A railroad's earthworks (its cuts, embankments, sidehill fills and the drainage that serves them) are among its largest and oldest assets, and they are usually the least recorded. Asset management treats them like bridges or rail: an inventory, a condition rating, an understanding of how they deteriorate, and a ranked program of interventions chosen to reduce risk most for the money available. This chapter sets out that framework and links it to the GHRM risk ratings and remedial design.
Without asset management, earthworks are maintained reactively: a slide or sinkhole occurs, it is repaired, and the next one is waited for. Asset management moves the effort earlier, finding and treating the earthworks most likely to fail with severe consequences before they fail. The GHRM risk ratings (Chapter 3.8) provide the scoring; this chapter provides the program around them.
The inventory divides the corridor into discrete earthwork assets and records the basic facts about each.
| Item | Content |
|---|---|
| Identification | Asset ID, line segment, mileposts, track(s), side |
| Type | Cut, embankment, sidehill (cut and fill), at-grade, retained |
| Geometry | Height or depth, slope angles, length, benches |
| Materials | Soil and rock types, fill type (Chapter 2.10), problem soils present |
| Drainage | Ditches, culverts, subdrains, outfalls and their condition |
| Hazards | Mapped hazards from the desktop study: landslide, rockfall, karst, mining, flooding, scour |
| History | Past failures, repairs, speed restrictions, maintenance frequency |
| Consequence factors | Traffic, speed, hazardous materials, passenger service, detour length, adjacent property |
LiDAR, aerial imagery and the KMZ workflow allow most of the inventory to be built at the desk, with field verification concentrated on the higher-hazard assets (Chapter 3.2).
Each asset is examined on a cycle set by its rating, with more frequent examinations for higher ratings and after triggering events (heavy rain, floods, earthquakes, freeze-thaw). The examination records observed defects using consistent terms so that changes can be tracked.
| Defect | Indicators |
|---|---|
| Instability | Tension cracks, scarps, bulging toe, leaning trees and poles, track alignment or surface defects |
| Erosion and scour | Gullies, undercut toe, exposed culvert ends, scour at bridge approaches |
| Drainage failure | Blocked ditches and culverts, ponding, seepage on slopes, soft wet track |
| Rockfall | Fresh rock in ditch, overhangs, open joints, damaged fences or detectors |
| Settlement and subsidence | Sags, depressions, sinkholes, repeated surfacing |
| Burrowing and vegetation | Animal burrows in embankments, large trees on steep slopes, root jacking of rock |
Defect ratings from the examination combine with the geospatial hazard ratings to give the current risk, as set out in Chapter 3.8.
Unpaved access roads, maintenance roads and the ditches along them deliver sediment to streams and wetlands and, when they erode, undermine the toe of embankments and cut slopes. County stormwater programs inspect unpaved roads once a year with a simple yes/no checklist, where “yes” means action is needed and a work order follows. The items translate directly to railroad access roads and right-of-way ditches:
Typical BMPs are check dams, filter fabric in ditches, filling potholes, grassing, road scraping and grading, ditch cleaning, and turnouts that divert water off the road before it gathers speed. Each finding should record the action, the work order and the follow-up.
For railroad work: Add access roads, maintenance roads and right-of-way ditches to the earthworks inventory (Section 7.4.1) and examine them on the same annual cycle, using a checklist like this. Ditches that erode toward a fill toe or a cut slope, or that silt up and pond water against the track, are geotechnical problems as well as stormwater problems; rate them with the drainage elements of the risk rating. Keep the inspection records, since stormwater permits for the right-of-way may require them.
Source: Richland County, SC, Roadway Runoff Management Program: Unpaved Roads Annual Inspection Form Guidance. Summarized and paraphrased.
Earthworks deteriorate in characteristic ways: cut slopes in weak rock and clay soften and flatten over decades; embankments of clay fill lose strength as seasonal wetting and drying opens fissures; ditches fill and culverts corrode; vegetation changes. Many failures, however, are not gradual but triggered: by intense or prolonged rainfall, by rising rivers, by changes made at the toe (ditch cleaning, excavation) or at the crest (loading, drainage changes). An asset program therefore needs two parts: a cyclic program addressing deterioration, and an event-driven program (inspection after storms, live risk rating) addressing triggers (Chapter 3.8).
With limited funds, interventions should be ranked by how much risk they remove per dollar, not simply by which assets score highest. A high-risk site that is very expensive to fix may rank below two moderate-risk sites that are cheap to fix.
