Chapter 7.4 — Earthworks Asset Management and Remedial Design

Treating the cuts and embankments of a railroad as an asset portfolio: inventory, condition, deterioration, prioritization and the choice of remedial works.
Author: Daniel P. Colwell

A railroad's earthworks (its cuts, embankments, sidehill fills and the drainage that serves them) are among its largest and oldest assets, and they are usually the least recorded. Asset management treats them like bridges or rail: an inventory, a condition rating, an understanding of how they deteriorate, and a ranked program of interventions chosen to reduce risk most for the money available. This chapter sets out that framework and links it to the GHRM risk ratings and remedial design.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
7.4.0 Purpose and Overview

Without asset management, earthworks are maintained reactively: a slide or sinkhole occurs, it is repaired, and the next one is waited for. Asset management moves the effort earlier, finding and treating the earthworks most likely to fail with severe consequences before they fail. The GHRM risk ratings (Chapter 3.8) provide the scoring; this chapter provides the program around them.

7.4.1 Inventory

The inventory divides the corridor into discrete earthwork assets and records the basic facts about each.

Table 7.4-1. Minimum inventory data for each earthwork asset
ItemContent
IdentificationAsset ID, line segment, mileposts, track(s), side
TypeCut, embankment, sidehill (cut and fill), at-grade, retained
GeometryHeight or depth, slope angles, length, benches
MaterialsSoil and rock types, fill type (Chapter 2.10), problem soils present
DrainageDitches, culverts, subdrains, outfalls and their condition
HazardsMapped hazards from the desktop study: landslide, rockfall, karst, mining, flooding, scour
HistoryPast failures, repairs, speed restrictions, maintenance frequency
Consequence factorsTraffic, speed, hazardous materials, passenger service, detour length, adjacent property

LiDAR, aerial imagery and the KMZ workflow allow most of the inventory to be built at the desk, with field verification concentrated on the higher-hazard assets (Chapter 3.2).

7.4.2 Condition Examination

Each asset is examined on a cycle set by its rating, with more frequent examinations for higher ratings and after triggering events (heavy rain, floods, earthquakes, freeze-thaw). The examination records observed defects using consistent terms so that changes can be tracked.

Table 7.4-2. Typical earthwork defects and indicators
DefectIndicators
InstabilityTension cracks, scarps, bulging toe, leaning trees and poles, track alignment or surface defects
Erosion and scourGullies, undercut toe, exposed culvert ends, scour at bridge approaches
Drainage failureBlocked ditches and culverts, ponding, seepage on slopes, soft wet track
RockfallFresh rock in ditch, overhangs, open joints, damaged fences or detectors
Settlement and subsidenceSags, depressions, sinkholes, repeated surfacing
Burrowing and vegetationAnimal burrows in embankments, large trees on steep slopes, root jacking of rock

Defect ratings from the examination combine with the geospatial hazard ratings to give the current risk, as set out in Chapter 3.8.

Supplemental reference

Access Roads and Right-of-Way Ditches: Annual Runoff Inspection

Unpaved access roads, maintenance roads and the ditches along them deliver sediment to streams and wetlands and, when they erode, undermine the toe of embankments and cut slopes. County stormwater programs inspect unpaved roads once a year with a simple yes/no checklist, where “yes” means action is needed and a work order follows. The items translate directly to railroad access roads and right-of-way ditches:

  • erosion of the road surface (rutting, depressions) and whether best management practices (BMPs) are needed;
  • potholes needing fill, and whether added crushed stone or millings are required;
  • sediment reaching a stream or wetland;
  • ditch condition: erosion undermining the ditch, need for check dams or cleaning;
  • whether existing BMPs work, and whether more are needed;
  • debris, spills and illegal dumping, with notification of the right group.

Typical BMPs are check dams, filter fabric in ditches, filling potholes, grassing, road scraping and grading, ditch cleaning, and turnouts that divert water off the road before it gathers speed. Each finding should record the action, the work order and the follow-up.

For railroad work: Add access roads, maintenance roads and right-of-way ditches to the earthworks inventory (Section 7.4.1) and examine them on the same annual cycle, using a checklist like this. Ditches that erode toward a fill toe or a cut slope, or that silt up and pond water against the track, are geotechnical problems as well as stormwater problems; rate them with the drainage elements of the risk rating. Keep the inspection records, since stormwater permits for the right-of-way may require them.

Source: Richland County, SC, Roadway Runoff Management Program: Unpaved Roads Annual Inspection Form Guidance. Summarized and paraphrased.

7.4.3 Deterioration and Triggers

Earthworks deteriorate in characteristic ways: cut slopes in weak rock and clay soften and flatten over decades; embankments of clay fill lose strength as seasonal wetting and drying opens fissures; ditches fill and culverts corrode; vegetation changes. Many failures, however, are not gradual but triggered: by intense or prolonged rainfall, by rising rivers, by changes made at the toe (ditch cleaning, excavation) or at the crest (loading, drainage changes). An asset program therefore needs two parts: a cyclic program addressing deterioration, and an event-driven program (inspection after storms, live risk rating) addressing triggers (Chapter 3.8).

7.4.4 Prioritizing Interventions

With limited funds, interventions should be ranked by how much risk they remove per dollar, not simply by which assets score highest. A high-risk site that is very expensive to fix may rank below two moderate-risk sites that are cheap to fix.

R = F × S(Eq. 7.4-1)
Risk score on the GHRM 5 × 5 matrix: F = frequency rating, S = severity rating (each 1 to 5).
E = (Rbefore − Rafter) / C(Eq. 7.4-2)
Risk reduction efficiency: reduction in risk score per unit cost C (for example, per $1 million).

