6.3.12 Practical Recommendations

Slope stability governs the design of railroad embankments, cut slopes, and side-hill fills across railroad networks.
Authors: Daniel P. Colwell and Mario Ruel
6.3.12 Practical Recommendations
  1. Search the critical failure surface systematically: The minimum FS may not occur at the toe; for embankments over soft clay, the critical circle often exits through the foundation rather than the embankment slope face. Use a grid search over at least 200 trial centers and 5 radii per center in SLOPE/W or equivalent.
  2. Never use peak strength for clay shale or Appalachian weathered shale: Identify pre-existing slickensides in the boring core before selecting design strength. A single set of slickensides on a joint dipping toward the cut is sufficient to require residual-strength analysis. Confirm in writing in the geotechnical report that slickensides were looked for.
  3. Always include the tension crack in cohesive slope analyses: A water-filled tension crack at the crest lowers FS and is often omitted in routine slope analyses. EM 1110-2-1902 discusses how to include it.
  4. Staged construction requires real-time instrumentation and a trigger plan: Specifying staged construction in a geotechnical report without a corresponding instrumentation plan and construction trigger criteria (maximum pore pressure ratio, minimum settlement rate before next lift) is incomplete and creates construction-phase liability. Include the trigger criteria in the geotechnical special provisions (GSP).
  5. Rapid drawdown is often the governing condition for river-crossing embankments: Embankments along rivers with large seasonal stage changes (the Missouri and Platte valleys, for example) are subject to drawdown failures after spring flood recession. The rapid drawdown case per USACE EM 1110-2-1902 Appendix G must be analyzed for any embankment adjacent to a river or reservoir with seasonal water level fluctuation > 5 ft.
  6. Report FS for all loading conditions — not just the critical one: Tabulate FS in the report for end-of-construction, long-term static, steady-state seepage and seismic (where applicable) conditions — even when some conditions clearly are not critical. This demonstrates due diligence and aids the client's Bridge/Track Engineering review.
  7. Coordinate with drainage design: Most railroad slope failures occur after prolonged rainfall that raises pore pressures above the design phreatic surface. The slope stability analysis should be accompanied by a drainage design recommendation (ditch grades, blanket drains, horizontal drains) that maintains pore pressures at or below the assumed steady-state seepage condition.
Micropile installation on a highway slope
Micropile installation on a highway slope
Slope Stability Radar
Slope Stability Radar
Figure 6.3-24. Toe berm about 1/3 of slope height on a drainage blanket.
Figure 6.3-24. Toe berm about 1/3 of slope height on a drainage blanket.

The slope remediation toolbox, in order

Consider remedial measures in this order: (1) drainage and subdrainage; (2) geometry, meaning a toe berm, flattening or moving the track; (3) structural support; (4) improving soil properties. Warning devices supplement these.

Measures to Prevent Landslides
Measures to Prevent Landslides
Highway Slope Stabilization Using Soil Nails & Shotcrete
Highway Slope Stabilization Using Soil Nails & Shotcrete
  • Slopes flattened to 2H:1V are generally very stable. A toe berm about 1/3 of slope height and 12–15 ft wide adds substantial stability; a 30-ft slope needs a berm about 10 ft high. Fill left “hanging” on the shoulder reduces stability.
  • Never leave riprap or fill at the top of an unstable slope. Place riprap from the toe upward. Where a slope has failed into muck, key a rock berm into virgin ground first and add a subdrain (“ballast sausage”).
  • Air-dump fill at a safe point and push it into the slide with an excavator. Never dump directly onto unstable ground.
  • If there is room uphill, shifting the track about 6 ft and flattening the old shoulder can be the whole fix.
  • Use a smooth-drum compactor on silt and clay backfill; a sheepsfoot roller can liquefy it. Clear ice-plugged culverts before building any structural fix.
  • Never go it alone: check with all agencies and follow environmental rules. Where a third party causes the instability (an upstream hydro dam, for example), the cost may shift to them.
Stabilizing a failed road fill slope in Fergus County, MT
Photo 6.3.12-1. Stabilizing a failed road fill slope in Fergus County, MT. (Photograph courtesy of Soil Nail Launcher, Inc., from www.soilnaillauncher.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Completed soil nail slope near Lake Tahoe
Photo 6.3.12-2. Completed soil nail slope near Lake Tahoe. (Photograph courtesy of Landslide Solutions, Inc., from www.landslidesolutions.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Carefully sculpted and stained shotcrete finish
Photo 6.3.12-3. Carefully sculpted and stained shotcrete finish, Del Norte Bluff. (Photograph courtesy of Del Norte County, from www.soilnaillauncher.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Installation of corrosion resistant fiberglass launched soil nails
Photo 6.3.12-4. Installation of corrosion resistant fiberglass Launched Soil Nails™, Del Norte Bluff. (Photograph courtesy of Soil Nail Launcher, Inc., from www.soilnaillauncher.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Shotcrete installation, all work done from above
Photo 6.3.12-5. Shotcrete installation, all work is being done from above, Del Norte Bluff. (Photograph courtesy of Soil Nail Launcher, Inc., from www.soilnaillauncher.com.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Bench and Dump Slope Stability Monitoring
Bench and Dump Slope Stability Monitoring
Figure 6.3-26. Key rock berm through slide muck with a subdrain.
Figure 6.3-26. Key rock berm through slide muck with a subdrain.
Figure 6.3-27. What to avoid: riprap and fill stockpiled at the top of an unstable slope.
Figure 6.3-27. What to avoid: riprap and fill stockpiled at the top of an unstable slope.
Figure 6.3-28. Air-dump cars unloading fill for slope reconstruction.
Figure 6.3-28. Air-dump cars unloading fill for slope reconstruction.
Figure 6.3-29. A proposed 6-ft track shift away from a slide.
Figure 6.3-29. A proposed 6-ft track shift away from a slide.
Figure 6.3-30. What not to do: sheepsfoot roller on saturated silt and clay.
Figure 6.3-30. What not to do: sheepsfoot roller on saturated silt and clay.

