3.6-9. Placement of geosynthetic in roadway. Courtesy of Kansas Department of Transportation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Workers unrolling a geosynthetic across a sandy road base, with an excavator, dump trucks, and a pickup truck staged along the alignment
Photo 7.3.6-10. Placement of geosynthetic in roadway. From Kansas Department of Transportation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A wider view of workers placing a geosynthetic across a sandy road base ahead of fill placement by excavator and dump trucks
Photo 7.3.6-11. Placement of geosynthetic in roadway. From Kansas Department of Transportation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Cement Treated Base (CTB)
Cement Treated Base (CTB)
Steps of Soil Lime Treatment
Steps of Soil Lime Treatment
Supplemental reference

Geotextile separation and geocell confinement (FHWA SHRP2 R02)

Table 19-S1. Separation vs. confinement for yard and access-road subgrades

Geotextile separatorGeocell confinement
FunctionKeeps base aggregate out of soft subgrade and subgrade fines out of the base; secondary filtration, drainage, reinforcement3-D honeycomb (HDPE or novel polymeric alloy) confines infill, raising stiffness and strength; reduces rutting and required base thickness
Where it fitsSubgrade soaked CBR 3–8 (Class 2 moderate-strength geotextile); seasonally weak, high-fines or pumping-susceptible soils. Little need where the soil stays dry.Soft to firm subgrade; most cost-effective with sand or rounded gravel infill (e.g., local material that would not otherwise qualify as base)
Design basisEmpirical (FHWA NHI-07-092 / AASHTO M 288 survivability, retention, permeability); separation does not reduce the base thickness needed for trafficNo FHWA method; research methods (e.g., KENLAYER damage analysis, modified Giroud–Han), modulus improvement factor capped at 7.6 for NPA cells
Construction notesEnd-dump base from the edge of the fabric; compact with a smooth-drum roller rather than vibratory compaction; maintain overlaps; hard to place in windStretch and pin cells, usually over a nonwoven separator; fill and compact (compaction inside cells is a known difficulty)
LimitationsNot in AASHTO M-E; life-cycle benefit not yet demonstrated; not economical where good base is cheapLimited design, QC/QA methods and long-term data; product cost
Types of Rollers
Types of Rollers
Soil Compaction and Maximum Dry Density
Soil Compaction and Maximum Dry Density
Smooth-Drum Vibratory Roller
Smooth-Drum Vibratory Roller
Padfoot (Sheepsfoot) Roller
Padfoot (Sheepsfoot) Roller

For railroad use, the same separation criteria apply beneath subballast on fine-grained subgrade, and geocells are an option for access roads and laydown areas that must carry heavy equipment over weak ground (Figures 19-S1 and 19-S2).

Placement of base course over a geotextile separator (photo: Minnesota DOT, via SHRP2 GeoTechTools).
Supplemental Figure 19-S1. Placement of base course over a geotextile separator (photo: Minnesota DOT, via SHRP2 GeoTechTools). Source: SHRP2 R02 / GeoTechTools (2012). Geosynthetic Separation in Pavement Systems — fact sheet, design guidance and photographs.

Source: SHRP2 R02 / GeoTechTools (2012). Geosynthetic Separation in Pavement Systems — fact sheet, design guidance and photographs · SHRP2 R02 / GeoTechTools (2012). Geocell Confinement in Pavement Systems — fact sheet, design guidance and photographs

Geocell-reinforced road construction (photo: J. Han, University of Kansas, via SHRP2 GeoTechTools).
Supplemental Figure 19-S2. Geocell-reinforced road construction (photo: J. Han, University of Kansas, via SHRP2 GeoTechTools). Source: SHRP2 R02 / GeoTechTools (2012). Geocell Confinement in Pavement Systems — fact sheet, design guidance and photographs.

Case study: 7.3.15.2 Desiccation cracks cut subgrade modulus by about a third (Look 2023), in §19.15 Case Studies.

