USACE EM 1110-2-1902 (2003) provides the standard minimum FS criteria used as a baseline:
| Loading Condition | Min FS |
|---|---|
| End-of-construction (undrained) | 1.3 |
| Long-term static (drained) | 1.5 |
| Steady-state seepage | 1.5 |
| Rapid drawdown | 1.1–1.3 (USACE) |
| Pseudo-static seismic | 1.0 (Hynes-Griffin and Franklin 1984) |
| Residual (progressive failure) | 1.2 (common practice; not in USACE) |
| Emergency repair (temporary) | 1.1 (owner decision; not in USACE) |
Owner railroads may require higher values where a failure would have severe consequences, such as on high-speed passenger lines. Confirm them when the work is scoped.
Table 6.3-1 lists a “USACE Min FS” column, but EM 1110-2-1902 prescribes values only for new earth and rock-fill dams (Table 2.1-1): 1.3 at end of construction (including staged construction), 1.5 for long-term steady seepage, 1.4 at maximum surcharge pool, and 1.1–1.3 for rapid drawdown (1.1 from maximum surcharge pool, 1.3 from maximum storage pool; 1.4–1.5 where drawdown is routine, as in pumped storage). The manual does not tabulate pseudo-static, residual or emergency-repair values; for earthquake loading it refers to ER 1110-2-1806. Cite those rows to the owner railroad's standards or to project-specific judgment, not to USACE.
For “other slopes” — and EM 1110-2-1902 names railway embankments explicitly — USACE says FS should reflect both the uncertainty in strength and pore pressure and the consequence of failure. Where both are small, about 1.3 or even less can be acceptable. Where either grows, a larger FS is needed, and “large uncertainties coupled with large consequences of failure represent an unacceptable condition, no matter what the calculated value of the factor of safety.” Typical minimums are about 1.3 for end of construction and multistage loading, 1.5 for long-term loading, and 1.1–1.3 for infrequent rapid drawdown.
Cuts get weaker with time. For excavated slopes, the long-term condition is normally critical because pore pressures rise and the soil swells and weakens after excavation. A cut in low-permeability soil can stand temporarily yet be unstable in the long term; USACE calls this inherently dangerous and allows it only with detailed study and the observational method.
Source: U.S. Army Corps of Engineers (2003). Slope Stability. EM 1110-2-1902