Efficiency ranking should be combined with judgment: any site with a severity of 5 and an increasing frequency needs action regardless of efficiency, and low-cost actions such as clearing drainage are usually worth doing everywhere.

7.4.5 Remedial Options
Table 7.4-3. Remedial measures for earthworks
CategoryMeasuresNotes
DrainageDitch cleaning and lining, culvert repair and upsizing, horizontal drains, trench drains, surface water diversionUsually the most cost-effective; clean ditches without undercutting the toe
GeometrySlope flattening, unloading the crest, toe berms and buttressesNeeds right-of-way; berms must sit on competent ground
StructuralSoldier pile and lagging walls, drilled shaft walls, sheet piles, anchored wallsRailroads favor driven or drilled soldier pile walls for stabilization (Chapter 7.1)
ReinforcementSoil nails, rock bolts, reinforced slopesCheck corrosion where ground chemistry is aggressive (Chapter 2.12)
Ground improvementGrouting, deep mixing, lime injection, aggregate columnsSee Chapter 7.2
Rock slopeScaling, trim blasting, mesh and drapes, rockfall barriers, catch ditches, slide fencesDetectors provide warning, not prevention
Erosion and scourRiprap, gabions, articulated mats, vegetation, channel trainingSize for design flood; protect toe below scour depth
OperationalMonitoring, speed restrictions, slide detection, inspection after stormsThe observational approach (Chapter 5.5)
Trench excavation and placement of Electro-Kinetic Geosynthetic (EKG) electrodes
Photo 7.4.5-1. Trench excavation (left) and placement of Electro-Kinetic Geosynthetic (EKG) electrode strips (right) during installation. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Cutaway illustration showing installation of electrodes in a slope stabilization project
Photo 7.4.5-2. Cutaway illustration showing the installation of electrodes in a slope stabilization project. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Illustration of the electrode pattern, wired for electrokinetic activation
Photo 7.4.5-3. Illustration of the electrode pattern, wired for electrokinetic activation. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Slope during electrode installation, with cathode and anode locations labeled
Photo 7.4.5-4. Slope during electrode installation, with tree preservation noted; cathode and anode locations labeled. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Close-up of anode and cathode connections during active electrokinetic treatment, with nearby plant growth
Photo 7.4.5-5. Anode (left) and cathode (right) connections during active electrokinetic treatment; nearby plant growth indicates the low impact of the treatment on the surrounding environment. (Courtesy of Electrokinetic, Ltd., United Kingdom.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Plan view diagrams of the vertical and horizontal electrode layouts used at the Interstate 40 test section
Photo 7.4.5-6. Plan view diagrams of the vertical-anode and horizontal-anode/cathode electrode layouts used at the Interstate 40 test section, Holbrook, AZ. (From O'Bannon, Morris, and Mancini, 1976; reproduced with permission of the Transportation Research Board.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Wiring diagram of the electrode instrumentation used at the Interstate 40 test section
Photo 7.4.5-7. Wiring diagram of the current and voltage instrumentation used at the Interstate 40 test section. (From O'Bannon, Morris, and Mancini, 1976; reproduced with permission of the Transportation Research Board.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Plan of electrode and chemical injection point arrangement used at the Seattle-Tacoma Airport runway test section
Photo 7.4.5-8. Plan of the electrode and chemical-injection-point arrangement used at the Seattle-Tacoma Airport runway test section. (Dearstyne and Newman, 1963; with permission of ASCE.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Cross section of the saturated runway subgrade with mud and void zones, Seattle-Tacoma Airport
Photo 7.4.5-9. Cross section of the saturated runway subgrade, showing mud and void zones beneath the pavement and the electrode/drain arrangement used to treat them. (Dearstyne and Newman, 1963; with permission of ASCE.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Close-up photograph of black perforated GEOWEB strip material showing the diamond-textured surface, perforation holes, and a weld point
Photo 7.4.5-10. Textured, perforated Geoweb strip material. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Photograph of three workers in high-visibility gear installing expanded black GEOWEB sections down a rock slope, with white geotextile visible beneath the cells
Photo 7.4.5-11. GEOWEB sections expanded and installed over a graded slope. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Line diagram showing a diamond-shaped Geoweb cell with Cell Length and Cell Width axes and dashed/solid lines illustrating the range of variable expansion
Photo 7.4.5-12. Variable Expansion of the Geoweb Cell. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Line diagram of an expanded Geoweb honeycomb section with an arrow through the center labeled Direction of Expansion, and Length/Width axis labels
Photo 7.4.5-13. Geoweb Expansion. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Line diagram of the standalone ATRA Stake Clip, a blue cup-shaped molded polyethylene device with prong-like legs
Photo 7.4.5-14. ATRA® Stake Clip. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Line diagram of the ATRA Anchor, showing the blue Stake Clip attached as an end cap to a green steel reinforcing rod
Photo 7.4.5-15. ATRA® Anchor. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Diagram of the ATRA Stake Clip installed over the top of a gray Geoweb cell wall, engaging the arm of the clip over the wall
Photo 7.4.5-16. ATRA® Anchor Connected Over the Cell Wall. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Diagram showing a blue ATRA Anchor clip driven flush with the base of a Geoweb cell, engaged over a green tendon rod passing through the wall
Photo 7.4.5-17. ATRA® Anchor over Tendon. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Rendering of the standalone gray ATRA Tendon Clip, a ring-shaped molded polyethylene device with a locking post
Photo 7.4.5-18. ATRA® Tendon Clip. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Rendering of two Geoweb cell walls each fitted with a gray ATRA Tendon Clip and a yellow tendon passing diagonally through the wall
Photo 7.4.5-19. ATRA® Tendon Clips with Tendons through the Geoweb Cell Wall. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Photograph of a hand inserting a black T-shaped ATRA Key into the slot between two black Geoweb cell walls
Photo 7.4.5-20. ATRA® Key Geoweb Panel Connection — inserting the key. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).

