Pavement subgrade evaluation for railroad facilities encompasses two distinct but related infrastructure domains: (1) paved surfaces within railroad right-of-way —…
Test the subgrade at finished-grade elevation, not natural grade. Many intermodal yard designs involve cut-and-fill grading of 3–8 ft. The pavement subgrade is the constructed fill surface, not the existing ground surface. Obtain CBR and M_r from test pits or undisturbed samples at the design subgrade elevation. Conducting CBR testing only at the surface of existing ground produces non-representative values when significant earthwork is planned.
Perform soaked CBR as the design value — never unsoaked. Intermodal yards in humid regions (the Southeast and the Mid-Atlantic) experience frequent storm events and elevated seasonal groundwater. Unsoaked CBR values commonly exceed soaked CBR by 3–8× for CL and CH soils. Owner railroads may require soaked CBR per ASTM D1883 as the governing design value.
Separate crane rail foundation design from reach stacker lane design. RMG crane rails impose point loads 5–10× greater than reach stacker distributed loads. Design crane rail foundation beams on piles (Chapter 6.1) independently of the pavement structural number calculation. Intermodal crane runway serviceability is governed by differential settlement (Chapter 6.2), not pavement structural number.
Address frost-susceptible materials at design stage, not during construction. Frost susceptibility classification (Table 7.3-5) must be completed during the geotechnical investigation, not deferred to construction. Discovering F4 material at frost depth during grading operations triggers costly change orders and schedule impacts. Budget for complete soil profiling to Z_f + 3 ft at all facility locations above 44°N latitude.
Apply lime or cement stabilization conservatively in freeze-thaw zones. Lime-stabilized clay subgrades in climates with frequent freeze-thaw cycling (Winnipeg, Chicago, Minneapolis) may experience swell and strength loss from ettringite formation where soluble sulfate exceeds about 3,000 ppm. Test for sulfates (ASTM D4327) before specifying lime treatment on the prairies. Cement and fly ash are also affected, so follow the NLA guidance in Chapter 7.2.
Document subgrade variability along crane runway alignments. Crane runway alignment over variable subgrade produces differential settlement that disrupts crane operations. Minimum investigation for crane runways: CBR at 50-ft intervals along each rail, with test pits to 10-ft depth. Flag locations where CBR coefficient of variation exceeds 25% for additional investigation or localized improvement.
Include a pavement management monitoring program in deliverables. Owner railroads may maintain facility pavement management systems. The geotechnical GDR should include a subgrade baseline data table suitable for direct import into the client's PAVER or similar pavement management system, with unique asset IDs, GPS coordinates, subgrade M_r, design ESAL, and year of construction for each pavement section.
Photo 7.3.11-1. Rubblization using RMI Resonant Breaker. Photograph courtesy of Resonant Machines, Inc., 2005.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.3.11-2. Particle distribution of the recycled pavement material (RPM). Li et al. (2007); with permission from ASCE.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.3.11-3. Hot In-place Recycling (HIR) train. Photograph courtesy of ARRA (2001).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.3.11-4. Multi-unit Cold In-place Recycling train. Photograph courtesy of ARRA (2001).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.3.11-5. Full-Depth Reclamation (FDR). From FHWA-SA-98-042; Kandhal and Mallick (1997).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.3.11-6. Cold milling. From FHWA-SA-98-042; Kandhal and Mallick (1997).Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.3.11-7. Break and seat operation. Photograph courtesy of Antigo Construction, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.Photo 7.3.11-8. Rubblization using MHB Badger Breaker. Photograph courtesy of Antigo Construction, Inc.Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Supplemental reference
Case: rubblizing a failed concrete entrance road inside a 7-day curfew (Class I railroad Intermodal located in Lathrop, CA)
The only access road to the railroad's Lathrop, CA intermodal facility (about 300,000 lifts/yr) was 7.5-in. unreinforced, undoweled PCC panels with corner breaks, cracking and faulting, and signs of weak subgrade. Grinding the faults would not have fixed the rocking panels. Full-depth replacement was estimated at about twice the rehabilitation budget. About 15,100 yd2 were instead rubblized in place with a multi-head breaker and overlaid with HMA within the seven-day road curfew. The authors estimate about 250% savings versus full-depth PCC for the same 20-year life. Geotechnical points from the project:
Longitudinal Cracks Between Asphalt Lanes
Drainage first: trapped water under the slabs defeats rubblization. Guidance cited in the paper recommends edge drains working at least two weeks beforehand unless the section drains freely (Lathrop sat on an embankment with side swales). The new HMA can then trap moisture, so permanent drainage matters.