Close-up of a geocell honeycomb structure with cells filled with soil, some cells filled and some awaiting infill
Photo 7.3.6-12. Geocell infilled with soil. From the files of Jie Han, University of Kansas. A closely related crop of this same photograph appears as the Fact Sheet document's own cover image.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A wheel loader dumping fill material onto an installed geocell field at a construction site, with a worker in a high-visibility vest observing
Photo 7.3.6-13. Geocell-reinforced road construction. From the files of Jie Han, University of Kansas. A closely related crop of this same photograph appears as the Fact Sheet document's own cover image.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A gravel logging road with a geosynthetic fabric berm along one edge, cleared timber and brush beyond it
Photo 7.3.6-14. Geosynthetic-reinforced temporary, unpaved road. From a National Highway Institute lecture. The Fact Sheet document's own cover image reuses this same photograph at higher resolution, reproduced here.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Construction equipment placing granular fill onto a geotextile fabric laid across a graded roadbed
Photo 7.3.6-15. Placement of geotextile during roadway construction. From the Kansas Department of Transportation. The Fact Sheet document's own cover image reuses this same photograph at higher resolution, reproduced here.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A straightedge laid across a paved road surface at a measurement point marked with red paint, used to gauge pavement rutting on a test section
Photo 7.3.6-16. Straightedge rut-depth measurement on a test section. From the project case history document; caption not provided in the source.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Cross-section diagram of base aggregate resting on a geotextile over subgrade, labeling caking of aggregate above the geotextile, blinding of the geotextile's t
Photo 7.3.6-17. Definition of blinding, clogging, and caking. Black and Holtz (1999); with permission from ASCE.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A motor grader spreading gravel base course over a geotextile laid across a road under construction, with a flagger and traffic signs along the alignment
Photo 7.3.6-18. Placement of base course materials over the geotextile in roadway. From Minnesota Department of Transportation.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A roll of geotextile unrolled over a gravel road bed, with white PVC pipe cores from spent rolls lying alongside the seam
Photo 7.3.6-19. Placement of geotextile in roadway. From National Highway Institute Lecture notes.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Yellow grader working a wide rock cap aggregate roadway with a line of trucks behind it
Photo 7.3.6-20. Grading of rock cap aggregate. From Uhlmeyer et al. (2003), Transportation Research Record 1821, Figure 5(c), p. 45. Copyright, National Academy of Sciences. Reproduced with permission of the Transportation Research Board.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Cross-section diagram of a rock cap pavement system, labeled Asphalt Surface, Crushed Stone Base, Rock Cap Aggregate, and Prior Pavement or Subgrade
Photo 7.3.6-21. Rock cap overlaid with crushed stone subbase (cross-section). From Uhlmeyer et al. (2003), Transportation Research Record 1821, Figure 2(a), p. 41. Copyright, National Academy of Sciences. Reproduced with permission of the Transportation Research Board.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Green belly dump truck unloading rock cap aggregate onto a roadway under construction
Photo 7.3.6-22. Placement of rock cap with belly dump trucks. From Uhlmeyer et al. (2003), Transportation Research Record 1821, Figure 5(b), p. 45. Copyright, National Academy of Sciences. Reproduced with permission of the Transportation Research Board.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A bulldozer pushing gravel base material across a black geotextile fabric laid over subgrade
Photo 7.3.6-23. Placement of base material on top of the geotextile. Photograph from www.tencate.com, courtesy of TenCate Geosynthetics North America.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
A tractor pulling a compaction roller unit over a gravel roadway on top of a geogrid
Photo 7.3.6-24. Compaction of base material on top of the geogrid. Photograph courtesy of North Dakota DOT. This same photograph is also used as the Fact Sheet document's cover image.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
← Previous · 7.0 Design Chapter 7.2 — Ground Improvement Methods
Next · 7.0 Design → Chapter 7.4 — Earthworks Asset Management and Remedial Design