Remedial design should address the cause identified in the investigation, not only the symptom; a wall built across a slide that is driven by a blocked culvert will be loaded by the same water that caused the slide. Retaining structures and ground improvement are covered in Chapter 7.1 and Chapter 7.2, and slope stability analysis in Chapter 6.3.

7.4.6 Worked Example
The example uses generic sites and costs and is not taken from any client project. It follows the five-part format.
Example 7.4-1: Ranking Three Earthwork Repairs by Risk Reduction per Dollar

A district has budget for about $2 million of earthwork repairs this year. Three candidate sites have been rated on the GHRM 5 × 5 matrix, with the expected rating after the proposed repair and its estimated cost.

Given

VariableValueDescription
Site AF = 4, S = 4; after: F = 2, S = 4; C = $1.2MEmbankment slide; soldier pile wall
Site BF = 3, S = 5; after: F = 1, S = 5; C = $2.5MRock cut over a bridge approach; full slope stabilization
Site CF = 5, S = 3; after: F = 2, S = 3; C = $0.6MCulvert-driven settlement; culvert replacement and drainage
BudgetAbout $2.0MAvailable this year

Required

  • Risk scores before and after for each site
  • Risk reduction per $1M
  • Ranked program within the budget

Equations

  1. Eq. 7.4-1: R = F × S — risk score
  2. Eq. 7.4-2: E = (Rbefore − Rafter)/C — risk reduction per $1M

Steps

Step 1 · Site A
R: 4 × 4 = 16 → 2 × 4 = 8; reduction 8; E = 8 / 1.2
E ≈ 6.7 per $1M
↓
Step 2 · Site B
R: 3 × 5 = 15 → 1 × 5 = 5; reduction 10; E = 10 / 2.5
E = 4.0 per $1M
Spot check: Largest reduction, but the most expensive.
↓
Step 3 · Site C
R: 5 × 3 = 15 → 2 × 3 = 6; reduction 9; E = 9 / 0.6
E = 15 per $1M
Spot check: Cheapest site gives the most risk reduction per dollar.
↓
Step 4 · Rank and fit to budget
C ($0.6M) + A ($1.2M) = $1.8M ≤ $2.0M; B would exceed budget
Program: C, then A; B next year
Spot check: Total reduction 9 + 8 = 17 points for $1.8M, against 10 points for $2.5M at B alone.
↓
Solution
Rank by efficiency: Site C (15 per $1M), Site A (6.7), Site B (4.0). Fund C and A this year ($1.8M, 17 points of risk reduction) and program B for next year.

Solution

Rank by efficiency: Site C (15 per $1M), Site A (6.7), Site B (4.0). Fund C and A this year ($1.8M, 17 points of risk reduction) and program B for next year.

Ranking by the before score alone would put A first (16) and treat B and C as equal (15). Ranking by efficiency shows that the culvert repair at C removes almost as much risk as the expensive rock stabilization at B for a quarter of the cost.

Judgment still applies: Site B has a severity of 5 (a rock cut over a bridge approach). If its frequency rating is rising, or if it is on a passenger route, it may justify interim measures this year, such as scaling, a slide fence or monitoring under a TARP (Chapter 5.5), while the full stabilization is designed and funded. The remaining $0.2M could fund those interim measures.

Example 7.4-2: Carbon Footprint of Two Facings for a Nailed Cut Slope

Problem Statement

A cut slope beside the main track of a Class I railroad located in Pennsylvania keeps raveling onto the ditch and needs a nailed facing over a 300-ft length (about 9,000 ft² of face). Two facings meet the stability and design-life requirements: reinforced shotcrete, or galvanized high-tensile steel wire mesh with an erosion mat. The owner reports emissions and wants the carbon footprint of each option alongside the cost estimate (Section 7.4.10).

Track Nails (both options) Facing:A shotcrete, orB steel wire mesh Given (300-ft cut, 9,000 ft² face) A: shotcrete 545,000 lb nail grout cement 113,000 lb steel (nails, rebar) 32,700 lb B: mesh steel 5,400 lb; zinc 160 lb nail steel 19,200 lb nail grout cement 113,000 lb erosion mat 450 lb Haul 40 miles by truck Required: footprint of A and B(lb CO₂e) and largest item
Figure 7.4-1. Example 7.4-2: nailed cut slope with two facing options.

