6.3.11 Worked Calculation Examples

Slope stability governs the design of railroad embankments, cut slopes, and side-hill fills across railroad networks.
Authors: Daniel P. Colwell and Mario Ruel
6.3.11 Worked Calculation Examples
The examples cover the three stability checks a railroad engineer runs most often: a circular slip through a fill and its foundation, undrained stability of a fill on soft clay, and a cut in strain-softening clay shale. Each is laid out as Given, Required, Equations, a flow chart of the steps with a spot check at each, and the Solution.
Example 6.3-1: Bishop Simplified Analysis of One Trial Circle

A 20-ft fill is proposed over residual clay derived from shale on a Class I railroad located in West Virginia. The example works one trial circle by hand with five slices, to show the mechanics of the Bishop method and why it must be iterated; a program then searches hundreds of circles for the critical one.

TrackFill: c′ = 100 psf, φ′ = 30°, γ = 120 pcfFoundation: c′ = 200 psf, φ′ = 22°, γ = 115 pcftrial circle, R = 38 ft12345phreatic surfaceFS = ?Givenb = 6, 8, 8, 8, 6 ftW = 2,880; 11,520; 17,464; 12,880; 4,140 lb/ftα = −15, 0, 12, 28, 42°u = 0, 0, 375, 624, 0 psfSlices 1–2 in fill; 3–5 in foundationTarget FS ≥ 1.5RequiredFS of the trial circle(Bishop simplified)Black = given; red = required
Given and required for Example 6.3-1.

Given

VariableValueDescription
Fillc′ = 100 psf, φ′ = 30°, γ = 120 pcfSlices 1 and 2
Foundationc′ = 200 psf, φ′ = 22°, γ = 115 pcfSlices 3 to 5
Slicesb = 6, 8, 8, 8, 6 ft; W = 2,880, 11,520, 17,464, 12,880, 4,140 lb/ft; α = −15°, 0°, 12°, 28°, 42°Trial circle R = 38 ft
u0, 0, 375, 624, 0 psfPhreatic surface at one-third height
TargetFS ≥ 1.5 (assumed owner requirement)

Required

  • FS of the trial circle

Equations

  1. Eq. 6.3-1: FS = Σ{[c′b + (W − ub) tanφ′] / mα} / Σ W sinα — Bishop simplified
  2. Eq. 6.3-2: mα = cosα [1 + tanα tanφ′ / FS] — FS appears on both sides, so iterate

Steps

Step 1 · Driving term
−746 + 0 + 3,633 + 6,041 + 2,770
ΣW sinα = 11,698 lb/ft
↓
Step 2 · Numerators c′b + (W − ub) tanφ′
600 + 1,662; 800 + 6,647; 1,600 + 5,835; 1,600 + 3,191; 1,200 + 1,673
2,262; 7,447; 7,435; 4,791; 2,873 lb/ft
↓
Step 3 · First pass with FS = 1.52 (Eq. 6.3-2)
mα = 0.867, 1.000, 1.034, 1.008, 0.921; Σ(Num/mα) = 25,120
FS = 25,120 / 11,698 = 2.15
↓
Step 4 · Iterate
Use FS = 2.15 in mα; repeat
Converges to FS = 2.18
Spot check: Second pass gives 2.181; third 2.183. Bishop converges in two or three passes.
↓
Solution
Trial circle FS = 2.18; the critical circle will be lower.

Solution

FS = 2.18 for this trial circle.

The trial value is not the design answer. The critical circle, found by moving the center and radius in a program such as SLOPE/W or SLIDE, gives the minimum, and that is what is compared with 1.5. The hand calculation is worth doing once per project to check the program’s slice forces and pore pressures; submit the search output for independent review where the owner railroad requires it.

Example 6.3-2: End-of-Construction Stability on Soft Clay

A siding extension on a Class I railroad located in Washington puts 12 ft of fill with 1.5H:1V slopes on soft saturated fat clay. At the end of construction the clay is undrained, so the analysis uses su with φ = 0, and both the slope and the bearing capacity of the base are checked.

H = 12 ftFill γ = 120 pcfSoft clay: su = 700 psfFS = ?GivenH = 12 ft; γfill = 120 pcfsu = 700 psfClay γ = 103 pcf; deep firm layerSlope 1.5H:1V (β ≈ 34°)Ns = 5.52 (Taylor)Target FS ≥ 1.4RequiredSlope FSBase FS (Taylor Ns = 5.52)Change if su = 300 psfBlack = given; red = required
Given and required for Example 6.3-2.

