Consider remedial measures in this order: (1) drainage and subdrainage; (2) geometry, meaning a toe berm, flattening or moving the track; (3) structural support; (4) improving soil properties. Warning devices supplement these.











One slide in western Canada (April 2013) is typical of most slides seen along the track. Snowmelt ran down small gullies, disappeared into the fill, raised pore pressure and took out the embankment. The repair keyed in a toe, rebuilt a 2:1 slope about 50 ft high from air-dumped fill, and added culverts.
After Geotechnology for Railroaders Program, Module 6.1, Module 7.1; Module 6.1 §02–04; Module 7.1 §05. Full reference under Supplemental References.
PERT handles uncertain durations by asking for three estimates per activity: optimistic a, most likely m and pessimistic b. A beta distribution gives the expected time t = (a + 4m + b) ÷ 6 and variance σ² = [(b − a) ÷ 6]². A forward pass gives the early start and finish (ES = largest EF of the predecessors; EF = ES + t), and a backward pass gives the late times (LF = smallest LS of the successors; LS = LF − t). Slack is LS − ES; activities with zero slack form the critical path. Project variance is the sum of the variances of the critical activities. Treating completion time as normally distributed, the probability of finishing by deadline D follows from Z = (D − T) ÷ σ.

Table 13-PM1. Worked example time estimates, weeks (after Swearingen n.d., slide PMT-17)
| Activity | a | m | b | t | σ² | Slack |
|---|---|---|---|---|---|---|
| A | 1 | 2 | 3 | 2 | 0.11 | 0 |
| B | 2 | 3 | 4 | 3 | 0.11 | 1 |
| C | 1 | 2 | 3 | 2 | 0.11 | 0 |
| D | 2 | 4 | 6 | 4 | 0.44 | 1 |
| E | 1 | 4 | 7 | 4 | 1.00 | 0 |
| F | 1 | 2 | 9 | 3 | 1.78 | 6 |
| G | 3 | 4 | 11 | 5 | 1.78 | 0 |
| H | 1 | 2 | 3 | 2 | 0.11 | 0 |
In the slides’ example, a foundry has 16 weeks to install a pollution-control system. The critical path A–C–E–G–H gives T = 15 weeks with variance 3.11, so σ = 1.76 weeks. Then Z = (16 − 15) ÷ 1.76 = 0.57, which corresponds to about a 71.6% chance of meeting the deadline.
For railroad work: slope repairs often have to be finished before a wet season, a freeze-up or a planned outage. Use wide pessimistic estimates for activities controlled by subsurface conditions, such as soldier pile or anchor drilling in uncertain rock, dewatering, or excavation below the slide plane. Use narrow ranges for routine tasks. If the computed probability is low, change the plan (more rigs, a second shift, a staged repair that restores track first) instead of only reporting the risk. The method assumes a single critical path. Where a near-critical path also carries large variance, the true chance of finishing on time is lower than the calculation shows, so check those paths as well.

Source: Swearingen, J. (n.d.). The Basics of Project Management Techniques [lecture slides PMT-1 to PMT-40; author from document properties], slides PMT-13 to PMT-34. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
The Swearingen example of Table 13-PM1. PERT turns three duration estimates per activity into an expected duration and a variance, and the critical path into a probability of meeting a deadline.
| Variable | Value | Description |
|---|---|---|
| Critical path | A–C–E–G–H | Figure 13-PM1 |
| Estimates | A 1/2/3; C 1/2/3; E 1/4/7; G 3/4/11; H 1/2/3 weeks | a / m / b |
| Deadline | 16 weeks |
Expected duration 15 weeks with σ = 1.76 weeks; about a 72% chance of finishing within 16 weeks.
Activity G contributes over half the variance; narrowing its range (by investigating the ground it depends on, for example) raises the probability more than shortening any other activity. On slope repairs before a wet season, use wide pessimistic estimates for work controlled by subsurface conditions.
Slope design relies on expert judgment wherever data are thin, for example in the location of the failure surface, residual strength, piezometric level or the effect of a drainage fix. Cretu et al. summarize the cognitive biases that distort such judgments and how a facilitator can counter them. The overconfidence effect is the tendency to give ranges that are too narrow. One study they cite asked seven very experienced geotechnical engineers to bracket the embankment height that would fail a clay foundation, using bounds intended to have a 50 percent chance of containing the true value. None of the seven ranges captured the actual failure height. Anchoring means that the first number spoken pulls later estimates toward it. Availability means that vivid recent events seem more probable than they are. Motivational bias covers people shading estimates to protect a past position, a budget or a client relationship, and subordinates deferring to superiors in the room. Optimism bias covers people underrating threats on projects they control.