Subgrade support: the breaker must not punch rubble into the subgrade. Buncher’s airfield chart relating subgrade CBR and slab thickness put Lathrop (CBR ≈ 7.8) in the low-risk category; slabs ≥ 9 in. or with substantial subbase are rarely a problem. Bid a contingency quantity of full-depth replacement for soft spots, and proof-roll behind the breaker with a heavy vibratory steel-wheel roller.
Test strip and test pit to confirm fragment size, no contamination of the rubblized layer by subgrade fines, and no shear distortion of the subgrade.
Vibration: four shallow culverts were protected by removing the pavement full depth over five panel lengths centered on each pipe instead of rubblizing over them.
Production was about 400 linear ft/hr (≈ 350 yd2/hr).
Source: Limburg, A. and Nielsen, D. (2019). “Fast-Tracked Pavement Maintenance Using Concrete Rubblization.” AREMA 2019 Annual Conference Proceedings
Project management · Bull (2015)
Counting Closures in a Life-Cycle Cost Comparison: The I-710 Case
In Bull’s volume, Lee, Kim and Harvey (Chapter 3.8) check the pavement type chosen for Caltrans’ I-710 Long Beach rehabilitation. They follow the Caltrans life-cycle cost procedure: a 60-year analysis period, a 4% real discount rate and no salvage value. Three alternatives were compared: innovative long-life asphalt (the design actually built), standard asphalt, and long-life concrete. Two tools were used. CA4PRS estimated the construction schedule, the number of closures, and the work-zone user delay for the initial work and for every future maintenance and rehabilitation event. RealCost then discounted the agency and user costs.
Potholes in Asphalt Pavement & Repair MethodsTypes of Asphalt Pavement Distresses
Figure 19-PM1. Stacked life-cycle present values for the three I-710 alternatives, split into agency cost (by section type), annual maintenance and road user cost. Source: Bull (2015), Figure 4.4.
Agency cost started from unit prices × quantities, taken from the contractor bid database. Allowances for traffic handling, drainage, storm-water protection, minor items, mobilization, supplemental work and a 20% contingency were then applied as cumulative multipliers. Together these multiplied the bare pavement cost by 1.80.
The closure count proved central. The built design needed 10 fifty-five-hour weekend closures at first and about 296 seven-hour night closures over 60 years. The concrete option needed 30 weekend closures at first, a further 18 at year 50, and about 148 nights.
Table 19-PM1. Table: 60-year present values (after Lee, Kim and Harvey in Bull 2015, Table 4.3)
Alternative
Agency cost
User cost
Total
Innovative long-life AC
$33.2M
$5.8M
$39.0M
Standard AC
$41.1M
$12.1M
$53.2M
Long-life PCC
$50.4M
$9.8M
$60.2M
The standard asphalt option had the lowest initial cost but the highest life-cycle user cost, about twice that of the design that was built.
For railroad work: for intermodal yard pavements, crane-rail runways and grade-crossing approaches, compare subgrade treatment and pavement options the way Caltrans did. For each alternative:
Lay out its maintenance and rehabilitation sequence over the full period.
Count the yard-track, lane or crane outages each event needs.
Price those outages as a user cost, using lost lifts, terminal dwell or train delay.
The same accounting applies to track itself: count the track windows each subgrade option needs over its life, not only the windows for first construction. State the markups explicitly, as the cumulative multiplier table does, so that a reviewer can see how much of the estimate is contingency.
Source: Bull, J. W. (ed.) (2015). Life Cycle Costing for the Analysis, Management and Maintenance of Civil Engineering Infrastructure. Dunbeath, Scotland: Whittles Publishing, pp. 91–108. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Empirical equation note · this section
Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.
RK-10 UCS from point load indexσ꜀Use: Hard, isotropic rock; quick strength index in field. Limits: K varies widely with rock type and anisotropy; calibrate with lab UCS. Unreliable in weak rock (σc < ~3,600 psi).