One slide in western Canada (April 2013) is typical of most slides seen along the track. Snowmelt ran down small gullies, disappeared into the fill, raised pore pressure and took out the embankment. The repair keyed in a toe, rebuilt a 2:1 slope about 50 ft high from air-dumped fill, and added culverts.

After Geotechnology for Railroaders Program, Module 6.1, Module 7.1; Module 6.1 §02–04; Module 7.1 §05. Full reference under Supplemental References.

Project management · Swearingen (n.d.)

PERT Three-Point Estimates and the Probability of Finishing a Slope Repair Before a Deadline

PERT handles uncertain durations by asking for three estimates per activity: optimistic a, most likely m and pessimistic b. A beta distribution gives the expected time t = (a + 4m + b) ÷ 6 and variance σ² = [(b − a) ÷ 6]². A forward pass gives the early start and finish (ES = largest EF of the predecessors; EF = ES + t), and a backward pass gives the late times (LF = smallest LS of the successors; LS = LF − t). Slack is LS − ES; activities with zero slack form the critical path. Project variance is the sum of the variances of the critical activities. Treating completion time as normally distributed, the probability of finishing by deadline D follows from Z = (D − T) ÷ σ.

Activity-on-node network for the worked example with early and late times; the critical path A–C–E–G–H totals 15 weeks.
Figure 13-PM1. Activity-on-node network for the worked example with early and late times; the critical path A–C–E–G–H totals 15 weeks. Source: Swearingen (n.d.), Slide PMT-30.

Table 13-PM1. Worked example time estimates, weeks (after Swearingen n.d., slide PMT-17)

Activityambtσ²Slack
A12320.110
B23430.111
C12320.110
D24640.441
E14741.000
F12931.786
G341151.780
H12320.110

In the slides’ example, a foundry has 16 weeks to install a pollution-control system. The critical path A–C–E–G–H gives T = 15 weeks with variance 3.11, so σ = 1.76 weeks. Then Z = (16 − 15) ÷ 1.76 = 0.57, which corresponds to about a 71.6% chance of meeting the deadline.

For railroad work: slope repairs often have to be finished before a wet season, a freeze-up or a planned outage. Use wide pessimistic estimates for activities controlled by subsurface conditions, such as soldier pile or anchor drilling in uncertain rock, dewatering, or excavation below the slide plane. Use narrow ranges for routine tasks. If the computed probability is low, change the plan (more rigs, a second shift, a staged repair that restores track first) instead of only reporting the risk. The method assumes a single critical path. Where a near-critical path also carries large variance, the true chance of finishing on time is lower than the calculation shows, so check those paths as well.

Figure 6.3-31. Work train delivering rock fill to a slope repair.
Figure 6.3-31. Work train delivering rock fill to a slope repair.

Source: Swearingen, J. (n.d.). The Basics of Project Management Techniques [lecture slides PMT-1 to PMT-40; author from document properties], slides PMT-13 to PMT-34. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Example 6.3-4: Probability of Finishing a Repair by a Deadline (PERT)

The Swearingen example of Table 13-PM1. PERT turns three duration estimates per activity into an expected duration and a variance, and the critical path into a probability of meeting a deadline.