The authors give these countermeasures. Explain the biases to the group before eliciting values. Ask for the worst credible outcome first, then the best case (which may not be “nothing”), then the most likely. Push explicitly for wider bounds. Collect estimates from junior staff or consultants separately and present them to management anonymously. Show the resulting distribution on screen so the experts can confirm that it says what they meant. Base estimates on personal experience, lessons learned, outside expert opinion and empirical records, and use the empirical records first when they exist.
For railroad work: When back-analysis or design inputs rest on judgment, run a short structured elicitation and document it. This applies to the depth of a slip surface between inclinometer readings, the residual friction angle of a slickensided clay, or the water level to assume for a ditch-line slide. Ask for the worst credible case first, record low/most-likely/high values with their reasons, and carry the full range into sensitivity or probabilistic stability runs. A single “engineering judgment” value tends to understate the uncertainty in the factor of safety. Railroad staff who have watched a site for years are valuable sources. Interview them separately from their managers, and treat their recollection of the last movement as an anchor to test, not a bound.
Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 111–121. Summarized and paraphrased. Full reference under Supplemental References.
Jacob and Müller show how a change is priced when the work as bid cannot be performed as described. The approach is not to negotiate a new lump sum. Instead, the original bid calculation is reopened, and only the parts of the item that changed are replaced. The original surcharge rates are kept.
In their example, half of a 131,000 CY excavate-haul-place item (65,400 CY) turns out to be contaminated. That portion must go to an owner-designated disposal site instead of into the on-site fill. The changed item is rebuilt as follows:
The new unit price came out about 3% above the original. The change can be paid either as a new item or as a price difference applied to the affected quantity. The authors prefer the difference method, because it shows exactly which costs were added and which were dropped.
They also list follow-on effects that may need their own pricing:
Underlying this is their split between time-variable and time-fixed site costs.
Keeping the two separate in the estimate is what makes delay and disruption costs calculable later.
For railroad work: Embankment and slide repairs regularly reveal conditions that change the work after award. Examples are contaminated or fouled-ballast spoil that cannot be reused, deeper failure surfaces, and wet borrow. Repricing from the contractor’s bid build-up only works if the contract requires that build-up to be submitted or escrowed. It also needs bid items split finely enough (excavation, haul, placement, disposal) to be reopened. For delay caused by lost track windows or a slower restoration of track speed, price the time-variable site costs per day in advance. That gives the railroad and contractor an agreed basis for standby and extension costs.
Source: Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn, pp. 12–14, 205–208. Summarized and paraphrased. Full reference under Supplemental References.
Pratt sets two rules for measuring earthwork. First, measure in bank measure: the actual in-place dimensions, with no allowance for swell or compaction. Those factors are applied later, when the work is priced. Second, keep each excavation category and each material separate, and measure disposal of surplus as total excavation minus common backfill.
He gives two manual methods for volumes. The grid method takes the cut or fill depth at each grid node and weights it by the area that node represents: one quarter-cell at a corner, two on an edge, and four in the interior. The section method suits long, narrow work such as road and railroad construction. Cross sections are plotted at regular stations, the cut and fill areas are measured at each section, and the volumes come from the average-end-area relation:

V = station spacing × (A1/2 + AN/2 + sum of the intermediate areas)
His example uses five stations 20 ft apart. The cut areas are 108, 40, 73, 91 and 0 ft², and the fill areas are 245, 248, 195, 195 and 328 ft². That gives 5,160 ft³ (191 CY) of cut and 18,490 ft³ (685 CY) of fill. All the cut is reused, so about 494 CY of fill must be imported. Accuracy depends mainly on how faithfully the section profiles are plotted, and closer station spacing improves it.
For railroad work: a slide or washout repair is a short, long-and-narrow job of exactly this kind. A reasonable procedure is:
Each material has its own swell and compaction behavior and its own haul. Report the volumes in bank measure, state the section spacing and the survey date, and keep the section sheets in the calculation appendix. A slide that is still moving changes the existing-ground line, so the quantities will need updating before the bid.
Source: Pratt, D. J. (2011). Fundamentals of Construction Estimating, 3rd ed. Clifton Park, NY: Delmar Cengage Learning, pp. 57, 59–64. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.