Given

VariableValueDescription
Option A materialsShotcrete 545,000 lb (including 25% rebound); nail grout cement 113,000 lb; steel nails and reinforcement 32,700 lbShotcrete facing
Option B materialsMesh steel 5,400 lb; zinc 160 lb; nail steel 19,200 lb; nail grout cement 113,000 lb; polypropylene mat 450 lbWire mesh facing
Factors (Table 7.4-10)Concrete 0.135; cement 0.83; reinforcing steel 1.25; primary steel 1.7; zinc 2.46; polypropylene 2.0 lb CO2e/lbGWP per lb of material
Transport40 miles by truck at 0.72 lb CO2e per ton-mileAll materials

Required

  • (a) Footprint of Option A
  • (b) Footprint of Option B
  • (c) Which item dominates, and the saving

Equations

  1. Eq. 7.4-4: Footprint = Σ(mass × GWP) + Σ(ton-miles × 0.72)

Steps

Step 1 · (a) Option A materials
545,000 × 0.135 + 113,000 × 0.83 + 32,700 × 1.25 = 73,600 + 93,800 + 40,900
208,300 lb CO2e
↓
Step 2 · (a) Option A transport
690,700 lb = 345 tons; 345 × 40 × 0.72
9,900 lb; total A ≈ 218,000 lb CO2e
↓
Step 3 · (b) Option B materials
5,400 × 1.7 + 160 × 2.46 + 19,200 × 1.25 + 113,000 × 0.83 + 450 × 2.0 = 9,200 + 400 + 24,000 + 93,800 + 900
128,300 lb CO2e
↓
Step 4 · (b) Option B transport
138,200 lb = 69 tons; 69 × 40 × 0.72
2,000 lb; total B ≈ 130,000 lb CO2e
Spot check: B uses one-fifth of the mass of A, and its haul footprint is about one-fifth of A’s: 2,000/9,900 = 0.20.
↓
Step 5 · (c) Compare
93,800 / 130,000 for the nail grout in B; (218,000 − 130,000) / 218,000
Nail grout cement is about 72% of B; B saves about 40%
↓
Solution
A ≈ 218,000 lb CO2e (109 tons); B ≈ 130,000 lb CO2e (65 tons); B is about 40% lower.

Solution

(a) About 218,000 lb CO2e. (b) About 130,000 lb CO2e. (c) The nail grout cement dominates both options, so B saves about 40%, less than the four to five times reported in Section 7.4.10.

The saving here is smaller than in the published comparison because the same nails are used in both options and their grout dominates. The next places to cut carbon are the nails themselves: fewer or shorter nails where the design allows, or a grout with supplementary cementitious material. Check the factors against current supplier declarations before reporting the numbers, and note that delivery by work train instead of truck would cut the small transport share further.

Example 7.4-3: Laying Out Recycled Plastic Pins for a Shallow Slide

Problem Statement

A 20-ft high-plasticity clay fill below the main track of a Class I railroad located in Texas has a shallow slide 100 ft long that has pushed the toe into the ditch after every wet season. Inclinometers show the slip surface is 4 to 6 ft deep. The railroad wants a repair that can be installed from the slope face in short work windows, and recycled plastic pins are proposed (Section 7.4.9). The engineer must choose the pin spacing that raises the factor of safety to 1.40 and estimate the number of pins and working days.

Track Slip surface, R = 40 ft 6 rows of 10-ft pins, 4 ft apart Required: spacing salong the slope, pin count Given (per ft of slope)MD = 300,000 lb-ftMR = 315,000 lb-ft (FS 1.05)Target FS = 1.40Pin resistance 1,200 lbRepair length 100 ft100–120 pins per day
Figure 7.4-2. Example 7.4-3: slip surface crossed by rows of plastic pins.

Given

VariableValueDescription
MD, MR300,000 and 315,000 lb-ft per ft of slope lengthDriving and resisting moments from back-analysis (FS = 1.05)
FStarget1.40Required factor of safety after repair
P1,200 lb per pinDesign lateral resistance per pin at the slip surface, reduced for creep (from limit-resistance curves or load tests)
R40 ftSlip circle radius; pin force taken as acting at R
Rows6 rows of 10-ft pins, 4 ft apart down the slopeRows that cross the slip surface
L; rate100 ft; 100 to 120 pins per dayRepair length and installation rate

Required

  • (a) Added resisting moment needed per ft of slope
  • (b) Pins needed per ft of slope length and the spacing along the slope
  • (c) Total pins and working days

Equations

  1. Eq. 7.4-3: FS = (MR + ΔMR) / MD
  2. Eq. 1: ΔMR = (nrows / s) P R per ft of slope length, with s the pin spacing along the slope

Steps

Step 1 · (a) Moment needed
1.40 × 300,000 − 315,000
ΔMR = 105,000 lb-ft per ft
↓
Step 2 · (b) Pins per ft
Each pin gives 1,200 × 40 = 48,000 lb-ft; 105,000 / 48,000
2.19 pins per ft of slope length
↓
Step 3 · (b) Spacing
s = 6 rows / 2.19 = 2.74 ft; round down
s = 2.5 ft along the slope (grid 2.5 ft × 4 ft)
Spot check: With s = 2.5 ft: ΔMR = (6/2.5) × 48,000 = 115,200; FS = (315,000 + 115,200)/300,000 = 1.43. A 3-ft spacing gives only 1.37.
↓
Step 4 · (c) Pins and days
100/2.5 = 40 per row; 40 × 6 rows; 240 / 100 to 240 / 120
240 pins; about 2 to 2.5 working days
↓
Solution
2.5 ft × 4 ft grid; FS ≈ 1.43; 240 pins; 2 to 3 days of installation.

Solution

(a) 105,000 lb-ft per ft of slope. (b) 2.19 pins per ft, so pins at 2.5 ft along the slope in rows 4 ft apart (FS ≈ 1.43). (c) 240 pins, about 2 to 3 working days.

This is a simplified moment check that treats every pin as mobilizing its full design resistance at the slip surface; pins near the crest and toe, where the slip surface is shallow, may mobilize less, so check the layout with a slope stability program that models pins as reinforcement. Close the spacing near the crest where movement threatens the shoulder, extend the rows 10 ft beyond each end of the slide, restore drainage at the toe, and set survey points to compare pinned and unpinned lengths (Section 7.4.9).