Given

VariableValueDescription
H12 ftFill height
γfill120 pcf
Claysu = 700 psf; γ = 103 pcfSoft CH
Slope1.5H:1V (β ≈ 34°); deep firm layer
Ns5.52Taylor chart (Coduto 2001)
TargetFS ≥ 1.4 at end of construction (assumed)

Required

  • Slope and base factors of safety
  • What changes if su were 300 psf

Equations

  1. Eq. 6.3-14: FS = Ns su / (γ H) — Taylor stability number, φ = 0
  2. Eq. 2: FSbase = 5.14 su / (γfill H) — bearing capacity of the base

Steps

Step 1 · Slope (Eq. 6.3-14)
5.52 × 700 / (120 × 12) = 3,864 / 1,440
FS = 2.68
↓
Step 2 · Base (Eq. 2)
5.14 × 700 / 1,440 = 3,598 / 1,440
FSbase = 2.50: governs
↓
Step 3 · Sensitivity: su = 300 psf
5.52 × 300 / 1,440; 5.14 × 300 / 1,440
1.15 and 1.07: both below 1.4; staged construction needed
↓
Solution
FS = 2.50 (base governs) at su = 700 psf.

Solution

The slope gives FS = 2.68 and the base FS = 2.50, so base capacity governs; both exceed 1.4.

Taylor’s chart assumes a homogeneous slope, so it is an approximation here. The result depends directly on su: at 300 psf the embankment would need staged lifts with piezometers and settlement plates (Chapter 5.3). Confirm the strength with at least two CPTu soundings at each embankment over about 8 ft high on soft ground; zones below 500 psf call for staging.

Example 6.3-3: Clay Shale Cut With Peak and Residual Strength

A 25-ft cut in Cretaceous clay shale on a Class I railroad main line located in Saskatchewan. Clay shale cuts often stand at first and then fail as the shale softens toward its residual strength, so the cut is checked at both strengths for a shallow slide parallel to the face.

z = 4 ftβ = 26.6° (2H:1V)FS on slip plane = ?water at surfaceGivenPeak: c′ = 300 psf, φ′ = 22°Residual: c′r = 0, φ′r = 9°γsat = 130 pcf; γ′ = 67.6 pcfWater at the surface (worst case)RequiredFS at peak and at residualSlope for FS = 1.2 at residual, wet and drainedBlack = given; red = required
Given and required for Example 6.3-3.

Given

VariableValueDescription
Peakc′ = 300 psf, φ′ = 22°
Residualc′r = 0, φ′r = 9°Ring shear
γsat130 pcf; γ′ = 67.6 pcf
Slope2H:1V, β = 26.6°
z4 ftDepth of the shallow slide
WaterAt the surface (worst case)

Required

  • FS at peak and at residual strength
  • Slope angle for FS = 1.2 at residual, wet and drained

Equations

  1. Eq. 6.3-15: FS = [c′ + γ′ z cos²β tanφ′] / (γsat z sinβ cosβ) — infinite slope, seepage parallel with the water table at the surface
  2. Eq. 2: tanβ = (γ′/γsat) tanφ′r / FS (wet); tanβ = tanφ′r / FS (drained) — c′ = 0

Steps

Step 1 · Driving stress
130 × 4 × 0.447 × 0.894
207.8 psf
↓
Step 2 · Peak (Eq. 6.3-15)
[300 + 67.6 × 4 × 0.797 × 0.404] / 207.8 = 387.1 / 207.8
FS = 1.86
↓
Step 3 · Residual (Eq. 6.3-15)
[67.6 × 4 × 0.797 × 0.158] / 207.8 = 34.2 / 207.8
FS = 0.17
↓
Step 4 · Slope for FS = 1.2 (Eq. 2)
Wet: (67.6/130)(0.158)/1.2 = 0.069; drained: 0.158/1.2 = 0.132
β = 3.9° (about 14.5H:1V) wet; 7.5° (about 7.5H:1V) drained
↓
Solution
FS = 1.86 at peak but 0.17 at residual.

Solution

FS = 1.86 at peak strength but 0.17 at residual. At residual, FS = 1.2 needs a slope of about 14.5H:1V wet or 7.5H:1V fully drained.

Neither slope is practical for a 25-ft cut. Residual strength governs only where a shear surface already exists (Section 6.3.6); where none is found, check first-time sliding with the fully softened strength and design with drainage (horizontal drains), berms or reinforcement. Instrument clay shale cuts deeper than about 15 ft with survey monuments and inclinometers, read at least annually.