Efficiency ranking should be combined with judgment: any site with a severity of 5 and an increasing frequency needs action regardless of efficiency, and low-cost actions such as clearing drainage are usually worth doing everywhere.
| Category | Measures | Notes |
|---|---|---|
| Drainage | Ditch cleaning and lining, culvert repair and upsizing, horizontal drains, trench drains, surface water diversion | Usually the most cost-effective; clean ditches without undercutting the toe |
| Geometry | Slope flattening, unloading the crest, toe berms and buttresses | Needs right-of-way; berms must sit on competent ground |
| Structural | Soldier pile and lagging walls, drilled shaft walls, sheet piles, anchored walls | Railroads favor driven or drilled soldier pile walls for stabilization (Chapter 7.1) |
| Reinforcement | Soil nails, rock bolts, reinforced slopes | Check corrosion where ground chemistry is aggressive (Chapter 2.12) |
| Ground improvement | Grouting, deep mixing, lime injection, aggregate columns | See Chapter 7.2 |
| Rock slope | Scaling, trim blasting, mesh and drapes, rockfall barriers, catch ditches, slide fences | Detectors provide warning, not prevention |
| Erosion and scour | Riprap, gabions, articulated mats, vegetation, channel training | Size for design flood; protect toe below scour depth |
| Operational | Monitoring, speed restrictions, slide detection, inspection after storms | The observational approach (Chapter 5.5) |




















Remedial design should address the cause identified in the investigation, not only the symptom; a wall built across a slide that is driven by a blocked culvert will be loaded by the same water that caused the slide. Retaining structures and ground improvement are covered in Chapter 7.1 and Chapter 7.2, and slope stability analysis in Chapter 6.3.
A district has budget for about $2 million of earthwork repairs this year. Three candidate sites have been rated on the GHRM 5 × 5 matrix, with the expected rating after the proposed repair and its estimated cost.
| Variable | Value | Description |
|---|---|---|
| Site A | F = 4, S = 4; after: F = 2, S = 4; C = $1.2M | Embankment slide; soldier pile wall |
| Site B | F = 3, S = 5; after: F = 1, S = 5; C = $2.5M | Rock cut over a bridge approach; full slope stabilization |
| Site C | F = 5, S = 3; after: F = 2, S = 3; C = $0.6M | Culvert-driven settlement; culvert replacement and drainage |
| Budget | About $2.0M | Available this year |
Rank by efficiency: Site C (15 per $1M), Site A (6.7), Site B (4.0). Fund C and A this year ($1.8M, 17 points of risk reduction) and program B for next year.
Ranking by the before score alone would put A first (16) and treat B and C as equal (15). Ranking by efficiency shows that the culvert repair at C removes almost as much risk as the expensive rock stabilization at B for a quarter of the cost.
Judgment still applies: Site B has a severity of 5 (a rock cut over a bridge approach). If its frequency rating is rising, or if it is on a passenger route, it may justify interim measures this year, such as scaling, a slide fence or monitoring under a TARP (Chapter 5.5), while the full stabilization is designed and funded. The remaining $0.2M could fund those interim measures.
A cut slope beside the main track of a Class I railroad located in Pennsylvania keeps raveling onto the ditch and needs a nailed facing over a 300-ft length (about 9,000 ft² of face). Two facings meet the stability and design-life requirements: reinforced shotcrete, or galvanized high-tensile steel wire mesh with an erosion mat. The owner reports emissions and wants the carbon footprint of each option alongside the cost estimate (Section 7.4.10).
| Variable | Value | Description |
|---|---|---|
| Option A materials | Shotcrete 545,000 lb (including 25% rebound); nail grout cement 113,000 lb; steel nails and reinforcement 32,700 lb | Shotcrete facing |
| Option B materials | Mesh steel 5,400 lb; zinc 160 lb; nail steel 19,200 lb; nail grout cement 113,000 lb; polypropylene mat 450 lb | Wire mesh facing |
| Factors (Table 7.4-10) | Concrete 0.135; cement 0.83; reinforcing steel 1.25; primary steel 1.7; zinc 2.46; polypropylene 2.0 lb CO2e/lb | GWP per lb of material |
| Transport | 40 miles by truck at 0.72 lb CO2e per ton-mile | All materials |
(a) About 218,000 lb CO2e. (b) About 130,000 lb CO2e. (c) The nail grout cement dominates both options, so B saves about 40%, less than the four to five times reported in Section 7.4.10.
