6.3.18 Vegetation in Slope Stability: Root Cohesion and Suction
Vegetation helps a slope in three ways: it shields the surface from erosion, its roots reinforce the soil, and transpiration removes water. The effect is seldom counted in design, but for shallow slides it can decide the answer (Nowak, 2012, Section 70.5, p. 1057).
Table 6.3-12. Apparent root cohesion c′R from historical data
Vegetation
General range, kPa
General range, psf
Maximum reported, psf
Grasses and shrubs
2 to 6
40 to 125
1,250
Deciduous trees
3 to 10
65 to 210
1,320
Coniferous trees
3 to 6
65 to 125
1,970
Nowak (2012), Table 70.7, p. 1057, data from Norris et al. (2008). Use the general range; the maxima are single records.
Most root reinforcement is within about 2 in. (50 mm) of the surface; tree roots reach about 10 ft (3 m). Another approach allows an enhanced cohesion of up to about 420 psf (20 kPa) only in the upper part of the slope that roots penetrate (Nowak, 2012, p. 1057).
Suction under vegetation also helps cut slopes. One UK metro standard allows a reduction of 0.05 in the design pore pressure ratio ru where cutting slopes are vegetated (Nowak, 2012, p. 1057).
On embankments the same suction gradient drives seasonal shrink–swell creep, so the benefit to a cutting can be a problem on a fill (Chapter 2.5, Section 2.5.18).
Shallow failures on UK highway slopes were rarely deeper than about 5 ft (1.5 m), within a range of about 0.7 to 8 ft (0.2 to 2.5 m), and were more common on slopes higher than about 16 ft (5 m) (Nowak, 2012, p. 1050). Root cohesion acts on exactly this depth range.
Example 6.3-6: Effect of root cohesion on a shallow slide
A grassed cut slope in silty clay stands at 30°. Check a 4-ft-deep slope-parallel slip with and without root cohesion, ignoring suction and seepage.
Given and required for Example 6.3-6.
Given
Variable
Value
Description
β
30°
Slope angle
d
4 ft
Slip depth (within the root zone)
γ
120 pcf
Unit weight
φ′
28°
Effective friction angle
c′
0
Effective cohesion of the soil
c′R
100 psf
Root cohesion, grasses and shrubs (Table 6.3-12)
Required
Factor of safety without and with root cohesion
Equations
SL-01, SL-12: F = (c′ + c′R)/(γ d sinβ cosβ) + tanφ′/tanβ — infinite slope, dry
Steps
Step 1 · Friction term
tan28°/tan30° = 0.532/0.577
0.92
Spot check: Slope steeper than φ′, so F < 1 without cohesion.
↓
Step 2 · Denominator
γ d sinβ cosβ = 120 × 4 × 0.500 × 0.866
208 psf
↓
Step 3 · Root cohesion term
100/208
0.48
↓
Step 4 · F with roots
0.92 + 0.48
1.40
Spot check: Root term is over a third of the total; F is sensitive to c′R.
↓
Solution
F = 0.92 without roots and 1.40 with c′R = 100 psf.
Solution
The grass is what holds this slope. A shallow slip is likely wherever the cover is lost (fire, herbicide, ditching that strips the toe) or where a slip would be deeper than the roots.
Do not use root cohesion to justify a new steep slope. Use it to explain why an existing slope stands and to rank the risk of losing the cover; check the case with c′R = 0 and with the wet-season water table (Section 6.4.11).
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.
Nowak, P. A. (2012). Design of new earthworks. Chapter 70 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1047–1066Find source ↗Library entry
McGinnity, B. T. and Saffari, N. (2012). Earthworks asset management and remedial design. Chapter 71 in Burland, J., Chapman, T., Skinner, H. and Brown, M. (eds) (2012). ICE Manual of Geotechnical Engineering, Volume II: Geotechnical Design, Construction and Verification. ICE Publishing, London, pp. 1067–1086Find source ↗Library entry