A1/2/3C1/2/3E1/4/7G3/4/11H1/2/3Critical path (a / m / b, weeks)Deadline: 16 weeksTE = ? σ = ? P(T ≤ 16 wk) = ?GivenA, C, H: 1 / 2 / 3 wkE: 1 / 4 / 7 wkG: 3 / 4 / 11 wkDeadline 16 weeksRequiredExpected duration TE Standard deviation σProbability of meeting deadlineBlack = given; red = required
Given and required for Example 6.3-4.

Given

VariableValueDescription
Critical pathA–C–E–G–HFigure 13-PM1
EstimatesA 1/2/3; C 1/2/3; E 1/4/7; G 3/4/11; H 1/2/3 weeksa / m / b
Deadline16 weeks

Required

  • Expected duration and standard deviation of the critical path
  • Probability of meeting the deadline

Equations

  1. Eq. 1: t = (a + 4m + b)/6; σ² = [(b − a)/6]² — per activity
  2. Eq. 2: T = Σt; σT = √Σσ² — critical path
  3. Eq. 3: Z = (deadline − T)/σT; P = Φ(Z) — normal distribution

Steps

Step 1 · Activities (Eq. 1)
t = 2, 2, 4, 5, 2 weeks; σ² = 0.11, 0.11, 1.00, 1.78, 0.11
↓
Step 2 · Path (Eq. 2)
T = 15 weeks; Σσ² = 3.11
σT = 1.76 weeks
↓
Step 3 · Probability (Eq. 3)
Z = (16 − 15)/1.76 = 0.57
P ≈ 72%
↓
Solution
T = 15 weeks; about a 72% chance of finishing in 16.

Solution

Expected duration 15 weeks with σ = 1.76 weeks; about a 72% chance of finishing within 16 weeks.

Activity G contributes over half the variance; narrowing its range (by investigating the ground it depends on, for example) raises the probability more than shortening any other activity. On slope repairs before a wet season, use wide pessimistic estimates for work controlled by subsurface conditions.

Project management · Cretu et al. (2011)

Eliciting Expert Ranges: Overconfidence, Anchoring and Motivational Bias

Slope design relies on expert judgment wherever data are thin, for example in the location of the failure surface, residual strength, piezometric level or the effect of a drainage fix. Cretu et al. summarize the cognitive biases that distort such judgments and how a facilitator can counter them. The overconfidence effect is the tendency to give ranges that are too narrow. One study they cite asked seven very experienced geotechnical engineers to bracket the embankment height that would fail a clay foundation, using bounds intended to have a 50 percent chance of containing the true value. None of the seven ranges captured the actual failure height. Anchoring means that the first number spoken pulls later estimates toward it. Availability means that vivid recent events seem more probable than they are. Motivational bias covers people shading estimates to protect a past position, a budget or a client relationship, and subordinates deferring to superiors in the room. Optimism bias covers people underrating threats on projects they control.

Figure 6.3-25. A counter berm; a flat plateau is enough.
Figure 6.3-25. A counter berm; a flat plateau is enough.

The authors give these countermeasures. Explain the biases to the group before eliciting values. Ask for the worst credible outcome first, then the best case (which may not be “nothing”), then the most likely. Push explicitly for wider bounds. Collect estimates from junior staff or consultants separately and present them to management anonymously. Show the resulting distribution on screen so the experts can confirm that it says what they meant. Base estimates on personal experience, lessons learned, outside expert opinion and empirical records, and use the empirical records first when they exist.

For railroad work: When back-analysis or design inputs rest on judgment, run a short structured elicitation and document it. This applies to the depth of a slip surface between inclinometer readings, the residual friction angle of a slickensided clay, or the water level to assume for a ditch-line slide. Ask for the worst credible case first, record low/most-likely/high values with their reasons, and carry the full range into sensitivity or probabilistic stability runs. A single “engineering judgment” value tends to understate the uncertainty in the factor of safety. Railroad staff who have watched a site for years are valuable sources. Interview them separately from their managers, and treat their recollection of the last movement as an anchor to test, not a bound.

Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 111–121. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Jacob and Müller (2017)

Repricing Changed Work from the Original Bid Build-Up

Jacob and Müller show how a change is priced when the work as bid cannot be performed as described. The approach is not to negotiate a new lump sum. Instead, the original bid calculation is reopened, and only the parts of the item that changed are replaced. The original surcharge rates are kept.