The saving here is smaller than in the published comparison because the same nails are used in both options and their grout dominates. The next places to cut carbon are the nails themselves: fewer or shorter nails where the design allows, or a grout with supplementary cementitious material. Check the factors against current supplier declarations before reporting the numbers, and note that delivery by work train instead of truck would cut the small transport share further.
A 20-ft high-plasticity clay fill below the main track of a Class I railroad located in Texas has a shallow slide 100 ft long that has pushed the toe into the ditch after every wet season. Inclinometers show the slip surface is 4 to 6 ft deep. The railroad wants a repair that can be installed from the slope face in short work windows, and recycled plastic pins are proposed (Section 7.4.9). The engineer must choose the pin spacing that raises the factor of safety to 1.40 and estimate the number of pins and working days.
| Variable | Value | Description |
|---|---|---|
| MD, MR | 300,000 and 315,000 lb-ft per ft of slope length | Driving and resisting moments from back-analysis (FS = 1.05) |
| FStarget | 1.40 | Required factor of safety after repair |
| P | 1,200 lb per pin | Design lateral resistance per pin at the slip surface, reduced for creep (from limit-resistance curves or load tests) |
| R | 40 ft | Slip circle radius; pin force taken as acting at R |
| Rows | 6 rows of 10-ft pins, 4 ft apart down the slope | Rows that cross the slip surface |
| L; rate | 100 ft; 100 to 120 pins per day | Repair length and installation rate |
(a) 105,000 lb-ft per ft of slope. (b) 2.19 pins per ft, so pins at 2.5 ft along the slope in rows 4 ft apart (FS ≈ 1.43). (c) 240 pins, about 2 to 3 working days.
This is a simplified moment check that treats every pin as mobilizing its full design resistance at the slip surface; pins near the crest and toe, where the slip surface is shallow, may mobilize less, so check the layout with a slope stability program that models pins as reinforcement. Close the spacing near the crest where movement threatens the shoulder, extend the rows 10 ft beyond each end of the slide, restore drainage at the toe, and set survey points to compare pinned and unpinned lengths (Section 7.4.9).
Related chapters in this manual:
Related ICE Manual chapters are listed in the Further Reading box at the top of this chapter and in Appendix G.
The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.
The earthworks inventory (Section 7.4.1) includes concrete and masonry structures that hold the earthworks together: culverts and their headwalls, retaining walls, wing walls, abutments and the footings of piers and signal structures. Their failure is a ground hazard even when the cause is the concrete, because a collapsed culvert or a failed wall takes the embankment with it. This section covers how concrete in these structures deteriorates, how to assess it, and the repair choices, drawing on the proceedings of the 2nd International Conference on Concrete Repair, Rehabilitation and Retrofitting (Cape Town, 2008).
The economics are summarized by de Sitter’s “rule of fives”, quoted by Walraven (2009): if maintenance is skipped, the later repair costs about five times the maintenance saved; if repair is skipped, renewal costs about five times the repair saved. Early condition assessment and timely repair are therefore part of the risk reduction in Chapter 3.8, not an optional extra.
Critical chloride content. Angst and Vennesland (2009) reviewed about 40 studies of the chloride content at which steel starts to corrode. Reported values ranged from 0.02% to 3.08% chloride by weight of cement, so no single threshold exists; the steel–concrete interface, the pH of the pore water and the electrochemical potential of the steel all control it. In practice, owners set decision levels: on one set of marine bridges, members with more than 1% chloride by weight of cement at the steel were judged too contaminated for coatings and inhibitors and were either treated electrochemically or rebuilt (Streicher et al. 2009).
