Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S10 under Supplemental References.
Related section: 7.3.2 Subgrade Strength Testing
Urban road works at Kelvin Grove, Brisbane (2002) required a soaked subgrade CBR of 7% over residual soil and near-surface phyllite. The weathered rock at subgrade level degraded to soil after rain. Samples were taken from the degraded surface with its clay seams, and the laboratory removed the “stone” sizes. The CBR came back at 5% or less. Two further rounds of excavation, each needing a rock-breaker attachment to reach the next sample depth, also failed, ending 4.9 ft below design level, with about AU$100,000 of claims for “unsuitable subgrade” and delays in a busy urban area.
Look’s review found that only the top 4 in had degraded. Below it was competent rock (it needed a rock breaker) with a CBR well above 10%, and once the pavement covered it no further degradation would occur. The tests themselves were unrepresentative because the stone fraction was discarded, so the low CBR could be disregarded.
For railroad work: the same cycle can play out under a new track or yard pavement in weathered shale or phyllite. Protect the formation from rain, trim the softened skin, and check whether the sample is representative before ordering more over-excavation.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §6.11, pp. 192–194. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Related section: 7.3.6 Subgrade Preparation and Compaction Criteria
An expansive clay subgrade passed its density tests (above 95% standard MDD) and was then left uncovered for several weeks of wind and heat. Desiccation cracks appeared, and the question was whether the design modulus of 7,200 psi (CBR about 5%) still held. Plate load tests on cracked and uncracked areas, using the site roller as reaction, showed the cracked areas reached about 60% of the uncracked modulus on the first load cycle and 70% on the second, which is used for fill. The target was EV2 above 7,200 psi at formation level and above 4,350 psi below it. A one-third loss of strength or modulus is typical for fissured or desiccated clays in design.
Table 19-LK1. Plate load tests on uncracked and cracked compacted clay (after Look 2023, Table 10.18)
| Load cycle | Uncracked E (psi) | Cracked E (psi) | Ratio |
|---|---|---|---|
| First | 4,600 | 2,760 | ~60% |
| Second | 11,600 | 8,100 | 70% |
For railroad work: a finished clay subgrade awaiting subballast should be covered or kept moist. If it cracks, re-test it before placing subballast; a passing density test from before the drying no longer applies.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §10.16, pp. 366–368. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Related section: 7.3.7 Intermodal Yard Crane Rail Foundation Subgrade
Wind-farm and substation access roads may carry a single heavy delivery, where a bogged transporter can cost over a million dollars. A 22-ton or 44-ton axle exerts about 92 or 116 psi at the running surface. These are wheeled loads, so the BR470 working-platform method for tracked plant does not apply, and neither does ordinary road pavement design; the Giroud and Han (2004) method is typically used. Roads and hardstands typically need 5,200 and 6,300 psf allowable bearing, more on grades above about 5%.
Soaked tests and drainage are usually left out of a one-off design for cost reasons, so rain is the main risk: Look treats more than about 0.8 in of rain as high risk when an unsoaked CBR was used. At this site the proof roll failed the day before the move, after 2.1 in. and 1.1 in. of rain two and three days earlier. No passing proof roll was seen, but the equipment went on anyway, with significant consequences. Deep ruts under one wheel and none under the other showed non-uniform construction or support.
Recommended field data: DCP, vane shear, light falling-weight deflectometer and plate load tests, with plate tests kept to hardstands and critical spots. The maximum plate pressure reached is not the allowable bearing capacity. In one example a 1,250 psf design subgrade strength, with influence extending 24–31 in, gave calculated ruts above 2 in.
Table 19-LK2. Ground contact pressure by axle load (after Look 2023, Table 11.5)
| Axle load (tons) | Wheel load (tons) | Contact area (in.²) | Contact pressure |
|---|---|---|---|
| 13 | 6.6 | 167 | 80 psi |
| 22 | 17 | 240 | 92 psi |
| 44 | 22 | 380 | 116 psi |
For railroad work: the same logic applies to crane pads and temporary access for bridge erection, transformer delivery to traction substations and intermodal heavy lifts. Hold the move on a failed proof roll after rain.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §11.7, pp. 390–392. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.