7.4.7 Cross-References

Related chapters in this manual:

Related ICE Manual chapters are listed in the Further Reading box at the top of this chapter and in Appendix G.

Photograph credits

The photographs in this chapter come from the Geo Technology Reference library. Each is credited as stated in its source document; they are reproduced for reference and remain the property of the credited owners.

  1. Photo 7.4.5-1 — Trench excavation (left) and placement of Electro-Kinetic Geosynthetic (EKG) electrode strips (right) during installation. (Courtesy of Electrokinetic, Ltd., United Kingdom.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  2. Photo 7.4.5-2 — Cutaway illustration showing the installation of electrodes in a slope stabilization project. (Courtesy of Electrokinetic, Ltd., United Kingdom.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  3. Photo 7.4.5-3 — Illustration of the electrode pattern, wired for electrokinetic activation. (Courtesy of Electrokinetic, Ltd., United Kingdom.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  4. Photo 7.4.5-4 — Slope during electrode installation, with tree preservation noted; cathode and anode locations labeled. (Courtesy of Electrokinetic, Ltd., United Kingdom.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  5. Photo 7.4.5-5 — Anode (left) and cathode (right) connections during active electrokinetic treatment; nearby plant growth indicates the low impact of the treatment on the surrounding environment. (Courtesy of Electrokinetic, Ltd., United Kingdom.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  6. Photo 7.4.5-6 — Plan view diagrams of the vertical-anode and horizontal-anode/cathode electrode layouts used at the Interstate 40 test section, Holbrook, AZ. (From O'Bannon, Morris, and Mancini, 1976; reproduced with permission of the Transportation Research Board.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  7. Photo 7.4.5-7 — Wiring diagram of the current and voltage instrumentation used at the Interstate 40 test section. (From O'Bannon, Morris, and Mancini, 1976; reproduced with permission of the Transportation Research Board.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  8. Photo 7.4.5-8 — Plan of the electrode and chemical-injection-point arrangement used at the Seattle-Tacoma Airport runway test section. (Dearstyne and Newman, 1963; with permission of ASCE.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  9. Photo 7.4.5-9 — Cross section of the saturated runway subgrade, showing mud and void zones beneath the pavement and the electrode/drain arrangement used to treat them. (Dearstyne and Newman, 1963; with permission of ASCE.) Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
  10. Photo 7.4.5-10 — Textured, perforated Geoweb strip material. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  11. Photo 7.4.5-11 — GEOWEB sections expanded and installed over a graded slope. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  12. Photo 7.4.5-12 — Variable Expansion of the Geoweb Cell. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  13. Photo 7.4.5-13 — Geoweb Expansion. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  14. Photo 7.4.5-14 — ATRA® Stake Clip. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  15. Photo 7.4.5-15 — ATRA® Anchor. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  16. Photo 7.4.5-16 — ATRA® Anchor Connected Over the Cell Wall. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  17. Photo 7.4.5-17 — ATRA® Anchor over Tendon. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  18. Photo 7.4.5-18 — ATRA® Tendon Clip. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  19. Photo 7.4.5-19 — ATRA® Tendon Clips with Tendons through the Geoweb Cell Wall. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
  20. Photo 7.4.5-20 — ATRA® Key Geoweb Panel Connection — inserting the key. Photographer not stated in the source. Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
7.4.8 Concrete Culverts, Walls and Abutments: Deterioration, Assessment and Repair

The earthworks inventory (Section 7.4.1) includes concrete and masonry structures that hold the earthworks together: culverts and their headwalls, retaining walls, wing walls, abutments and the footings of piers and signal structures. Their failure is a ground hazard even when the cause is the concrete, because a collapsed culvert or a failed wall takes the embankment with it. This section covers how concrete in these structures deteriorates, how to assess it, and the repair choices, drawing on the proceedings of the 2nd International Conference on Concrete Repair, Rehabilitation and Retrofitting (Cape Town, 2008).

The economics are summarized by de Sitter’s “rule of fives”, quoted by Walraven (2009): if maintenance is skipped, the later repair costs about five times the maintenance saved; if repair is skipped, renewal costs about five times the repair saved. Early condition assessment and timely repair are therefore part of the risk reduction in Chapter 3.8, not an optional extra.

7.4.8.1 How concrete deteriorates

  • Chloride-induced corrosion of reinforcement, from deicing salt at grade crossings and on overhead structures, salt-laden runoff, and sea water. It is the most common cause of serious damage, together with carbonation.
  • Carbonation of the cover concrete, which lowers the pH around the steel until it can corrode. It is slow in good, wet concrete and fast in porous, partly dry concrete with thin cover.
  • Freeze–thaw damage, worse with deicing salts and in saturated concrete such as culvert inverts, headwalls and wall faces that stay wet.
  • Chemical attack: sulfate attack from sulfate-bearing soil and groundwater (Chapter 2.12), and acid attack. Culverts that carry sewage-affected flow can suffer biogenic sulfuric acid attack above the water line, as in concrete sewers.
  • Alkali-aggregate reaction (AAR): the reaction of alkalis in the cement with reactive silica in the aggregate forms a gel that swells and causes map cracking and longitudinal cracks, often years after construction.