In their example, half of a 131,000 CY excavate-haul-place item (65,400 CY) turns out to be contaminated. That portion must go to an owner-designated disposal site instead of into the on-site fill. The changed item is rebuilt as follows:

  • loading stays, but at 70% of the original productivity, which raises the excavator cost per CY by 43%;
  • the on-site haul is replaced by an external haul quote that includes weighing and road fees;
  • placement and compaction are removed;
  • fine grading is unchanged;
  • the original 20% surcharges are applied.

The new unit price came out about 3% above the original. The change can be paid either as a new item or as a price difference applied to the affected quantity. The authors prefer the difference method, because it shows exactly which costs were added and which were dropped.

They also list follow-on effects that may need their own pricing:

  • more testing;
  • more surveying and billing, because the quantity has to be measured in two parts;
  • import of replacement fill for the volume that is no longer placed;
  • a possible productivity loss on the remaining uncontaminated material.

Underlying this is their split between time-variable and time-fixed site costs.

  • Time-variable costs include equipment ownership and standby, site supervision, site offices and traffic control. They grow with duration.
  • Time-fixed costs include mobilization, setup and removal of facilities, engineering, testing and waste disposal. They do not grow with duration.

Keeping the two separate in the estimate is what makes delay and disruption costs calculable later.

For railroad work: Embankment and slide repairs regularly reveal conditions that change the work after award. Examples are contaminated or fouled-ballast spoil that cannot be reused, deeper failure surfaces, and wet borrow. Repricing from the contractor’s bid build-up only works if the contract requires that build-up to be submitted or escrowed. It also needs bid items split finely enough (excavation, haul, placement, disposal) to be reopened. For delay caused by lost track windows or a slower restoration of track speed, price the time-variable site costs per day in advance. That gives the railroad and contractor an agreed basis for standby and extension costs.

Source: Jacob, D. and Müller, C. (Eds.) (2017). Estimating in Heavy Construction: Roads, Bridges, Tunnels, Foundations. Berlin: Ernst & Sohn, pp. 12–14, 205–208. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Pratt (2011)

Quantifying a Slide Repair: Section and Grid Methods for Cut and Fill

Pratt sets two rules for measuring earthwork. First, measure in bank measure: the actual in-place dimensions, with no allowance for swell or compaction. Those factors are applied later, when the work is priced. Second, keep each excavation category and each material separate, and measure disposal of surplus as total excavation minus common backfill.

He gives two manual methods for volumes. The grid method takes the cut or fill depth at each grid node and weights it by the area that node represents: one quarter-cell at a corner, two on an edge, and four in the interior. The section method suits long, narrow work such as road and railroad construction. Cross sections are plotted at regular stations, the cut and fill areas are measured at each section, and the volumes come from the average-end-area relation:

Pratt’s section-method example: plan contours and cross sections at 20-ft stations, each annotated with its cut and fill area.
Figure 13-PM2. Pratt’s section-method example: plan contours and cross sections at 20-ft stations, each annotated with its cut and fill area. Source: Pratt (2011), Figure 4.3.

V = station spacing × (A1/2 + AN/2 + sum of the intermediate areas)

His example uses five stations 20 ft apart. The cut areas are 108, 40, 73, 91 and 0 ft², and the fill areas are 245, 248, 195, 195 and 328 ft². That gives 5,160 ft³ (191 CY) of cut and 18,490 ft³ (685 CY) of fill. All the cut is reused, so about 494 CY of fill must be imported. Accuracy depends mainly on how faithfully the section profiles are plotted, and closer station spacing improves it.

For railroad work: a slide or washout repair is a short, long-and-narrow job of exactly this kind. A reasonable procedure is:

  1. Cut sections perpendicular to the track at a regular spacing from the survey or LiDAR surface. Add extra sections at the head scarp, the toe and any culvert.
  2. On each section, plot the existing ground, the interpreted slip surface, and the repair geometry: removal limits, keyway, benches and buttress.
  3. Tabulate the areas separately for removal of slide debris, excavation into competent material for the key, granular buttress or rock fill, and select embankment fill.

Each material has its own swell and compaction behavior and its own haul. Report the volumes in bank measure, state the section spacing and the survey date, and keep the section sheets in the calculation appendix. A slide that is still moving changes the existing-ground line, so the quantities will need updating before the bid.

Source: Pratt, D. J. (2011). Fundamentals of Construction Estimating, 3rd ed. Clifton Park, NY: Delmar Cengage Learning, pp. 57, 59–64. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.