| Option | What it does | Notes for use |
|---|---|---|
| Water repellent (silane) impregnation | Keeps water and chlorides out of sound concrete | Works only if it penetrates deeply enough. Johansson et al. (2009) found that extending contact time from 1 to 5 hours (for example by using a paste or gel rather than a liquid) about doubles the depth, as do drier concrete and higher porosity. Check depth by splitting a treated core and wetting it. |
| Corrosion inhibitors | Slow corrosion of steel in contaminated concrete | Less effective at high chloride levels. |
| Patch repair | Replaces damaged concrete around the steel | Bond depends more on an undamaged substrate than on roughness. Bissonnette et al. (2009) found that jackhammering leaves a damaged surface that outweighs its extra roughness; hydrodemolition, scarifying and blasting gave better bond. Verify with pull-off tests. |
| Galvanic (sacrificial) anodes | Zinc anodes connected to the steel corrode instead of it | No power supply; typical design life about 25 years. Anode mortar dosages of roughly 0.1 lb per ft² of steel surface have been used (Bänziger et al. 2009). Can be checked during routine inspections by measuring anode current. |
| Impressed-current cathodic protection | A power supply drives protective current to the steel | Long-lived; needs monitoring and maintenance of the power supply. |
| Electrochemical chloride extraction | A temporary external anode draws chlorides out of the cover and raises the pH at the steel | Treatment over weeks; seal the surface afterward to stop new chlorides. Treated bridge members showed no new spalling or rust staining after four years (Streicher et al. 2009). |
| Realkalisation and hybrid treatments | Restore high pH at the steel | A brief impressed-current “pit realkalisation” of 1 to 2 weeks, followed by galvanic protection from the same installed anodes, arrests and then prevents corrosion (Glass et al. 2009). |
| Externally bonded FRP | Restores or adds flexural and shear strength | For walls, caps and beams; needs sound substrate and anchorage at the ends. |
| Demolish and rebuild | Removes the problem | Compare with repair options by life-cycle cost (Chapter 3.8, Section 3.8.40). |
Andrade et al. (2009) note that the efficiency of electrochemical treatments has traditionally been checked by switching off the protection current or by coring after treatment, and propose nondestructive checks (impedance, corrosion rate and potential, and the charge passed adjusted for concrete resistance). Ask for a measurable acceptance criterion in any electrochemical treatment contract.
Da Silva and Goyns (2009) assessed two deep concrete sewers under a busy street that had deteriorated in different ways: one, made with dolomitic aggregate and a sacrificial layer, had lost material evenly; the other, cast in place with siliceous aggregate, had lost cement paste and exposed its aggregate. Because open-cut replacement was ruled out, both were rehabilitated by trenchless lining with a close-fitting continuous liner, and the annular space between liner and host pipe was grouted to prevent water paths. The same reasoning applies to deep culverts under track: open-cut replacement needs a track outage and a temporary shoofly or bridge, so lining, with the annulus grouted and any voids around the pipe filled, is often the preferred choice where the remaining pipe and surrounding soil can carry the load. Check the lined culvert’s hydraulic capacity with the reduced diameter (Chapter 3.5, Section 3.5.10).
After a rainfall-triggered failure of a road cut on a mountain pass, Kruger et al. (2009) compared three repairs: an anchored pile wall with a cantilevered deck, a mechanically stabilized earth wall, and a half-width viaduct on piers. Steeply dipping, weathered and jointed rock made isolated pier footings vulnerable to block and wedge failure, and the MSE wall could have been undercut by future slides, so the anchored pile solution was chosen: eight 4-ft-diameter bored piles at about 26-ft centers, about 46 ft long and socketed about 13 ft into competent rock, carrying a 200-ft-long cantilevered deck balanced by a buried slab, with re-stressable rock anchors and the slab bolted down to rock. A temporary soil-nail wall kept traffic moving during construction.
For railroad work: the same logic applies to a sidehill grade that has lost its outer shoulder: where the rock structure dips out of the slope, prefer continuous anchored piles socketed into rock over isolated footings or a reinforced fill that could be undercut (Chapter 7.1, Section 7.1.4; Chapter 6.3). Use re-stressable anchors so that load can be checked and restored during the structure’s life.
Papers in Alexander, M. G., Beushausen, H.-D., Dehn, F. and Moyo, P. (eds.) (2009). Concrete Repair, Rehabilitation and Retrofitting II. Proceedings of the 2nd International Conference on Concrete Repair, Rehabilitation and Retrofitting (ICCRRR), Cape Town, 2008. London: CRC Press/Balkema. Summaries are paraphrased and values converted to English units.
Shallow, surface-parallel slides 3 to 6 ft deep are the most common earthwork failure on side slopes built of or cut into high-plasticity clay. They follow prolonged rain: the near-surface soil wets, seasonal shrink–swell cycles open cracks and loosen it, and its strength falls toward the fully softened value. Each slide is small, but the slides recur, and they undermine shoulders, fill ditches and threaten the ballast section at the crest. Driven recycled plastic pins (RPPs) are a low-cost repair that reinforces the slope across the slip surface without excavation (Khan et al. 2018).