Critical chloride content. Angst and Vennesland (2009) reviewed about 40 studies of the chloride content at which steel starts to corrode. Reported values ranged from 0.02% to 3.08% chloride by weight of cement, so no single threshold exists; the steel–concrete interface, the pH of the pore water and the electrochemical potential of the steel all control it. In practice, owners set decision levels: on one set of marine bridges, members with more than 1% chloride by weight of cement at the steel were judged too contaminated for coatings and inhibitors and were either treated electrochemically or rebuilt (Streicher et al. 2009).

7.4.8.2 Condition assessment and nondestructive testing

  • Visual mapping of cracks, spalls, rust stains, efflorescence, scaling, exposed steel and wall movement, tied to stations and photographs (Section 7.4.2).
  • Cores for strength, chloride profiles and carbonation depth, and petrography for AAR. Fischboeck and Harmuth (2009) combined visual examination, a damage rating index from polished sections, ultrasonic pulse velocity and resonant frequency to identify and rank AAR damage; profiles of dynamic modulus from pulse velocity located the worst-damaged zones.
  • Ultrasonic pulse-echo with low-frequency, dry point-contact transducers and synthetic-aperture imaging measures thickness and finds voids, delaminations and ungrouted ducts from one face (Wiggenhauser 2009). Ground-penetrating radar locates reinforcement and measures cover, and electrical resistance tomography maps reinforcement and moisture.
  • Culverts: a CCTV survey alone does not give a complete assessment. Da Silva and Goyns (2009) calibrated CCTV with physical measurements, including windows cut through the pipe wall to measure the actual loss of material, and assessed the pipe and surrounding soil as one system. Leaks out of a culvert carry soil with them and create voids under the track (Chapter 2.1, Section 2.1.5; Chapter 2.11).
  • Reliability of NDT. Methods should be validated against reference specimens or cores before they are relied on for decisions, and combining methods gives more reliable results than any one alone.

7.4.8.3 Repair and protection options

Table 7.4-8. Repair and protection options for reinforced concrete earthwork structures
OptionWhat it doesNotes for use
Water repellent (silane) impregnationKeeps water and chlorides out of sound concreteWorks only if it penetrates deeply enough. Johansson et al. (2009) found that extending contact time from 1 to 5 hours (for example by using a paste or gel rather than a liquid) about doubles the depth, as do drier concrete and higher porosity. Check depth by splitting a treated core and wetting it.
Corrosion inhibitorsSlow corrosion of steel in contaminated concreteLess effective at high chloride levels.
Patch repairReplaces damaged concrete around the steelBond depends more on an undamaged substrate than on roughness. Bissonnette et al. (2009) found that jackhammering leaves a damaged surface that outweighs its extra roughness; hydrodemolition, scarifying and blasting gave better bond. Verify with pull-off tests.
Galvanic (sacrificial) anodesZinc anodes connected to the steel corrode instead of itNo power supply; typical design life about 25 years. Anode mortar dosages of roughly 0.1 lb per ft² of steel surface have been used (Bänziger et al. 2009). Can be checked during routine inspections by measuring anode current.
Impressed-current cathodic protectionA power supply drives protective current to the steelLong-lived; needs monitoring and maintenance of the power supply.
Electrochemical chloride extractionA temporary external anode draws chlorides out of the cover and raises the pH at the steelTreatment over weeks; seal the surface afterward to stop new chlorides. Treated bridge members showed no new spalling or rust staining after four years (Streicher et al. 2009).
Realkalisation and hybrid treatmentsRestore high pH at the steelA brief impressed-current “pit realkalisation” of 1 to 2 weeks, followed by galvanic protection from the same installed anodes, arrests and then prevents corrosion (Glass et al. 2009).
Externally bonded FRPRestores or adds flexural and shear strengthFor walls, caps and beams; needs sound substrate and anchorage at the ends.
Demolish and rebuildRemoves the problemCompare with repair options by life-cycle cost (Chapter 3.8, Section 3.8.40).

Andrade et al. (2009) note that the efficiency of electrochemical treatments has traditionally been checked by switching off the protection current or by coring after treatment, and propose nondestructive checks (impedance, corrosion rate and potential, and the charge passed adjusted for concrete resistance). Ask for a measurable acceptance criterion in any electrochemical treatment contract.

7.4.8.4 Culverts: rehabilitate or replace

Da Silva and Goyns (2009) assessed two deep concrete sewers under a busy street that had deteriorated in different ways: one, made with dolomitic aggregate and a sacrificial layer, had lost material evenly; the other, cast in place with siliceous aggregate, had lost cement paste and exposed its aggregate. Because open-cut replacement was ruled out, both were rehabilitated by trenchless lining with a close-fitting continuous liner, and the annular space between liner and host pipe was grouted to prevent water paths. The same reasoning applies to deep culverts under track: open-cut replacement needs a track outage and a temporary shoofly or bridge, so lining, with the annulus grouted and any voids around the pipe filled, is often the preferred choice where the remaining pipe and surrounding soil can carry the load. Check the lined culvert’s hydraulic capacity with the reduced diameter (Chapter 3.5, Section 3.5.10).

7.4.8.5 Retrofitting a slope failure with a structure

After a rainfall-triggered failure of a road cut on a mountain pass, Kruger et al. (2009) compared three repairs: an anchored pile wall with a cantilevered deck, a mechanically stabilized earth wall, and a half-width viaduct on piers. Steeply dipping, weathered and jointed rock made isolated pier footings vulnerable to block and wedge failure, and the MSE wall could have been undercut by future slides, so the anchored pile solution was chosen: eight 4-ft-diameter bored piles at about 26-ft centers, about 46 ft long and socketed about 13 ft into competent rock, carrying a 200-ft-long cantilevered deck balanced by a buried slab, with re-stressable rock anchors and the slab bolted down to rock. A temporary soil-nail wall kept traffic moving during construction.

For railroad work: the same logic applies to a sidehill grade that has lost its outer shoulder: where the rock structure dips out of the slope, prefer continuous anchored piles socketed into rock over isolated footings or a reinforced fill that could be undercut (Chapter 7.1, Section 7.1.4; Chapter 6.3). Use re-stressable anchors so that load can be checked and restored during the structure’s life.

7.4.8.6 Fitting concrete condition into the asset program

  • Add concrete condition (cracking, spalling, corrosion staining, AAR, wall loss, leaking joints) to the condition examination of culverts, walls and abutments (Section 7.4.2), and record it as a defect rating (Chapter 3.8).
  • Treat deterioration mechanisms as preparatory factors in the trigger analysis (Chapter 3.8): a corroding culvert is a slow loss of margin until a storm or a train load finishes it.
  • Plan intervention early: by the rule of fives, protecting sound concrete or patching early is far cheaper than rebuilding a failed structure under traffic.

7.4.8.7 Sources

Papers in Alexander, M. G., Beushausen, H.-D., Dehn, F. and Moyo, P. (eds.) (2009). Concrete Repair, Rehabilitation and Retrofitting II. Proceedings of the 2nd International Conference on Concrete Repair, Rehabilitation and Retrofitting (ICCRRR), Cape Town, 2008. London: CRC Press/Balkema. Summaries are paraphrased and values converted to English units.

  1. Walraven, J. C. (2009). “Design for service life: How should it be implemented in future codes.” ICCRRR 2008, 3–10.Find source ↗
  2. Wiggenhauser, H. (2009). “Advanced NDT methods for the assessment of concrete structures.” ICCRRR 2008, 19–30.Find source ↗
  3. Andrade, C., Martínez, I., Castellote, M. and García de Viedma, P. (2009). “Efficiency control of electrochemical repair techniques.” ICCRRR 2008, 31–38.Find source ↗
  4. Angst, U. and Vennesland, Ø. (2009). “Critical chloride content in reinforced concrete – State of the art.” ICCRRR 2008, 149–150.Find source ↗
  5. Fischboeck, E. K. and Harmuth, H. (2009). “An Austrian experience with identification and assessment of alkali-aggregate reaction in motorways.” ICCRRR 2008, 191–192.Find source ↗
  6. Da Silva, V. A. and Goyns, A. M. (2009). “The aging of concrete sewers: Replace or rehabilitate.” ICCRRR 2008, 281–282.Find source ↗
  7. Johansson, A., Janz, M., Silfwerbrand, J. and Trägårdh, J. (2009). “Protection of concrete with water repellant agents – What is required to achieve a sufficient penetration depth?” ICCRRR 2008, 287–288.Find source ↗
  8. Streicher, P. E., Hoppe, G. E., da Silva, V. A. and Kruger, E. J. (2009). “The application of electrochemical chloride extraction to reinforced concrete bridge members.” ICCRRR 2008, 303–304.Find source ↗
  9. Bänziger, H., Vogelsang, J. and Schulze, G. (2009). “The corrosion protection of embedded steel reinforcement in reinforced concrete structures using galvanic anodes.” ICCRRR 2008, 305–306.Find source ↗
  10. Glass, G. K., Roberts, A. C. and Davison, N. (2009). “Re-alkalisation technology applied to corrosion damaged concrete.” ICCRRR 2008, 307–308.Find source ↗
  11. Bissonnette, B., Nuta, A., Morency, M., Marchand, J. and Vaysburd, A. M. (2009). “Concrete repair and interfacial bond: Influence of surface preparation.” ICCRRR 2008, 345–346.Find source ↗
  12. Kruger, E. J., Newmark, A. A. and Smuts, M. (2009). “Mountain pass slope failure retrofitted with half viaduct bridge structure.” ICCRRR 2008, 395–396.Find source ↗
7.4.9 Recycled Plastic Pins for Shallow Slope Failures

Shallow, surface-parallel slides 3 to 6 ft deep are the most common earthwork failure on side slopes built of or cut into high-plasticity clay. They follow prolonged rain: the near-surface soil wets, seasonal shrink–swell cycles open cracks and loosen it, and its strength falls toward the fully softened value. Each slide is small, but the slides recur, and they undermine shoulders, fill ditches and threaten the ballast section at the crest. Driven recycled plastic pins (RPPs) are a low-cost repair that reinforces the slope across the slip surface without excavation (Khan et al. 2018).

7.4.9.1 How the pins work

RPPs are square plastic members, typically 4 in. × 4 in. and 8 to 10 ft long, made mostly of recycled high-density polyethylene with other plastics and minor fillers; fiber-reinforced versions are stiffer. They are driven perpendicular to the slope face on a grid. Each pin crossing the slip surface adds bending and shear resistance, so the factor of safety becomes FS = (MR + ΔMR) / MD (Eq. 7.4-3), where MR and MD are the resisting and driving moments about the slip circle and ΔMR is the added resistance from the pins. Plastic does not rot or corrode, but it creeps under sustained load, so the design resistance per pin should allow for creep over the design life.