RPPs are square plastic members, typically 4 in. × 4 in. and 8 to 10 ft long, made mostly of recycled high-density polyethylene with other plastics and minor fillers; fiber-reinforced versions are stiffer. They are driven perpendicular to the slope face on a grid. Each pin crossing the slip surface adds bending and shear resistance, so the factor of safety becomes FS = (MR + ΔMR) / MD (Eq. 7.4-3), where MR and MD are the resisting and driving moments about the slip circle and ΔMR is the added resistance from the pins. Plastic does not rot or corrode, but it creeps under sustained load, so the design resistance per pin should allow for creep over the design life.
| Item | Value |
|---|---|
| Soil | CH clay fill from a weathered shale formation; LL 48–79, PI 25–51; back-analyzed FS = 1.05 with fully softened strength |
| Pins | 4 in. × 4 in., 8 and 10 ft long, at 3, 4, 5 and 6 ft centers (4 ft in most sections) |
| Computed FS after pinning | 1.43 to 1.54 (finite element analysis) |
| Installation | Crawler rig with a mast-mounted vibratory percussion hammer working on the slope; about 4 minutes per 10-ft pin; 100 to 120 pins per day |
| Crest settlement after 5 years | Pinned sections 2.75 to 6.25 in. (least where pins were 3 ft apart); unpinned control sections 9.5 to 15 in. |
| Movement after pinning | Less than 1.5 in. of additional settlement in the pinned sections; inclinometers showed movement largest at the surface and decreasing with depth |
| Untreated slopes nearby | Six shallow failures on the opposite, unpinned slope during the monitoring period |
| Effect of spacing (analysis) | Crest displacement rose from about 1 in. at 2-ft spacing to 4.7 in. at 8-ft spacing |
For railroad work: Pins suit sloughing cut and fill side slopes in high-plasticity clay where the failures keep reaching the ditch line or the ballast shoulder. The rig works on the slope face, so most of the work can stay outside the track foul zone, but check rig access, the stability of the slope under the rig, and buried signal and communication cables near the crest before driving. Monitor pinned and unpinned lengths with survey points at the crest and an inclinometer, and compare them, as the case history did, before using pins across a whole subdivision. This guidance on use is engineering judgment drawn from the case history, not a design method.
A worked pin layout is Example 7.4-3 (Section 7.4.6).
Values are as reported in English units.
Owners increasingly ask for the carbon footprint of a repair alongside its cost. A simple footprint can be estimated from the materials and transport each option needs: list the mass of each material, multiply by an emission factor, and add the transport. Emission factors are expressed as global warming potential (GWP): the mass of CO2-equivalent per unit mass of material, which counts all greenhouse gases, weighted by their effect, and not only CO2 from burning fuel (Gross et al. 2018).
Footprint (lb CO2e) = Σ (mass of material × GWP factor) + Σ (ton-miles hauled × transport factor) (Eq. 7.4-4)
| Material or process | GWP (lb CO2e per lb) |
|---|---|
| Reinforcing steel (mixed converter and electric-arc steel) | 1.25 |
| Primary (converter) steel | 1.7 |
| Portland cement | 0.83 |
| Concrete or shotcrete (about 630 lb cement per yd³) | 0.135 |
| Zinc for galvanizing | 2.46 |
| Aluminum | 11.7 |
| PVC pipe | 2.16 |
| Polypropylene erosion mat | 2.0 |
| Truck transport | 0.72 lb CO2e per ton-mile |
For a 330-ft length of nailed slope, a facing of high-tensile steel wire mesh with nails used about 37 tons of materials, most of it the cement grout for the nails. An equivalent reinforced shotcrete facing with nails used about 680 tons, mostly shotcrete (including about 25% rebound loss). The GWP of the mesh option was four to five times lower, because concrete has a high footprint per job and because the lighter option needed less hauling. The open mesh also lets the slope be vegetated and does not trap water behind the facing.
For railroad work: Add a footprint line to the option comparison in Section 7.4.5 when the owner reports emissions. Materials delivered by work train rather than truck have a lower transport footprint per ton-mile, so record how material will reach the site. Do not let the footprint override safety, track outage limits or design life; use it to choose between options that meet those.
A worked comparison of two facings is Example 7.4-2 (Section 7.4.6).
Metric values converted to English units; the product names in the paper are omitted.