7.4.9.2 Field performance

Table 7.4-9. Pinned and unpinned sections of a 30-ft, 3H:1V high-plasticity clay fill slope over five years (after Khan et al. 2018)
ItemValue
SoilCH clay fill from a weathered shale formation; LL 48–79, PI 25–51; back-analyzed FS = 1.05 with fully softened strength
Pins4 in. × 4 in., 8 and 10 ft long, at 3, 4, 5 and 6 ft centers (4 ft in most sections)
Computed FS after pinning1.43 to 1.54 (finite element analysis)
InstallationCrawler rig with a mast-mounted vibratory percussion hammer working on the slope; about 4 minutes per 10-ft pin; 100 to 120 pins per day
Crest settlement after 5 yearsPinned sections 2.75 to 6.25 in. (least where pins were 3 ft apart); unpinned control sections 9.5 to 15 in.
Movement after pinningLess than 1.5 in. of additional settlement in the pinned sections; inclinometers showed movement largest at the surface and decreasing with depth
Untreated slopes nearbySix shallow failures on the opposite, unpinned slope during the monitoring period
Effect of spacing (analysis)Crest displacement rose from about 1 in. at 2-ft spacing to 4.7 in. at 8-ft spacing

7.4.9.3 When to use pins

  • Use them for recurring shallow slides where inclinometers, probing or scarp geometry show the slip surface is well within the pin length. Pins are not a repair for deep-seated or translational slides on a weak layer below the pin tips.
  • Repair the cause as well: restore surface drainage, seal tension cracks, and re-establish vegetation. Pins reduce movement; they do not stop water getting into the slope.
  • Close spacing near the crest gives the most benefit, because that is where movement threatens the shoulder.

For railroad work: Pins suit sloughing cut and fill side slopes in high-plasticity clay where the failures keep reaching the ditch line or the ballast shoulder. The rig works on the slope face, so most of the work can stay outside the track foul zone, but check rig access, the stability of the slope under the rig, and buried signal and communication cables near the crest before driving. Monitor pinned and unpinned lengths with survey points at the crest and an inclinometer, and compare them, as the case history did, before using pins across a whole subdivision. This guidance on use is engineering judgment drawn from the case history, not a design method.

A worked pin layout is Example 7.4-3 (Section 7.4.6).

7.4.9.4 Sources

  1. Khan, M. S., Hossain, M. S., Khan, M. A. and Faysal, M. (2018). “Performance of Recycled Plastic Pin (RPP) for Slope Stabilization.” In Frikha, W., Varaksin, S. and Viana da Fonseca, A. (eds.) (2018). Soil Testing, Soil Stability and Ground Improvement. Proceedings of the 1st GeoMEast International Congress and Exhibition, Egypt 2017. Sustainable Civil Infrastructures. Cham: Springer, 136–148.Find source ↗

Values are as reported in English units.

7.4.10 Carbon Footprint of Remedial Options

Owners increasingly ask for the carbon footprint of a repair alongside its cost. A simple footprint can be estimated from the materials and transport each option needs: list the mass of each material, multiply by an emission factor, and add the transport. Emission factors are expressed as global warming potential (GWP): the mass of CO2-equivalent per unit mass of material, which counts all greenhouse gases, weighted by their effect, and not only CO2 from burning fuel (Gross et al. 2018).

Footprint (lb CO2e) = Σ (mass of material × GWP factor) + Σ (ton-miles hauled × transport factor) (Eq. 7.4-4)

Table 7.4-10. Example GWP emission factors used in a 2017 comparison of slope facings (after Gross et al. 2018)
Material or processGWP (lb CO2e per lb)
Reinforcing steel (mixed converter and electric-arc steel)1.25
Primary (converter) steel1.7
Portland cement0.83
Concrete or shotcrete (about 630 lb cement per yd³)0.135
Zinc for galvanizing2.46
Aluminum11.7
PVC pipe2.16
Polypropylene erosion mat2.0
Truck transport0.72 lb CO2e per ton-mile

7.4.10.1 Example: mesh versus shotcrete facing

For a 330-ft length of nailed slope, a facing of high-tensile steel wire mesh with nails used about 37 tons of materials, most of it the cement grout for the nails. An equivalent reinforced shotcrete facing with nails used about 680 tons, mostly shotcrete (including about 25% rebound loss). The GWP of the mesh option was four to five times lower, because concrete has a high footprint per job and because the lighter option needed less hauling. The open mesh also lets the slope be vegetated and does not trap water behind the facing.

7.4.10.2 Using footprints in option selection

  • Compare options that give the same performance and design life; a low-carbon option that has to be redone sooner is not lower carbon.
  • Count the big items first: cement and concrete, steel, and haul distance usually dominate.
  • Emission factors vary by region, plant and year. Use current environmental product declarations from suppliers where available, and state the factors used.
  • Options that reuse material on site (regrading, rock buttresses from cut material, recycled plastic pins, Section 7.4.9) often have low footprints.

For railroad work: Add a footprint line to the option comparison in Section 7.4.5 when the owner reports emissions. Materials delivered by work train rather than truck have a lower transport footprint per ton-mile, so record how material will reach the site. Do not let the footprint override safety, track outage limits or design life; use it to choose between options that meet those.

A worked comparison of two facings is Example 7.4-2 (Section 7.4.6).

7.4.10.3 Sources

  1. Gross, D., Kytzia, S. and Roduner, A. (2018). “Comparison of the CO2 Record of Different Slope Stabilization Methods.” In Frikha, W., Varaksin, S. and Viana da Fonseca, A. (eds.) (2018). Soil Testing, Soil Stability and Ground Improvement. Proceedings of the 1st GeoMEast International Congress and Exhibition, Egypt 2017. Sustainable Civil Infrastructures. Cham: Springer, 69–78.Find source ↗

Metric values converted to English units; the product names in the paper are omitted.